ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
Text |
|
433
|
Wednesday, March 13, 2019, 15:43 |
Marla Cervantes | | 43630-6 | | Done | Graphite insert test #4 | Wednesday, March 13, 2019, 15:41
An uncoated tantalum tube was loaded
with a graphite insert (with conical caps). |
|
428
|
Wednesday, January 23, 2019, 13:06 |
Marla Cervantes | | 43630-2 | | Done | Graphite insert test #3 | Wednesday, January 23, 2019, 13:01
A previously coated tantalum |
|
424
|
Thursday, November 22, 2018, 10:19 |
Marla Cervantes | | 43630-7 | | Done | Graphite insert test #2 | Thursday, November 22, 2018, 10:12
A previously sintered tantalum tube
with 3 layers of shielding was loaded with |
|
422
|
Friday, November 02, 2018, 17:36 |
Marla Cervantes | Empty | 39530-1 | LP-FEBIAD | Done | Graphite insert test #1 | Friday, November 02, 2018, 17:33
A new LP-FEBIAD was coated and |
|
393
|
Thursday, November 23, 2017, 15:10 |
Laura Lambert | | 41882-4 | TARGET BOAT | Done | Graphite insert test | Thursday, November 23, 2017, 14:54
Graphite insert loaded into previously
TaC coated target boat. |
6x |
439
|
Wednesday, April 17, 2019, 09:06 |
Marla Cervantes | | 38295-10 | LP-FEBIAD | Done | Graphite insert test | Wednesday, April 17, 2019, 09:03
An uncoated target container was
loaded with a graphite insert and wrapped |
|
446
|
Friday, May 24, 2019, 15:29 |
Marla Cervantes | | 43943-2 | | Done | Graphite insert test | Friday, May 24, 2019, 15:26
A graphite insert with tantalum
wires in its caps |
|
448
|
Monday, June 17, 2019, 17:03 |
Marla Cervantes | | 43943-2 | | Done | Graphite insert test | Thursday, June 6, 2019, 16:43
A graphite insert with tantalum |
|
454
|
Wednesday, August 28, 2019, 05:59 |
Marla Cervantes | | 44062-2-SK | | Done | Graphite insert test | Wednesday, August 28, 2019, 06:00
A graphite insert (with conical |
|
669
|
Thursday, August 08, 2024, 11:17 |
Marla Cervantes | C | 44139-5 SK | LP TUBE | Done | Graphite foils conditioning |
|
|
445
|
Tuesday, May 21, 2019, 18:01 |
Marla Cervantes | | 43943-1 | | Done | Graphite foil test | Tuesday, May 21, 2019, 17:57
A tantalum tube previously coated
with TaC and sintered was loaded with graphite |
|
525
|
Tuesday, November 24, 2020, 12:56 |
Marla Cervantes | | 44139-8-SK | TARGET BOAT | Done | Graphite casting conditioning | Tuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter
were loaded in a tantalum tube. The tantalum |
|
606
|
Friday, December 02, 2022, 09:50 |
Darwin Ortiz Rosales | | 45220-12 | TARGET BOAT | Done | Grahite disc conditioning 221130-Graphite | Friday, December 02, 2022, 09:46
297 graphite discs packed into a
Ta tube wrapped in four heatshields. |
|
591
|
Wednesday, September 14, 2022, 11:48 |
Darwin Ortiz Rosales | | | TARGET BOAT | Done | Grahite disc conditioning 220907G | Wednesday, September 14, 2022, 9:30
A Ta container tube was wrapped with
3 Ta heatshields. |
|
414
|
Tuesday, July 10, 2018, 16:43 |
John Wong | Empty | | LP-SIS | Done | For nano-SiC#1 | Tuesday, July 10, 2018, 16:40
Container was flashed with TaC solution
and let dry in air. |
|
470
|
Monday, November 25, 2019, 11:35 |
Aaron Schmidt | | | | In progress | Flex - line HS installed | Leak noted on previous TaC sintering
on HP FEBIAD # 42464-3.
Swapped out gaskets on HS flex line |
|
524
|
Tuesday, November 24, 2020, 08:13 |
Aaron Schmidt | | | | | Flex - line HS installed | Monday, November 23, 2020, 17:01: Flex-line
HS installed.
Tuesday, November 24, 2020, |
|
532
|
Monday, March 01, 2021, 13:58 |
Aaron Schmidt | | | | | Flex - line HS installed | Flex-Line HS had been fully scrubbed out
earlier. All gaskets replaced.
Empty. Quick check for leaks. |
|
506
|
Thursday, September 10, 2020, 07:53 |
Aaron Schmidt | Empty | 41790-8 | LP-FEBIAD | Done | Fernando FEBIAD / Anode testing. | FEBIAD installed. Anode PS installed.
ANODE connected!.
Leak check |
|
3
|
Monday, February 13, 2012, 16:24 |
John Wong | | | | Done | Evaporator #2 Commissioned | Monday, February 13, 2012, 16:21
The Evaporator 2 is now commissioned.
See attachment#1 for the commissioning |
|
|