  945   Tuesday, November 15, 2022, 15:32 Sam Gupta       ATTS tantalum Bracket Heating test

Heated up sample 01 for the second time and measured the temperature with increasing current. Used pyrometre to measure temperature and calibrated it with the emmissivity values from cassidy

  946   Wednesday, November 16, 2022, 13:28 Aaron Schmidt      Problems/SolutionsTSG:TP1A Replaced

 See elog 944

Wednesday, November 16, 2022, 13:23: TP1 A replaced

Wednesday, November 16, 2022, 13:25: Roughing.

Wednesday, November 16, 2022, 14:53: TP1B on

Wednesday, November 16, 2022, 14:56: TP1B at speed.

Wednesday, November 16, 2022, 14:58: TP1A on.

Wednesday, November 16, 2022, 15:07: TP1A at speed. IG1 on. Vacuum @ 3.32e-05T

 

 

  948   Monday, December 05, 2022, 15:41 Aaron Schmidt       Source tray insulator replacement

 Monday, December 05, 2022, 15:38: Source Tray TGHT & TBHT insulators replaced. 

Torqued @ 75 in-lbs. (Reference image attached)

 

Attachment 1: TBHT_Glow_-__Before.jpg
TBHT_Glow_-__Before.jpg
Attachment 2: TBHT_Insulator_-_Removed.jpg
TBHT_Insulator_-_Removed.jpg
Attachment 3: Torque_references.jpg
Torque_references.jpg
Attachment 4: TGHT_Insulator_-_Before.jpg
TGHT_Insulator_-_Before.jpg
Attachment 5: TGHT_Insulator_-_After.jpg
TGHT_Insulator_-_After.jpg
Attachment 6: TBHT_Insulator_-_After.jpg
TBHT_Insulator_-_After.jpg
Attachment 7: Finished.jpg
Finished.jpg
  952   Monday, December 19, 2022, 12:49 Carla Babcock HP-FEBIAD     HP-FEBIAD tests

Monday, December 19, 2022, 12:06 : Tomislav changed the polarity of the anode power supply last week and everything has been closed up again. The anode wire was switched to feedthru J and the short there removed. Forgot to put the short on the tube before closing the top but it should be ok for these tests since it has the resistor still installed to keep it at some potential. Pumping out gas lines.

Monday, December 19, 2022, 12:46 : Anode voltage ramped to 500V no problems. BIAS\EE\EL at 30kV\-1kV\13kV. Starting heaters ramping to TGHT=600A TBHT=290A.

Tuesday, December 20, 2022, 08:23 : Cancelled heater ramp at 500A yesterday, resuming now.

Wednesday, December 21, 2022, 14:48 : Everything ramped down


Friday, January 06, 2023, 09:27: Turbo pumps off. - AS 

  953   Wednesday, December 21, 2022, 17:06 Carla Babcock       Prep for power outage

Source and beamline power supplies turned off in EPICS

HV cage power off

Magnet ramped down and power supplies turned off manually (bira and tdk lambda)

VME crates and kepco turned off

Water lines closed

Will turn off pumps remotely later. Left PLC on

  954   Tuesday, January 03, 2023, 10:03 Carla Babcock       Recovery from power outage

Easy recovery after power outage, just had to power cycle the ground PLC IOC and the BiRa IOC.

Test stand vacuum currently pumping down again. Water and HV elements still off.

Tuesday, January 03, 2023, 11:13: Reset IG6 - Filament 2. Vacuum 7.22e-06T - AS

Tuesday, January 03, 2023, 14:00: Both Turbo pumps on.

Tuesday, January 03, 2023, 14:27: Vacuum @ 2.32e-06T

Tuesday, January 03, 2023, 14:28: FS#2 opened. Vacuum ok.

Tuesday, January 03, 2023, 14:29: FS#3 opened. Vacuum ok.

Tuesday, January 03, 2023, 14:30: FS#4 opened. Vacuum ok.

Tuesday, January 03, 2023, 14:31: FS#5 opened. Vacuum ok. Stable @ (2.24-2.32)e-06T. - AS

  956   Monday, January 16, 2023, 16:02 Aaron Schmidt HP-FEBIAD-CTL    In progressHP-FEBIAD tests

Extra wraps of foil around the center block (6) + 3 full wraps around the shield.

Monday, January 16, 2023, 15:40: Roughing.

Monday, January 16, 2023, 16:10: TP1B on.

Monday, January 16, 2023, 16:17: TP1A on.

Monday, January 16, 2023, 16:32: Bypass on BV1A/BV1B used to undo TP1A trip. IG1 on & TP up to speed now.


Tuesday, January 17, 2023, 09:35: TMS:RP2 is failing. Beamline side roughing pump.

Tuesday, January 17, 2023, 09:35: Waterline FS#5 is open. Chamber side vacuum @ 1.14e-06T.

Tuesday, January 17, 2023, 09:46: TMS:TP6 & TMS TP2 off. PV2 shut. TMS RP2 off.

Tuesday, January 17, 2023, 12:46: Manually tapped up TGHT / TBHT to 10 A. 100 V on Anode. ok.

Tuesday, January 17, 2023, 12:47: Auto-ramping TGHT / TBHT to 25 / 25 A @ 2 A per min.

