  511   Monday, September 28, 2020, 09:36 John WongNb TARGET BOATDoneHeat Treatment of Nb for Edward

Darwin Ortiz Rosales wrote:

Friday, September 25, 2020, 10:30 

Target boat with a layer of niobium foil on the bottom is used to heat up Nb samples to 1400 C for 4 hrs.

OMEGA slope = 0.99

The niobium samples are wrapped in two layers of  Nb foil.

Boat is wrapped with 2 layers of Ta foil, careful to avoid touching samples.


 Friday, September 25, 2020, 10:35
Manually ramped TGHT to 40 A and kept at that current for approximately 15 minutes.  
Then started autoramp at  1A/min up to 100 A

 Friday, September 25, 2020, 16:58
IPG1= 4.7e-07 Torr
TGHT =100.0 A, 1.3 V
Start autoramp to TGHT to 300 A  @ 2A/min

 @ 300A temperature = 1179 C
 

Friday, September 25, 2020, 20:00 

autoramp to 345 A


 Friday, September 25, 2020, 20:39

TGHT = 345 A, 5.4 V

OMEGA = 1296 C

IPG1= 8.1 e-07 Torr

Ramp manually to 1400 C


 Friday, September 25, 2020, 20:51

reached 1400 C on OMEGA at TGHT = 476 A


Friday, September 25, 2020, 20:59

OMEGA increased to 1410, lowered TGHT to 468 A to get back to 1400 C on OMEGA 


Friday, September 25, 2020, 21:40

Lowered TGHT to 463 A,  5.79 V to bring OMEGA to 1400 C from 1404 C


 Saturday, September 26, 2020, 00:51

Sample has been at 1400 C for 4 hours.

IGP1= 7.2 e-07 Torr

Cooling at- 2A/min

 

 

 Monday, September 28, 2020, 09:36

Vented chamber - for Darwin.


 

  96   Thursday, November 07, 2013, 09:38 Anders Mjos   Problems resolvedHeat Shield cooling line twisted

See attached photo.

The Heat Shield has been taken to the Machine Shop for repair.

Friday, November 08, 2013

 The Heat Shield cooling line has been repaired and the lid re-installed in the evaporator. Photo attached.

Friday, November 08, 2013, 10:58 : Roughing Started

Friday, November 08, 2013, 11:05: Turbo started 

Friday, November 08, 2013, 11:15: Turbo at speed Vacuum at (IGP1) 5.7E-5 T 

Attachment 1: Twisted_Tube.jpg
Twisted_Tube.jpg
Attachment 2: Twisted_Tube_Repaired.jpg
Twisted_Tube_Repaired.jpg
  444   Tuesday, May 21, 2019, 14:34 Aaron Schmidt    HS swap to EVAP 2 flex line.

 Tuesday, May 21, 2019, 14:33: Install flexible line evap 2 HS.

  406   Wednesday, April 25, 2018, 07:21 Aaron Schmidt   DoneHS swap evap 2

Wednesday, April 25, 2018, 07:05: TGHT & TBHT off

Wednesday, April 25, 2018, 07:15: BV1 & TP1 off

Wednesday, April 25, 2018, 07:17: PV1 & BP1off

Wednesday, April 25, 2018, 07:19: Begin venting

Wednesday, April 25, 2018, 07:22: Full venting.

Wednesday, April 25, 2018, 07:29: HS waterlines purged.

Wednesday, April 25, 2018, 07:48: Aurelia's test ta target assembly was removed. The blank target heating heat shield for evap 2 was reinstalled. shields in but empty.

Evap 2 Doors closed.

  459   Thursday, September 26, 2019, 14:03 Aaron SchmidtNb41882-3TARGET BOATIn progressHS swap & test Nb target

 HS# 42752-7

Thursday, September 26, 2019, 13:46: Remove Flexible lines HS

Thursday, September 26, 2019, 14:03: Assy installed.


Friday, September 27, 2019, 07:07: Vacuum @ 1.16e-06T. 

Friday, September 27, 2019, 07:09: Waterlines opened. Vacuum stable @ 1.15e-06T 


Monday, September 30, 2019, 10:04: Remove Nb target & assy. Install flexible line HS. 

