82
|
Friday, November 01, 2013, 13:08 |
Anders Mjos | | | | Maintenance | Gloves, window and window gasket replaced. | Work covered under work permit 2013-11-01-3
and performed by Anders and Rick with the
help of Danno (RPG). |
|
|
83
|
Monday, December 02, 2013, 16:09 |
Anders Mjos | | | | Problems resolved | TGHT connector repositioned and tightened | The right connector for the TGHT had rotated.
It has now been repositioned and both connectors
have been tightened to reduce the chance |
|
|
84
|
Monday, December 02, 2013, 16:10 |
Anders Mjos | | | | Done | Copper bar on TGHT | The conductivity of the TGHT circuit will
be measured with a copper bar shunt.
Monday, December 02, 2013, 16:00: |
|
|
89
|
Tuesday, March 04, 2014, 15:48 |
John Wong | | | TARGET BOAT | In progress | Re-sinterring end caps | Tuesday, March 04, 2014, 15:43
Theses endcaps (4) were previously
sinterred in Evap#2 but some surfaces were |
|
|
90
|
Wednesday, March 05, 2014, 10:30 |
Laura Lambert | | | TARGET BOAT | In progress | Re-sinterring end caps |
|
|
|
91
|
Wednesday, March 05, 2014, 23:05 |
John Wong | | | TARGET BOAT | Done | Re-sinterring end caps |
|
|
|
92
|
Monday, March 24, 2014, 17:53 |
John Wong | UO2/C | | TARGET BOAT | Done | Processing UC2Flk_02 | Monday, March 24, 2014, 17:50
UO2/C cast was prepared on March
21 and let dry over the weekend. The |
|
|
94
|
Wednesday, May 21, 2014, 11:41 |
John Wong | UC2 | | TARGET BOAT | In progress | Tests: Sintering carbon Mesh coated with UC2 | Tuesday, May 20, 2014, 16:01
Target boat contains one pellet of
carbon mesh coated with UC2. The sample |
|
|
98
|
Thursday, August 14, 2014, 17:56 |
John Wong | ThO2 | | LP-SIS | Done | Sintering ThO2#1 | Thursday, August 14, 2014, 17:54
Target container consists of 240
discs of ThO2/Nb discs. The container |
|
|
105
|
Thursday, December 11, 2014, 10:17 |
Laura Lambert | | | | Maintenance | water supply shut off for lab closure over holidays | Thursday, December 11, 2014, 10:16
water valve shut off for lab closure
over the holidays. |
|
|
106
|
Friday, January 23, 2015, 15:02 |
Laura Lambert | | | | Maintenance | water supply turned back on to EVAP1 and fume hoods | Friday, January 23, 2015, 15:02
water supply turned back on to EVAP1
and fume hoods |
|
|
108
|
Monday, March 09, 2015, 16:58 |
Laura Lambert | Empty | | TARGET BOAT | Maintenance | Testing new software | Monday, March 09, 2015, 16:55
After upgrading IOC for CXML program,
experienced some issues; therefore, switched |
|
|
110
|
Tuesday, April 21, 2015, 11:28 |
Laura Lambert | | | | Maintenance | Ion Gauge replaced March 23rd 2015 | |
|
|
119
|
Saturday, August 29, 2015, 16:12 |
Anders Mjos | | | | Problems | Restarting vacuum after power outage | Saturday, August 29, 2015, 16:10: Roughing
Saturday, August 29, 2015, 16:10:
Starting turbo |
|
|
131
|
Monday, May 16, 2016, 15:52 |
Laura Lambert | | | | | Full clean of EVAP1 | Monday, May 16, 2016, 15:51
full clean of inside evap1 this afternoon.
|
|
|
134
|
Tuesday, August 23, 2016, 17:35 |
John Wong | | | TARGET BOAT | | Sintering TaC coated target boat | Tuesday, August 23, 2016, 17:33
Target boat coated with TaC (sprayed)
and wrapped with Ta-heat shield. |
|
|
135
|
Monday, September 12, 2016, 17:41 |
John Wong | | | TARGET BOAT | In progress | RUSH. Sintering end-caps | Monday, September 12, 2016, 17:30
A bunch of end caps (12?) and a long
Ta-wire in spring sharp were coated |
|
|
136
|
Tuesday, September 20, 2016, 10:49 |
Laura Lambert | | | TARGET BOAT | Done | RUSH. Sintering end-caps |
|
|
|
143
|
Tuesday, December 20, 2016, 15:03 |
Laura Lambert | | | | Maintenance | RETURN and SUPPLY valves CLOSED for xmas break | |
|
|
148
|
Wednesday, May 24, 2017, 09:34 |
Laura Lambert | | | | Maintenance | VACUUM TRIP OFF SETPOINT CHANGED | Wednesday, May 24, 2017, 09:31
Last week the vacuum trip off point
was changed to 8e-4 Torr when previously |
|