    Reply  Friday, August 23, 2013, 16:11, John Wong, UO2/C, Target Boat #2, , Problems resolved, Processing UC2 flaskes (batch#06 - 08222013 

John Wong wrote:

Thursday, August 22, 2013, 17:31

1st attempt:

UO2/C green was prepared on Aug 14, 2013 (wed).  The slurry was cast on a piece of glass coated with WD40.

The cast was let dry until Aug 26 (Mon) - couldn't peel off from the glass. 

2nd attempt:

So, scrapped off cast, mixed with 30ml H20 in the WC jar, re-milled for 3 hrs, and cast/let dry over night  - SAME SHIT! couldn't peel off!  Don't understand why?!

3rd attempt:

scrapped off, added the additional compositions:

1g PEG400,1g Glycerol, 10g 7% PVA, 2ml n-butanol, 2ml methonal, 20ml DI H2O.

Re-milled for 3 hours, cast and let dry!  Wahlaa... it works! (See attachment#1: pretty uranium pancake!)

However... During this process, some lost of uranium was resulted.  The slurry was more viscous than normal.  Some material was stuck to the WC jar wall and the balls.

Initial UO2 powder used = 50.14g (Inventory R-00835A UO2 + bottle = 795.56 before use)

Graphite powder used = 10g.

1st attempt dried UO2/C + organic  mass = 55.75g

2nd attempt = didn't measure

3rd attempt + additional org mass = 44.5g  (expecting to loss more uranium from the scraping/sticking to jar/balls)

The green was rolled up and wrapped in a piece of graphite sheet.

The Ta-target boat was wrapped with 3-Ta layers of heat shield and installed in Evap1 on Aug 22, 2013.

Chamber is currently being pumped down. IG1 @ 2.4e-4 Torr.

Target will be ramped up to 520A at the rate of 0.1A/min

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr


 

 

 Friday, August 23, 2013, 15:08

The chamber wasn't pumping down well; there was a problem with the seal on the lid.

Rick M. replaced it. 

The chamber is currently being pumped down;  it seems OK!


 

    Reply  Tuesday, September 10, 2013, 12:20, Laura Lambert, UO2/C, Target Boat #2, , Done, Processing UC2 flaskes (batch#06 - 08222013 

John Wong wrote:

John Wong wrote:

Thursday, August 22, 2013, 17:31

1st attempt:

UO2/C green was prepared on Aug 14, 2013 (wed).  The slurry was cast on a piece of glass coated with WD40.

The cast was let dry until Aug 26 (Mon) - couldn't peel off from the glass. 

2nd attempt:

So, scrapped off cast, mixed with 30ml H20 in the WC jar, re-milled for 3 hrs, and cast/let dry over night  - SAME SHIT! couldn't peel off!  Don't understand why?!

3rd attempt:

scrapped off, added the additional compositions:

1g PEG400,1g Glycerol, 10g 7% PVA, 2ml n-butanol, 2ml methonal, 20ml DI H2O.

Re-milled for 3 hours, cast and let dry!  Wahlaa... it works! (See attachment#1: pretty uranium pancake!)

However... During this process, some lost of uranium was resulted.  The slurry was more viscous than normal.  Some material was stuck to the WC jar wall and the balls.

Initial UO2 powder used = 50.14g (Inventory R-00835A UO2 + bottle = 795.56 before use)

Graphite powder used = 10g.

1st attempt dried UO2/C + organic  mass = 55.75g

2nd attempt = didn't measure

3rd attempt + additional org mass = 44.5g  (expecting to loss more uranium from the scraping/sticking to jar/balls)

The green was rolled up and wrapped in a piece of graphite sheet.

The Ta-target boat was wrapped with 3-Ta layers of heat shield and installed in Evap1 on Aug 22, 2013.

Chamber is currently being pumped down. IG1 @ 2.4e-4 Torr.

Target will be ramped up to 520A at the rate of 0.1A/min

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr


 

 

 Friday, August 23, 2013, 15:08

The chamber wasn't pumping down well; there was a problem with the seal on the lid.

Rick M. replaced it. 

The chamber is currently being pumped down;  it seems OK!


 

 Tuesday, September 10, 2013, 12:13

The TGHT reached zero on Monday and the chamber was left under vacuum overnight at 1.3e-6 Torr.

The chamber was accidentally vented in air until ~25mTorr for ~10min, then it was quickly pumped down again for ~10min before it was vented in Ar.

The chamber was vented in Ar and the UC2 flakes were transported into the Ar-glove box.