  518   Friday, October 16, 2020, 16:31 Luca EgoritiEmpty TARGET BOATIn progressHPOG annealing

Friday, October 16, 2020, 11:30

 Target mounted in EVAP2. Pump down started

Friday, October 16, 2020, 12:05

Pressure goes up. Checked with Ferran and he says that the valve IEVAP2:RV1 automatically closes sometimes. WEIRD, to be chacked.

Friday, October 16, 2020, 15:20

IGP2 bottoms at 0.2T, and doesn't increase recover if I close RV1 while it shouldn't (as shown before). --> Vented to restart from scratch

 

Friday, October 16, 2020, 15:45

 

Pumped down again, vacuum went down to 0.16 and then started raising until ~0.18. This time the valve was open indeed! opening and closing the valve had no effect on the vacuum as if the  booster pump was not effective

 

 

Friday, October 16, 2020, 16:27

Tried a THIRD time, this time effectively, to turn the turbo ON. I managed to, but the turbo makes weird spinning sounds every ~30 sec. Moreover, its pumping down plot seems quite weird  - see spike UP while pumping. Could it be related to a dysfunction of the backing pump?

 

  521   Monday, November 02, 2020, 18:32 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneHEA heat treatment

2020-11-02 6:32: roughing on

2020-11-02 7:21: Turbo on for a while, IGP1:1.8e-5T . water leak check ok.

2020-11-02 7:47: IGP1:1e-5T . Ramping up target heater to 200A, 1A/10s.

2020-11-02 7:47: TGHT at 275A, pyrometer at 1300degC. Leaving it hot for 24h.

 2020-11-04 9:06: After 37h treatment, ramping down to 0A.2A/10s.

2020-11-04 9:46: target ramped down. Venting.

2020-11-04 17:30: Big amounts of outgassing non detected in GP1 coated some inner walls in evap2. The walls got cleaned with acetone. All as before now.

 

 20201104_102925.jpg

Attachment 2: 20201104_144831.jpg
20201104_144831.jpg
  636   Tuesday, June 06, 2023, 09:14 Darwin Ortiz RosalesC44139-4TARGET BOATDoneGraphite inside insert Experiment 2 (regular formulation discs)

Tuesday, June 06, 2023, 09:11

A Ta container tube was wrapped with 4 Ta heatshields.  Note final container is 45220-6

272 graphite discs were loaded.

a TaC coated Ta spring at the front end.

The system was left to establish vacuum over previous night.

Good vacuum set to5e-04Torr

Bad vacuum was set to 5e-2 Torr

Total weight of system including spring= 253.94 g

OMEGA slope = 0.99

The target will be heated to ~2000 C, held there for 10 hours. 

Initial ramp at 1A/min to 200A

Then ramp at 0.5A/min while taking temperature readings periodically unti l250A.

At 250 A will let pressure stabilize and then ramp at 1A/min to 2000C or 480A.  Will use read back current

Will hold at target Temperature or Current for 10 hours before starting ramp-down.


Tuesday, June 06, 2023, 09:14

 Starting ramt at 1A/min

initial IGP1= 8.2e-07


Tuesday, June 06, 2023, 21:25

@480 A on readback, 1823C on OMEGA.  ramping to 510A set point which should be around 490 RD.  (see heating profile for details)


Tuesday, June 06, 2023, 22:02

ramped to 516 on RD 527 on set.  Will leave for 10 hours

OMEGA =1930 C

 


Wednesday, June 07, 2023, 06:32

OMEGA at 1950 C this morning.  Will continue heating.  Lowered to 1940 C as in experiment 1 this was the top temperature.


Wednesday, June 07, 2023, 07:40

OMEGA= 1940 C

IGP1=1.7-6 Torr

TGHT= 513A, 9.4V

starting ramp down at -2A/min

  634   Wednesday, May 24, 2023, 15:23 Darwin Ortiz Rosales 44139-4LP TUBEDoneGraphite inside insert Experiment 1

 

Wednesday, May 24, 2023, 15:22

A Ta container tube was wrapped with 4 Ta heatshields.  Note final container is 45220-11

219 graphite discs were loaded.

a TaC coated Ta spring at the front end.

