Entry  Friday, April 19, 2013, 09:39, Rick Maharaj, Empty, , , Done, thermocouple Feedthru 
 A thermocouple feedthru was installed via 9 pin sub-D connector. It runs from the the conflat cross on the top of the evaporator to the upper 9
pin connector of the target mounting plate.
Entry  Thursday, June 18, 2015, 11:39, Rick Maharaj, , , , , Installation of Extraction Electrode Insulator - New Material 
Tuesday June 16, 2015
An Extraction Insulator ITD0381 made from a different grade of AiN was installed in Evaporator 2 for testing purposes. The sub assembly included
the SIS Restraint Housing ITD0389, New Extraction Insulator ITD0381, Repeller Electrode ITD0377, Extraction Electrode ITD0374 with fingerstock mounted.
Entry  Thursday, July 21, 2011, 17:33, Pierre Bricault, , , , Maintenance,  
Rick mentioned to me that the evaporator is ready for the next steps of the commissioning process.
In the chamber only the target leg heaters have current by-pass clamps on them. 
The ionizer tube heaters do not have them because these lines do not have the same configuration as the others. The current by-pass clamps will 
Entry  Friday, August 01, 2014, 11:47, Peter Kunz , , 40282-3, LP-SIS, In progress, ZrC #6 conditioning 
The maximum current of 580A was reached at 9:15.
TGHT:RDCUR 578 A
TGHT:RDVOL 9.87 V
Entry  Friday, August 01, 2014, 13:27, Peter Kunz , , 40282-3, LP-SIS, In progress, ZrC #6 conditioning zrc6_conditioning.png
Target was conditioned for 4 hours at 580A.
Initiating ramp-down sequence @ 2A/min
 
Entry  Monday, March 19, 2012, 17:10, Nikita Bernier, BeO, Target boat #1, , Done, Sintering BeO pellets 
 Monday, March 19, 2012, 17:04
 
Target boat contains 4 BeO pellets with 30% PVB:
    Reply  Thursday, March 22, 2012, 17:56, Nikita Bernier, BeO, Target boat #1, , Done, Sintering BeO pellets 


    
        
            Nikita Bernier wrote:
        
        
            
             Monday, March 19, 2012, 17:04
Entry  Thursday, March 29, 2012, 19:30, Nikita Bernier, BeO, Target boat #1, , Done, Sintering new BeO pellets 
 Thursday, March 29, 2012, 19:17
 
Target boat contains 3 BeO pellets :
    Reply  Monday, April 02, 2012, 16:26, Nikita Bernier, BeO, Target boat #1, , Done, Sintering new BeO pellets 


    
        
            John Wong wrote:
        
        
            
            
            
              
Entry  Thursday, April 05, 2012, 16:40, Nikita Bernier, BeO, Target boat #2, , Done, Sintering BeO pellets #3 
Thursday, April 05, 2012, 16:31
Target boat contains 6 BeO pellets :
Sample,    Mass (g),   Thickness (mm),   Density (g/cm3)
    Reply  Friday, May 18, 2012, 12:19, Nikita Bernier, SiC, 38481-2, HP-SIS, Done, Re-condition the HP-SIS SiC target autoramp1.pngievap2autoheat1.png


    
        
            John Wong wrote:
        
        
            
            Tuesday, May 15, 2012, 12:24
    Reply  Tuesday, May 22, 2012, 12:15, Nikita Bernier, SiC, 38481-2, HP-SIS, Done, Re-condition the HP-SIS SiC target TGHT-VAC1.JPGTBHT-VAC1.JPG


    
        
            John Wong wrote:
        
        
            
            
            
    Reply  Tuesday, May 22, 2012, 16:45, Nikita Bernier, BeO, Target boat #2, , Done, Sintering BeO pellets #3 


    
        
            Nikita Bernier wrote:
        
        
            
            Thursday, April 05, 2012, 16:31
    Reply  Tuesday, May 29, 2012, 15:43, Nikita Bernier, BeO, Target boat #2, , Failed, Sintering BeO pellets #3 


    
        
            John Wong wrote:
        
        
            
            
            
Entry  Wednesday, June 20, 2012, 17:29, Nikita Bernier, NiO, Ta target boat, , Done, NiO development NiO_density_measurements.xlsxCasts_thickness.GIF
Wednesday, June 20, 2012, 17:23
New Target boat, with no coating, wrapped with a 0.002 inches thick Ta foil, contains 3 NiO pellets :
Sample,   # Disks,    Mass (g),    Thickness (mm)
Entry  Friday, August 10, 2012, 19:57, Nikita Bernier, , , , Done, Sintering Ta foil with TaO coating 
 Friday, August 10, 2012, 19:54
 
Target boat with TaC coating, inside covered with a 0.002 inches thick Ta foil, wrapped
    Reply  Saturday, August 11, 2012, 19:21, Nikita Bernier, , , , Done, Sintering Ta foil with TaO coating TaO1.pngTaO2.png


    
        
            Nikita Bernier wrote:
        
        
            
             Friday, August 10, 2012, 19:54
    Reply  Monday, August 13, 2012, 13:50, Nikita Bernier, , , , Done, Sintering Ta foil with TaO coating TaO3.png


    
        
            Nikita Bernier wrote:
        
        
            
            
            
              
Entry  Monday, September 24, 2012, 15:12, Nikita Bernier, TaC, , , Done, Sintering Ta foil with TaC coating striptool1.PNG
 Monday, September 24, 2012, 15:01
The target boat with TaC coating is being used again. The inside of the boat is covered with a 0.002 inches thick Ta foil with TaC coating, wrapped
with a 0.002 inches thick Ta foil.
    Reply  Monday, September 24, 2012, 18:09, Nikita Bernier, TaC, , , Done, Sintering Ta foil with TaC coating striptool2.PNGstriptool4.PNGstriptool5.PNG


    
        
            Nikita Bernier wrote:
        
        
            
             Monday, September 24, 2012, 15:01
ELOG V2.9.2-2455