The process is complete 


 

Entry  Thursday, September 19, 2013, 15:41, Laura Lambert, UO2/C, Target Boat #2, , In progress, Processing UC2 flakes (batch #07 - 09192013) 

Thursday, September 19, 2013, 15:35

UO2/C green was prepared on Aug 17, 2013. The slurry was cast on a piece of glass coated with WD40.

The cast was let dry until Aug 19, 2013.

Initial UO2 powder used = 49.97g (Inventory R-00835A UO2 + bottle = 745.42 before use)

Graphite powder used = 10.12g

Green cast dried UO2/C + organic mass = 59.62g

The green was rolled up and wrapped in a piece of graphite sheet.

The Ta-target boat was wrapped with 3-Ta layers of heat shield and installed in Evap1 on Sept 19, 2013.

Chamber is currently being pumped down. IG1 @ 9.97e-12T.

Target will be ramped up to 520A at the rate of 0.1A/min

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr


 

    Reply  Friday, September 20, 2013, 13:49, John Wong, UO2/C, Target Boat #2, , Done, Processing UC2Flk_00 

Laura Lambert wrote:

Thursday, September 19, 2013, 15:35

UO2/C green was prepared on Aug 17, 2013. The slurry was cast on a piece of glass coated with WD40.

The cast was let dry until Aug 19, 2013.

Initial UO2 powder used = 49.97g (Inventory R-00835A UO2 + bottle = 745.42 before use)

Graphite powder used = 10.12g

Green cast dried UO2/C + organic mass = 59.62g

The green was rolled up and wrapped in a piece of graphite sheet.

The Ta-target boat was wrapped with 3-Ta layers of heat shield and installed in Evap1 on Sept 19, 2013.

Chamber is currently being pumped down. IG1 @ 9.97e-12T.

Target will be ramped up to 520A at the rate of 0.1A/min

Vacuum limit stop at 5.0e-5 Torr, backing off at 6.0e-5 Torr


 

 Friday, September 20, 2013, 13:48

Chamber has been pumped down overnight.  IG at 6.2e-6 Torr, BP @ 32mT.

Stepping up TGHT to 30A.


 Friday, September 20, 2013, 15:12

TGHT auto ramping initiated.  


 Monday, October 07, 2013, 14:09

TGHT has reached to 520A/5.5V.

Vac at 7.7e-6 Torr. 

The carbonization process is complete.

Auto-cooling is initiated at 2A/min, and the chamber will be vented in Ar after the target is cooled.


 Thursday, October 09, 2014, 13:36

*update* RENAME: batch #07 - 09192013 to UC2Flk_00 used for UCx#11


 

Entry  Friday, November 01, 2013, 13:08, Anders Mjos, , , , Maintenance, Gloves, window and window gasket replaced. 

Work covered under work permit 2013-11-01-3 and performed by Anders and Rick with the help of Danno (RPG).

No significant contamination was found during the work. The old window could be disposed as normal waste.

Entry  Monday, December 02, 2013, 16:09, Anders Mjos, , , , Problems resolved, TGHT connector repositioned and tightened Evap1_rotated_TGHT_conductor_2013-12-02.pdf

The right connector for the TGHT had rotated. It has now been repositioned and both connectors have been tightened to reduce the chance for further rotation.

Entry  Monday, December 02, 2013, 16:10, Anders Mjos, , , , Done, Copper bar on TGHT Current_and_Voltage.pdf

The conductivity of the TGHT circuit will be measured with a copper bar shunt.

Monday, December 02, 2013, 16:00: Pumping down. 

Tuesday, December 03, 2013, 09:40: Stepped current up to 600A. Impedance of system ~0.7 mOhm. See attached graph for P(I).

Tuesday, December 03, 2013, 12:06: Stopped turbo. Vacuum at 1.3E-5 Torr

Wednesday, December 04, 2013, 09:20: Copper bar removed from vacuum chamber.

Test finished.

Entry  Thursday, December 11, 2014, 10:17, Laura Lambert, , , , Maintenance, water supply shut off for lab closure over holidays 

 Thursday, December 11, 2014, 10:16

water valve shut off for lab closure over the holidays.


 

Entry  Friday, January 23, 2015, 15:02, Laura Lambert, , , , Maintenance, water supply turned back on to EVAP1 and fume hoods 

 Friday, January 23, 2015, 15:02

water supply turned back on to EVAP1 and fume hoods


 

Entry  Tuesday, April 21, 2015, 11:28, Laura Lambert, , , , Maintenance, Ion Gauge replaced March 23rd 2015 
 
Entry  Saturday, August 29, 2015, 16:12, Anders Mjos, , , , Problems, Restarting vacuum after power outage 

Saturday, August 29, 2015, 16:10: Roughing

Saturday, August 29, 2015, 16:10: Starting turbo

Saturday, August 29, 2015, 16:12: Turbo running. IG1 at 2.4E-4 T

Entry  Tuesday, April 19, 2016, 10:48, Laura Lambert, UC2, ***, , Done, ***ALL FUTURE UCx TARGETS*** 

 Tuesday, April 19, 2016, 09:47

Temperature measurements have been taken in evap2 on target containers. 