The system was left to establish vacuum over previous night.

Good vacuum set to5e-04Torr

Bad vacuum was set to 5e-2 Torr

Total weight of system including spring= 250.1 g

OMEGA slope = 0.99

The target will be heated to 2000 C, held there for 10 hours. 

Initial ramp at 1A/min to 200A

Then ramp at 0.5A/min while taking temperature readings periodically unti l250A.

At 250 A will let pressure stabilize and then ramp at 1A/min to 2000C or 450A.  

Will hold at target Temperature or Current for 10 hours before starting ramp-down.


 Wednesday, May 24, 2023, 15:50

Currently heating at 0.5A/min to250A.  Taking temperature/current measurements

IGP1= 1.06e-06 Torr


Wednesday, May 24, 2023, 18:28

heating at 1A/min to 275A to collect more temperature data


Wednesday, May 24, 2023, 19:22

Slight offset between set and RD current observed. 

Ramping at 1A/min to 440A according to the regression below

Should be around 2000 C.


Wednesday, May 24, 2023, 20:22

Currently at 339 A, 4.8V

OMEGA = 1614 C, IGP1= 2.04e-06 Torr

Will ramp up at 2A/min to 450A as new data point suggests


Wednesday, May 24, 2023, 21:05

1730 C   411.0 A 6.9 V

heating curve has new slope suggesting 500A as minimum to reach 2000 C

Increasing ramp to 1A/10s to reach 450A


Wednesday, May 24, 2023, 21:17

TGHT

1804 C   441.0 A 7.4 V

IGP1= 3.9e-06 Torr

Continue ramping to 480A


Wednesday, May 24, 2023, 22:11

Offset between setpoint of current and readback.  readback 10A below. 

1941 C   480.0 A 8.5V

Will keep at this setting until 7:30 am tomorrow then start ramp down @-2A/min


Thursday, May 25, 2023, 07:25

OMEGA=1912C, IGP1 =1.29e-06 Torr, TGHT = 480A, 9.0V

begin ramp down at -2A/min


Thursday, May 25, 2023, 09:52

Some odd current readback behaeviour noticed.  Have contacted Gelo from controls.  He will look at it next week.  Discrepancy between read back and set point and drop in read back currrent. See picture

 

 

Attachment 1: Screenshot_Graphite_insert_Exp1.png
Screenshot_Graphite_insert_Exp1.png
  430   Wednesday, February 13, 2019, 10:08 Darwin Ortiz Rosales 43630-1  DoneGraphite insert test 3b

 Wednesday, February 13, 2019, 10:04

A previously coated tantalum tube with 3 layers of shielding (Details in e-log 426) was loaded with a graphite insert. 

The tube was loaded in evaporator 2 and pumped down

The graphite insert will be heated to 2000 C for 1 week

IGP1=1.37e-07 Torr


 Wednesday, February 13, 2019, 10:27

IGP1= 1.46e-07 Torr

Manual tapping to 40A on TGHT

TGHT 40.7A, 0.104V

Autoramp started at 1A/min up to 400 A

Good Vacuum = 3.00e-05, Bad Vacuum = 5.00e-05


 Thursday, February 14, 2019, 08:42

IGP1= 2.2e-07 Torr, T=1705 C, TGHT 401A, 6.7 V

Manually tapping to 2000 C (Slow ~1 A/min) in 5 A increments followed by waiting for equillibrium


Thursday, February 14, 2019, 10:54

IGP1 = 1.4e-06 Torr, T = 2003 C, TGHT 500A, 9.1 V

Waiting for equillibrium

manually tapped TGHT to 503A,  T = 2003 C

Will leave for 1 week


Wednesday, February 20, 2019, 08:44

 IGP1= 1.37e-07 Torr, T=1943 C, THGT= 503 A, 8.9 V

Ramp-down @ 2A/min

 


Wednesday, February 20, 2019, 14:02  

1 hour since TGHT = 0 A

Venting will proceed.


 

  437   Sunday, April 07, 2019, 08:13 Marla Cervantes 43630-5 DoneGraphite insert test #5

 Sunday, April 07, 2019, 08:10

A graphite insert (with conical caps) was loaded in tantalum tube previously coated with TaC,

and wrapped with 3 tantalum foils,

a tanalum cap was inserted in one side of the Ta tube and sealed.

