Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_1, Page 1 of 11  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Tuesday, January 14, 2025, 16:28, Darwin Ortiz Rosales, UO2/C, conditioning oven#3, LP TUBE, In progress, UCx250113 reduction 
Tuesday, January 14, 2025, 16:26
 
Cartridge #22 loaded with 211 discs including 3 analysis discs
Entry  Thursday, September 19, 2024, 22:48, Darwin Ortiz Rosales, UO2/C, conditioning oven#3, LP TUBE, Done, UCx240917 reduction 
Thursday, September 19, 2024, 22:44
 
Cartridge #21 loaded with 211 discs including 3 analysis discs
Entry  Tuesday, September 17, 2024, 06:49, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, UCx240916 reduction 
Tuesday, September 17, 2024, 06:45
Cartridge #20 loaded with 224 discs plus 3 analysis discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Thursday, September 12, 2024, 06:23, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, UCx240904 reduction 

Thursday, September 12, 2024, 06:19
Cartridge #19 loaded with 232 discs including 5 analysis discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Tuesday, April 09, 2024, 14:43, Darwin Ortiz Rosales, UO2, , LP TUBE, Done, UCx240408 reduction 
 Tuesday, April 09, 2024, 14:42
Cartridge #16 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, October 11, 2023, 10:06, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, TUCx-231005 reduction & conditioning 
Wednesday, October 11, 2023, 9:36
Cartridge #10 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, March 22, 2023, 22:29, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, 230316 Reduction 
Wednesday, March 22, 2023, 22:29
Cartridge #9 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Thursday, January 19, 2023, 10:02, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, C230105 Reduction 
Thursday, January 19, 2023, 09:57
Cartridge #8 loaded with 198 discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Monday, December 19, 2022, 10:45, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, C-221207 Reduction 
Monday, December 19, 2022, 10:38
Cartridge with 175 discs (including 5 analysis discs) loaded into a graphite cartridge. 
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields
Entry  Monday, November 28, 2022, 05:59, Darwin Ortiz Rosales, UO2/C, , LP-SIS, Done, C221125experiment Data_summary.png
Monday, November 28, 2022, 05:58
Left weekend to pump down
current IGPI= 7.23e-7 Torr
Entry  Wednesday, October 19, 2022, 12:28, Darwin Ortiz Rosales, UC2, 40253-5, LP TUBE, Done, C-220510 further conditioning 
Wednesday, October 19, 2022, 10:27
Cartridge-220510Cx was installed in the EVAP1 and pumped down yesterday.
Material will be further conditioned at 450A for 4 hours.
Entry  Friday, October 07, 2022, 08:14, Darwin Ortiz Rosales, UO2/C, , LP-SIS, Done, C-220928UCx conditioning experiments Cap_1_221011.pngCap_2.pngcap3.png
Friday, October 07, 2022, 07:55
Cartridge-220928UCx was installed in the EVAP1 and pumped down yesterday.
Material will be reduced in LP-SIS wrapped with 3 Ta foils.
Entry  Tuesday, June 07, 2022, 07:09, Darwin Ortiz Rosales, UO2/C, Target Boat, , Done, UO2 reduction ID C220510-1 
Tuesday, June 07, 2022, 07:05
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (previous
day)
Entry  Friday, June 03, 2022, 06:21, Darwin Ortiz Rosales, UO2/C, 42218-4, LP-IG-LIS, Done, UCx#39 reduction 

Friday, June 03, 2022, 06:24
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (previous
day)
Entry  Wednesday, June 01, 2022, 08:42, Darwin Ortiz Rosales, UO2/C, Target Boat, , Done, UO2 reduction Provisional ID C211209-1  
Wednesday, June 01, 2022, 08:39
A loaded graphite cartridge was set in a tantalum boated and wrapped with 3 tantalum sheets (previous
day)
Entry  Wednesday, May 04, 2022, 09:47, Luca Egoriti, UC2, , P2N-SIS, Done, P2N carbothermal reduction P2NC220408 
 Wednesday, May 04, 2022, 09:42
Yesterday, a second graphite cartridge was installed in EVAP1, it consists of the old, 3-body cartridge design, and was sanded on the outside to
be able to fit a P2N container. 
Entry  Wednesday, April 13, 2022, 10:55, Luca Egoriti, UC2, , P2N-SIS, Done, P2N carbothermal reduction P2Ncartridge-220323 
Wednesday, April 13, 2022, 10:50
P2NC-220323
Preparing the P2N-UCx for online operation on June 2022
Entry  Wednesday, November 24, 2021, 10:38, Luca Egoriti, Ta, , , In progress, IPF release tests 
Wednesday, November 24, 2021, 10:38
A first, short "FullTa1" target was loaded into the evap1. It consists of a short container (10 cm) with lateral thickness of ~0.2mm.
The ends of the target connect with the TGHT terminals through two copper adapters.
Entry  Friday, November 05, 2021, 13:38, Luca Egoriti, Ta, , LP-SIS, In progress, Full target release test 2 Ta-ReleaseTest-2_low-current.JPG
 Friday, November 05, 2021, 13:23
Full target loaded with ~500 non-active foils plus 4 active foils.  
Initial pressure when heating: 1.6E-5 T 
Entry  Friday, September 24, 2021, 15:40, Luca Egoriti, Ta, , LP-SIS, In progress, Full target release test 1 
 Friday, September 24, 2021, 15:38
Full target loaded with ~500 non-active foils plus 4 active foils.  
Initial pressure when heating: 6.6E-5 T 
ELOG V2.9.2-2455