Previously all UCx targets have been conditioned in evap1 at 520A. The respective target containers TaC coating was sintered in evap2 at a different current.

All future UCx targets will now be conditioned in evap1 at the same current required to reach 1900C in evap2 when sintering the TaC coating on the container to be used for the respective target.

ie. If a container is being sintered in evap2 at 450A [1900C], this same container is used for UCx - then that specific UCx target will be conditioned in evap1 at 450A.

Confirm full carbonization has been achieved by following with the vacuum on the strip tool and make sure the final vacuum comes down at the end of the whole process.


 

Entry  Monday, May 16, 2016, 15:52, Laura Lambert, , , , , Full clean of EVAP1 

 Monday, May 16, 2016, 15:51

full clean of inside evap1 this afternoon.


 

Entry  Tuesday, December 20, 2016, 15:03, Laura Lambert, , , , Maintenance, RETURN and SUPPLY valves CLOSED for xmas break 
 
Entry  Wednesday, May 24, 2017, 09:34, Laura Lambert, , , , Maintenance, VACUUM TRIP OFF SETPOINT CHANGED 

 Wednesday, May 24, 2017, 09:31

Last week the vacuum trip off point was changed to 8e-4 Torr when previously it was set to 8e-5 Torr.

Vacuum limits were set to stop at 5e-5 Torr and back-off at 6e-5 Torr

Now vacuum limits will be changed by an order of magnitude in an attempt to speed up the processes in the evaporator.


 

Entry  Wednesday, June 07, 2017, 12:48, Aaron Schmidt, , , , , Turbo pump cooling 

 Wednesday, June 07, 2017, 10:00-12:00: Cooling was split/routed from two bottom lines with tees and run to the turbo pump.

 

Entry  Thursday, July 13, 2017, 12:49, Laura Lambert, , , , Problems, *hot lab is HOT* Capture.JPG

Thursday, July 13, 2017, 12:48

NOTE: hot lab reached 27degrees every day this week and went up to 28C today! 

This is with the small portable fan running.

27C was reached even with both evaporators off.

When at 28C: evap2 = ~1500C and evap1 = 35A


 Thursday, July 20, 2017, 15:58

Hot lab reached 30C today.

Small fan off - unsure if able to run due to contamination spread...

Both evap1 and evap2 were under vacuum but had not initiated ramping up yet.


 

    Reply  Thursday, July 27, 2017, 09:08, Laura Lambert, , , , Problems resolved, *hot lab is HOT* 

Laura Lambert wrote:

Thursday, July 13, 2017, 12:48

NOTE: hot lab reached 27degrees every day this week and went up to 28C today! 

This is with the small portable fan running.

27C was reached even with both evaporators off.

When at 28C: evap2 = ~1500C and evap1 = 35A


 Thursday, July 20, 2017, 15:58

Hot lab reached 30C today.

Small fan off - unsure if able to run due to contamination spread...

Both evap1 and evap2 were under vacuum but had not initiated ramping up yet.


 

 Thursday, July 27, 2017, 09:06

There was a broken valve motor affecting all ISAC rooms - temporary fix in place.

Ventilation in ISAC hot lab has been increased.

Temperature back to a reasonable level - currently sitting at 22C!


 

Entry  Thursday, September 07, 2017, 14:26, Aaron Schmidt, , , , Maintenance, roughing pump oil replaced 

 Thursday, September 07, 2017, 11:00 -12:00

The roughing pump was disconnected from Evaporator 1, along with the exhaust/ventilation. No contamination was found on swipes.

The oil was refilled.

The roughing pump was then moved away from the PLC to allow access for Dave Morris. The RP can be reconnected and tested after the PLC work is complete.

Work permit # I2017-09-07-1

 

Entry  Wednesday, September 20, 2017, 08:07, Aaron Schmidt, , , , Maintenance, Ion gauge & RP status 

Wednesday, September 20, 2017, 08:00: 

-A new ion gauge was installed yesterday afternoon and the old one removed. The old IG was found to be contaminated (300 cpm) and as of 20/09/2017, it is double bagged and stashed underneath the evaporator for the time being. 

Completed under work permit: I2017-09-19-9

-The roughing pump was reconnected this morning without issue.