The tube was set in the EVAP2 and the furnace was pumped down.

IGP1 = 1.24e-7 Torr.

The current was tapped to 40 A

Autoramp was set to 1 A/min to 300 A.


At TGHT 335.53 S, 5.28 V the temperature was 1560

The autoramp was set to 450 A.


At TGHT 474.75 S, 7.96 V the temperature was 1560

The autoramp was set to 450 A.


To reach 2000 C, TGHT = 500.25 A, 8.45 V.

After 1hr the temperature stabilized to 1959 C

and the  current was increased to TGHT = 510.28 A, 8.64 V.

After stabilization the temperature reached 2010 C.

The current was decreased to TGHT = 503.15 A, 8.45 V

and the temperature stabilized to 2001 C.


The voltage increased  unexpectedly to 8.89 V and the temperature increased to 2055,

the current was reduced to keep the tube at 2000 C.

The voltage kept increasing and we kept decreasing the current to keep the tube at 2000


The final current before venting and getting out the container was

TGHT = 466.219 A and 8.467 V.


Test result: Broken tantalum tube.

Attachment 1: 190407-GraphiteInsertTest.pdf
190407-GraphiteInsertTest.pdf
Attachment 2: V1.JPG
V1.JPG
Attachment 3: V2.JPG
V2.JPG
Attachment 4: 20190415_170133.jpg
20190415_170133.jpg
  433   Wednesday, March 13, 2019, 15:43 Marla Cervantes 43630-6 DoneGraphite insert test #4

 Wednesday, March 13, 2019, 15:41

An uncoated tantalum tube was loaded with a graphite insert (with conical caps).

3 tantalum foils were wrapped around the tantalum tube and a Ta cap was added.

EVAP2 is currently pumping down

The tube will be hated for 5 days at 2000 C


Thursday, March 14, 2019, 10:07

IGP1 = 5.37e-7 Torr

The TGHT will be tapped manually to 50 A  

After aprox 1 hour IGP1 = 5.08e-7 Torr, TGHT=46.5 A, 0.224 V

Autoramp is set to 1A/min to 300 A

 Autoramp is set to 1A/min to 450 A

Autoramp was stopped at 425 A when 2000 C were achieved


 Sunday, March 17, 2019, 00:25

IGP1 = 2.03e-7 Torr

TGHT=424.2 A, 7.117 V, temp 1976 C


Sunday, March 17, 2019, 15:04 

IGP1 = 21.6e-7 Torr

TGHT=424.1 A, 7.085 V, temp 1967 C

cooling down -1 A/min

  428   Wednesday, January 23, 2019, 13:06 Marla Cervantes 43630-2 DoneGraphite insert test #3

 Wednesday, January 23, 2019, 13:01

A previously coated tantalum tube with 3 layers of shielding (Details in e-log 426) was loaded with a graphite insert. 

The tube was loaded in evaporator 2 and pumped down

The graphite insert will be heated to 2000 C for 3 weeks


 Thursday, January 24, 2019, 10:04

Pressure = 3.66e-7 Torr

TGHT manually tapped to 45 A

Final pressure = 3.8e-7 Torr

Set autoramp to 350 A @ 2A/min

TGHT = 1643 C

Set autoramp to 400 A @ 2A/min

TGHT = 1790 C

Started to tapped manually at approx 5 A every 30 s

Final TGHT => 1896 C, 8.16 V, 480.46 A

The current will stay at 480 A until temperature stabilizes. 

