Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_1, Page 10 of 15  Not logged in ELOG logo
ID Date Author Target Material Target Oven W.O# Source Status Subject Text Attachments
  115   Wednesday, July 08, 2015, 10:52 John WongUC240860-1LP-IG-LISDoneConditioning UCx #13

    

       
            
 Screen_Shot_2015-07-09_at_5.20.37_PM.pngpressure_current_plot.PNG 
  114   Friday, July 03, 2015, 13:45 Laura LambertUC240860-1LP-IG-LISIn progressConditioning UCx #13

    

       
            
 evap1_trip_off_july_3rd.JPG 
  113   Thursday, July 02, 2015, 13:01 John WongUC240860-1LP-IG-LISIn progressConditioning UCx #13

    

       
            
  
  112   Tuesday, June 30, 2015, 13:31 Laura LambertUC240860-1LP-IG-LISIn progressConditioning UCx #13 Tuesday, June 30, 2015, 13:28
Target container was previously
  
  111   Monday, May 11, 2015, 11:49 Laura LambertUO2/C40282-1TARGET BOATDoneProcessing UC2Flk_06 Monday, May 11, 2015, 11:45
UO2/C green was prepared May
 IMG_20150508_143957199_HDR.jpgstriptool.JPGstriptool-zoom.JPG 
  110   Tuesday, April 21, 2015, 11:28 Laura Lambert   MaintenanceIon Gauge replaced March 23rd 2015    
  109   Friday, March 20, 2015, 15:21 Laura LambertUC241177-2LP-SISDoneConditioning UCx #12Friday, March 20, 2015, 15:17 
Target container was previously
  
  108   Monday, March 09, 2015, 16:58 Laura LambertEmpty TARGET BOATMaintenanceTesting new software Monday, March 09, 2015, 16:55
After upgrading IOC for CXML program,
experienced some issues; therefore, switched
  
  107   Monday, January 26, 2015, 11:28 Laura LambertUO2/C40282-1TARGET BOATDoneProcessing UC2Flk_05 Monday, January 26, 2015, 11:19
UO2/C green was prepared Jan 20,
2015. The slurry was cast on a piece of glass
 flk5.jpgstriptool.JPG 
  106   Friday, January 23, 2015, 15:02 Laura Lambert   Maintenancewater supply turned back on to EVAP1 and fume hoods Friday, January 23, 2015, 15:02
water supply turned back on to EVAP1
and fume hoods
  
  105   Thursday, December 11, 2014, 10:17 Laura Lambert   Maintenancewater supply shut off for lab closure over holidays Thursday, December 11, 2014, 10:16
water valve shut off for lab closure
over the holidays.
  
  104   Monday, November 10, 2014, 13:50 Laura LambertUC240282-5LP-SISDoneConditioning UCx #11

    

       
            
  
  103   Monday, October 20, 2014, 16:22 John WongUC240282-5LP-SISDoneConditioning UCx #11

    

       
            
 power_bump.PNG 
  102   Friday, October 17, 2014, 11:55 Laura LambertUC240282-5LP-SISIn progressConditioning UCx #11 Friday, October 17, 2014, 11:47
Target container was previously coated
with TaC spray and sintered.
  
  101   Friday, October 10, 2014, 14:00 John WongUO2/C40282-1TARGET BOATDoneProcessing UC2Flk_04

    

       
            
 archiver_TGHT&VAC.PNG 
  100   Tuesday, September 23, 2014, 15:00 Laura LambertUO2/C40282-1TARGET BOATIn progressProcessing UC2Flk_04 Tuesday, September 23, 2014, 14:54
UO2/C green was prepared Sept 18,
2014. The slurry was cast on a piece of glass
  
  99   Tuesday, August 26, 2014, 15:27 Laura LambertUO2/C40282-1TARGET BOATDoneProcessing UC2Flk_03 Tuesday, August 26, 2014, 11:54
UO2/C green was prepared Aug 20,
2014. The slurry was cast on a piece of glass
 carbonization.JPG 
  98   Thursday, August 14, 2014, 17:56 John WongThO2 LP-SISDoneSintering ThO2#1 Thursday, August 14, 2014, 17:54
Target container consists of 240
discs of ThO2/Nb discs.  The container
  
  97   Wednesday, July 09, 2014, 13:57 Laura LambertThO240282-2TARGET BOATDoneTest: Sintering ThO2 with Nb backing foils

    

       
            
 test_batch_full_sintering.JPGjul9_2014_(2).jpg 
  96   Friday, July 04, 2014, 10:23 John WongThO240282-2TARGET BOATDoneTest: Sintering ThO2 with Nb backing foils Friday, July 04, 2014, 10:13
Target boat contains 4 set of samples. 
Each sample consists of 5pack ThO2/Nb. 
 2014-07-03_12.29.29.jpgThO_raw_green_sintered_30um.pngpressure_current_plot.PNG 
ELOG V2.9.2-2455