67
|
Friday, April 19, 2013, 09:39 |
Rick Maharaj | Empty | | | Done | thermocouple Feedthru | A thermocouple feedthru was installed
via 9 pin sub-D connector. It runs from the
the conflat cross on the top of the evaporator |
|
|
218
|
Thursday, June 18, 2015, 11:39 |
Rick Maharaj | | | | | Installation of Extraction Electrode Insulator - New Material | Tuesday June 16, 2015
An Extraction Insulator ITD0381 made
from a different grade of AiN was installed |
|
|
2
|
Thursday, July 21, 2011, 17:33 |
Pierre Bricault | | | | Maintenance | | Rick mentioned to me that the evaporator is
ready for the next steps of the commissioning
process.
|
|
|
147
|
Friday, August 01, 2014, 11:47 |
Peter Kunz | | 40282-3 | LP-SIS | In progress | ZrC #6 conditioning | The maximum current of 580A was reached
at 9:15.
TGHT:RDCUR 578 A |
|
|
148
|
Friday, August 01, 2014, 13:27 |
Peter Kunz | | 40282-3 | LP-SIS | In progress | ZrC #6 conditioning | Target was conditioned for 4 hours at 580A.
Initiating ramp-down sequence @ 2A/min
|
|
|
6
|
Monday, March 19, 2012, 17:10 |
Nikita Bernier | BeO | Target boat #1 | | Done | Sintering BeO pellets | Monday, March 19, 2012, 17:04
Target boat contains 4 BeO pellets |
|
|
10
|
Thursday, March 22, 2012, 17:56 |
Nikita Bernier | BeO | Target boat #1 | | Done | Sintering BeO pellets |
|
|
|
11
|
Thursday, March 29, 2012, 19:30 |
Nikita Bernier | BeO | Target boat #1 | | Done | Sintering new BeO pellets | Thursday, March 29, 2012, 19:17
|
|
|
14
|
Monday, April 02, 2012, 16:26 |
Nikita Bernier | BeO | Target boat #1 | | Done | Sintering new BeO pellets |
|
|
|
16
|
Thursday, April 05, 2012, 16:40 |
Nikita Bernier | BeO | Target boat #2 | | Done | Sintering BeO pellets #3 | Thursday, April 05, 2012, 16:31
Target boat contains 6 BeO |
|
|
22
|
Friday, May 18, 2012, 12:19 |
Nikita Bernier | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target |
|
|
|
24
|
Tuesday, May 22, 2012, 12:15 |
Nikita Bernier | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target |
|
|
|
26
|
Tuesday, May 22, 2012, 16:45 |
Nikita Bernier | BeO | Target boat #2 | | Done | Sintering BeO pellets #3 |
|
|
|
29
|
Tuesday, May 29, 2012, 15:43 |
Nikita Bernier | BeO | Target boat #2 | | Failed | Sintering BeO pellets #3 |
|
|
|
31
|
Wednesday, June 20, 2012, 17:29 |
Nikita Bernier | NiO | Ta target boat | | Done | NiO development | Wednesday, June 20, 2012, 17:23
New Target boat, with no coating,
wrapped with a 0.002 inches thick Ta foil, |
|
|
39
|
Friday, August 10, 2012, 19:57 |
Nikita Bernier | | | | Done | Sintering Ta foil with TaO coating | Friday, August 10, 2012, 19:54
|
|
|
40
|
Saturday, August 11, 2012, 19:21 |
Nikita Bernier | | | | Done | Sintering Ta foil with TaO coating |
|
|
|
41
|
Monday, August 13, 2012, 13:50 |
Nikita Bernier | | | | Done | Sintering Ta foil with TaO coating |
|
|
|
46
|
Monday, September 24, 2012, 15:12 |
Nikita Bernier | TaC | | | Done | Sintering Ta foil with TaC coating | Monday, September 24, 2012, 15:01
The target boat with TaC coating
is being used again. The inside of the boat |
|
|
47
|
Monday, September 24, 2012, 18:09 |
Nikita Bernier | TaC | | | Done | Sintering Ta foil with TaC coating |
|
|