The current was reduced to 476 A to stay at 1900 C


Friday, January 25, 2019, 17:16

Pressure = 3.22e-7 Torr

TGHT = 8.17 V, 477.65 A, 1882 C 


Monday, January 28, 2019, 09:09 

Pressure = 1.67e-7 Torr

TGHT = 8.07 V, 477.65 A, 1859 C 

The temperature readings are fluctuating between 1880 and 1859 C


Tuesday, January 29, 2019, 07:32

Pressure = 1.55e-7 Torr

TGHT = 8.17 V, 477.75 A, 1880 C 


Tuesday, January 29, 2019, 11:34

 Pressure = 1.55e-7 Torr

TGHT = 8.27 V, 477.56 A, 1897C 


Tuesday, January 29, 2019, 12:47 

 Pressure = 1.53e-7 Torr

TGHT = 8.19 V, 477.75 A, 1899C 


Tuesday, January 29, 2019, 13:38

 Pressure = 1.55e-7 Torr

TGHT = 8.25 V, 477.75 A, 1905C


Thursday, January 31, 2019, 16:12  

 Pressure = 1.40e-7 Torr

TGHT = 8.4 V, 476.81 A, 1918C


Thursday, January 31, 2019, 22:32

Pressure = 1.39e-7 Torr

TGHT = 8.37 V, 476.71 A, 1914C

The current will be ramped down @1 A/min


Friday, February 01, 2019, 09:58

 Last 22 A tapped to 0 manually

Tantalum tube was removed from the EVAP2

  424   Thursday, November 22, 2018, 10:19 Marla Cervantes 43630-7  DoneGraphite insert test #2

 Thursday, November 22, 2018, 10:12

A previously sintered tantalum tube with 3 layers of shielding was loaded with a graphite insert.

The tube was loaded in evaporator 2 on Wednesday 21/11/2018 and pumped down

The graphite insert will be heated to 2000 C


current pressure IGP1 =  4.2e-7 Torr

TGHT manually tapped to 40 A

Autoramp set to 2 A/min on TGHT to 400 A aiming for 1800 C


 Thursday, November 22, 2018, 17:13

TGHT 401.25 A, 6.79 V

Temperature 1780 C

IGP1 7.89e-7 Torr

Tapping manually to reach 1800 C, final current 407.2 A, 6.96 V


  Friday, November 23, 2018, 17:13

Tapped manually to TGHT 469.0 A, 8.64 V

Temperature 2019 C

IGP1 2.68e-7 Torr


Thursday, November 29, 2018, 08:03

TGHT 469.0 A, 8.945 V

Temperature 2061 C

IGP1 2.12e-7 Torr


 Tuesday, December 04, 2018, 07:53

TGHT 469.1 A, 8.814 V

Temperature 1983 C

IGP1 1.52e-7 Torr


Wednesday, December 05, 2018, 21:30

 TGHT 469.1 A, 8.75 V

Temperature 1983 C

IGP1 1.22e-7 Torr


Thursday, December 06, 2018, 12:25

 TGHT 468.9 A, 8.66 V

Temperature 1977 C

IGP1 1.42e-7 Torr


Friday, December 07, 2018, 17:59

  TGHT 468.9 A, 8.80 V

Temperature 1977 C

IGP1 1.42e-7 Torr


Wednesday, December 12, 2018, 12:18 

TGHT 469.2 A, 8.7 V

Temperature 1945 C

IGP1 1.10e-7 Torr


Thursday, December 13, 2018, 10:42

TGHT 469 A, 8.7 V

Temperature 1939 C

IGP1 1.04e-7 Torr

Ramping temperature down at -2 A/min


 Friday, December 14, 2018, 10:42

TGHT 0.0 A, 0.051 V

IGP1 4.36e-8 Torr

  422   Friday, November 02, 2018, 17:36 Marla CervantesEmpty39530-1LP-FEBIADDoneGraphite insert test #1

 Friday, November 02, 2018, 17:33

A new LP-FEBIAD was coated and syntered (e-log 421 Evaporator_2) 

The container was loaded with an empty graphite insert.

Graphite insert mass = 24.1724 g

A current of 440 A TGHT and 230 A TBHT will be inputed to the container

EVAP2 currently pumping down


 Saturday, November 03, 2018, 08:04

IGP1 = 5.66e-7 Torr

Tapping manually to 40 A on TGHT and TBHT

Then auto/ramp wiill be set to 2 A/min on TGHT and 1 A/min on TBHT

Maximum temperature achieve 1802 C


 Tuesday, November 06, 2018, 14:49

Container has reduced and increased its temperature from ~1760 to 1802 C.

IGP1  3.44e-7 Torr

TGHT 441.7 A and 7.7 V

TBHT 233.2 A and 3.2 V


 Wednesday, November 07, 2018, 08:32

Temperature 1785 C

IGP1  2.90e-7 Torr

TGHT 441.38 A and 7.7 V

TBHT 233.2 A and 3.2 V


 Friday, November 09, 2018, 17:26

Temperature 1787 C

IGP1  2.12 -7 Torr

TGHT 442.03 A and 7.7 V

TBHT 233.06 A and 3.19 V


Tuesday, November 13, 2018, 14:13: Turbos, power supplies off. Prepare for venting. 

  393   Thursday, November 23, 2017, 15:10 Laura Lambert 41882-4TARGET BOATDoneGraphite insert test

 Thursday, November 23, 2017, 14:54

Graphite insert loaded into previously TaC coated target boat.

One endcap removed to allow for outgassing: left side out, right side in.

Weight of graphite tube + single endcap = 10.2012g

Same Ta heats shields remain on container from sintering TaC coating.

Currently pumping down in evap2.


Friday, November 24, 2017, 11:31

IGP1 = 4.52e-7 Torr

IGP2 = 3.43e-7 Torr

OMEGA slope = 0.98

Good vac at 3.0e-4, bad vac at 8.0e-4 Torr.

HS water valves have remained open since the last time evap2 was used.

No leak check done.

Tapped up manually to 50A.

Vacuum stable.

IGP1 = 5.34e-7 Torr

IGP2 = 5.54e-7 Torr

Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 300A

Once max setpoints achieved, will tap up manually to final desired temperature of 2000C

Uranium targets go to a max temperature of 1950C online, so graphite insert should be tested to 2000C


 Monday, November 27, 2017, 10:15

IGP1 = 2.5e-7 Torr

IGP2 = 1.9e-7 Torr

Reached 300A, 4.61V

OMEGA = 1298C

Tapped up manually to 485A, 8.46V

OMEGA = 1808C

Remained at this setpoint for a day


Tuesday, November 28, 2017, 15:41 

IGP1 = 3.88e-7 Torr

IGP2 = 3.58e-7 Torr

Tapping up to 2000C...


Tuesday, November 28, 2017, 16:10 

TGHT = 570A, 10.20V

OMEGA = 2005C

IGP1 = 9.64e-7 Torr

IGP2 = 1.05e-6 Torr

There was a minor drop in voltage at 540A, 9.58V - dropped to ~9.4V then slowly went back up to 9.58V [see photo]

Will remain at this setpoint overnight and cool down in the a.m.


 Wednesday, November 29, 2017, 08:48

Voltage increased slowly while sitting at max setpoint of 570A [see photo]

TGHT = 570A, 11.20V --> voltage increased by 1.0V over ~16.5hrs

OMEGA = 2114C

IGP1 = 6.6e-7 Torr

IGP2 = 6.5e-7 Torr

Initiating auto-cool at 2.0A/min


 Wednesday, November 29, 2017, 16:15

Vented in air and removed today.

Will update tomorrow with results and photos.


 

Attachment 1: IMG_0018.JPG
IMG_0018.JPG
Attachment 2: IMG_0021.JPG
IMG_0021.JPG
Attachment 3: IMG_0028.JPG
IMG_0028.JPG
Attachment 4: IMG_0029.JPG
IMG_0029.JPG
Attachment 5: voltage_drop_11.28.2017.JPG
voltage_drop_11.28.2017.JPG
Attachment 6: voltage_increase_11.29.2017.JPG
voltage_increase_11.29.2017.JPG
  439   Wednesday, April 17, 2019, 09:06 Marla Cervantes 38295-10LP-FEBIADDoneGraphite insert test

 Wednesday, April 17, 2019, 09:03

An uncoated target container was loaded with a graphite insert and wrapped with 3 tantalum layers,

Two Ta caps were used

EVAP2 was pumped down, IGP1 = 5.14e-7 Torr


 The TGHT and TBHT current was tapped to 40 A manually

Autoramp was set to TGHT 1A/min to 500 A

and TBHT 0.5A/min to 230 A.

The temperature reached 2000 C as planned 

the target container stayed at that temperature for 1 week.


Tuesday, April 23, 2019, 10:00

EVAP2 was vented and the target container was removed.


The container crystalized but did not break.

Attachment 1: 190417-TargetContainer-TEMP.pdf
190417-TargetContainer-TEMP.pdf
Attachment 2: IMG_1074.JPG
IMG_1074.JPG
  446   Friday, May 24, 2019, 15:29 Marla Cervantes 43943-2 DoneGraphite insert test

Friday, May 24, 2019, 15:26

 A graphite insert with tantalum wires in its caps

was loaded in a tantalum tube, the system will be heated to 2000 C

and after 6 hrs at that temperature, it will be cooled and heated to 2000 C again.

The temperature will be hold at 2000 C for a 6 days.

Currently the chamber is being evacuated.


 Saturday, May 25, 2019, 06:01

IGP1 = 2.2e-7 Torr

Manually tapping to 50 A

Autoramp set to 1 A/min to 400 A


Saturday, May 25, 2019, 13:37

The autoramp was set to 450 A

Then it was manually tappe to 475 A 

  448   Monday, June 17, 2019, 17:03 Marla Cervantes 43943-2 DoneGraphite insert test

Thursday, June 6, 2019, 16:43

A graphite insert with tantalum wires in its caps was loaded in a tantalum tube.


The system will be heated to 2000 C again (see elog 446)

Currently the chamber is being evacuated.


Friday, June 7, 2019, 16:40

Autoramp was set to 450 A at 1A/min to reach 2000 C

The temperature will be hold at 2000 C for a 4 days.


Tuesday, June 11, 2019, 16:46 

Autoramp is set to -2 A/min to 0 A


Wednesday, June 12, 2019, 17:01 

The tube present sever crystallization but is not broken and has some resistance against pressure.

  454   Wednesday, August 28, 2019, 05:59 Marla Cervantes 44062-2-SK DoneGraphite insert test

Wednesday, August 28, 2019, 06:00

A graphite insert (with conical caps) was loaded in tantalum tube 

the Ta tube was wrapped with 3 tantalum foils,

a tantalum cap was inserted in one side of the Ta tube and sealed.

The tube was set in the EVAP2 and the furnace was pumped down.

IGP1 = 1.23e-6 Torr.

The current was tapped to 50 A

Autoramp was set to 1 A/min to 400 A.


 Wednesday, August 28, 2019, 12:02

Autoramp reached 400 A

TGHT = 6.57 V, 404.4 A, IGP1=4.7e-6 Torr

Autoramp was set to 450 A at 1A/min


 Wednesday, August 28, 2019, 12:48

Autoramp reached 450 A

TGHT =7.526 V, 450.188 A, IGP1=5.88e-6 Torr

Autoramp was set to 500 A at 1A/min


Wednesday, August 28, 2019, 13:40

Autoramp reached 500 A, temperature 1880 C

TGHT =8.79 V, 501.094A, IGP1=7.48-6 Torr

Autoramp was set to 540 A at 1A/min 


Wednesday, August 28, 2019, 14:03

The autoramp was stopped at 520 A, because according to previous tests that current is enough to have 2000 C,

the temperature read was 1930 C

TGHT =9.23 V, 520.7 A, IGP1=7.8-6 Torr


Wednesday, August 28, 2019, 15:20

The autoramp was set to 540 A at 1A/min

When the ramp stopped the conditions were:

TGHT=9.59 V, 539.5 A, IGP1= 6.08e-6 Torr

Temperature= 1988 C

Manually tapped to 545 A the temperature reached 2000 C


Wednesday, August 28, 2019, 17:08 

To keep the temperature at 2000 or less the current was decreased,

TGHT= 8.91 V, 445.125 A, IGP1=9.93e-7 Torr

Max temperature read: 2001 C

Min temperature read: 1996 C


Tuesday, September 03, 2019, 11:15

The tube was stable at 1950-1960 C during the weekend but today at around 6 am it had a drop in the current indicating mechanical failure 

The autoramp was set to -2A/min to 0 A. 

The tube will be examined and in case that it is not broken it will be set in the EVAP1 to continue heating it.


Monday, September 09, 2019, 16:35  

The tube became brittle and broke.