Tuesday, January 17, 2023, 13:00: Auto-ramping TGHT / TBHT to 100 / 100 A @ 2 A per min.

Tuesday, January 17, 2023, 13:47 : Ramping TGHT/TBHT to 0 / 0 A @ 4A per min as the datalogger is not showing up reading.

Tuesday, January 17, 2023, 14:24: Previous data logger was off. But could be turned back on. Dataloggers swapped just in case. Reading T2 @ 68.8 C. - AS

Tuesday, January 17, 2023, 15:49: Auto-ramping TGHT / TBHT to 100 / 100 A @ 2 A per min.

Tuesday, January 17, 2023, 17:10: Auto-ramping TGHT / TBHT to 200 / 200 A @ 2 A per min.

Tuesday, January 17, 2023, 19:56: Auto-ramping TGHT / TBHT to 250 / 250 A @ 2 A per min.

Tuesday, January 17, 2023, 20:28: Auto-ramping TGHT  to 300 A @ 2 A per min.

Wednesday, January 18, 2023, 10:17: Auto-ramping TGHT to 400 A @ 2 A per min. 

Wednesday, January 18, 2023, 11:35 : Auto-ramping TGHT to 500 A @ 2 A per min.

Wednesday, January 18, 2023, 13:51 :Auto-ramping TGHT / TBHT to 600 / 300 A @ 2 A per min.

Wednesday, January 18, 2023, 16:06 : Auto-ramping down TGHT / TBHT to 580 / 270 A @ 2 A per min to stay overnight.


Thursday, January 19, 2023, 10:49: BIAS / EE / EZL @ 30 / -1.5 / 13 kV.

Thursday, January 19, 2023, 10:53: Anode @ 500 V.

Thursday, January 19, 2023, 10:54: Coil @ 50 A. Vacuum @ 1.36e-06T.

Thursday, January 19, 2023, 11:00: Auto-ramping TBHT to 290 A @ 2 A per minute.

Thursday, January 19, 2023, 11:14: Anode current @ 1.221 mA. Vacuum @ 1.52e-06T. TGHT /  TBHT @ 580 / 290 A.

Thursday, January 19, 2023, 11:24: Auto-cooling @ 2 A per min.

Thursday, January 19, 2023, 17:04: Anode voltage ramped down to 0 V.

Thursday, January 19, 2023, 17:04: Auto ramping down TGHT/TBHT to 0/ 0 A @ 2A per min.


Monday, January 30, 2023, 08:49: IG1 off. Turbo pumps off.

  957   Tuesday, January 17, 2023, 09:48 Aaron Schmidt      Problems/SolutionsTMS:RP2 Failure

Tuesday, January 17, 2023, 09:48: TMS:RP2 off. Audible failure was in progress. Also observable on the strip tool. Vacuum group contacted.

  961   Thursday, April 13, 2023, 11:07 Aaron Schmidt      In progressInstallation of new IDP-15 TMS:TP2

IDP15 Scroll Pump, Std w/ inlet.

TMS:RP2

PN: X3815-64010

Serial: MY2301SA17

Thursday, April 13, 2023, 11:04: Roughing RP2

Thursday, April 13, 2023, 11:05: Open BV6 & BV2

Thursday, April 13, 2023, 11:15: TMS:TP2 & TMS:TP6 on.

Thursday, April 13, 2023, 11:19: IG6 on.

Thursday, April 13, 2023, 12:05: Vacuum @ 1.43e-05T.

  968   Thursday, May 25, 2023, 13:47 Aaron Schmidt       Rough down empty chamber

Thursday, May 25, 2023, 13:47: Roughing.

  970   Thursday, June 08, 2023, 14:22 Aaron Schmidt       Rough down empty chamber

Thursday, June 08, 2023, 14:22: Roughing.

  972   Monday, July 10, 2023, 15:01 Aaron Schmidt       Pump down empty chamber

Monday, July 10, 2023, 15:01: Roughing.


Wednesday, July 12, 2023, 09:38: Venting both chambers. 

  973   Thursday, July 13, 2023, 07:37 Aaron Schmidt       Tests - Aurelia L

Thursday, July 13, 2023, 07:37: Chamber is vented. Beamline is vented. Interlock bypassed on TPS:IV4 - AS

  974   Thursday, July 13, 2023, 18:29 Aurelia Laxdal LP-SIS    In progressSpectrometer tests

 Pumping down: TS loaded with a LP-SIS container for spectrometer test. 

Started heating up the target container: up to 300A.

Last week: the LP container was heated up to TGHT 580A and TBHT 230A, and cooled down before the weekend. 

Pumping again (LP container in) for one more check. Last check was completed on July 26: up to 400A. 

Vented the chamber today (July 27). 

Did another test over the weekend. Currently the PSs are off and the chamber under vacuum. 

  977   Wednesday, August 16, 2023, 11:32 Aaron Schmidt       Pump down empty chamber

Wednesday, August 16, 2023, 11:32: Roughing.


Thursday, August 17, 2023, 11:01: Venting.

  979   Tuesday, August 29, 2023, 12:14 Aaron Schmidt       Pump down empty chamber

Tuesday, August 29, 2023, 12:14: Roughing.

Tuesday, August 29, 2023, 13:17: TP1B started. 

Tuesday, August 29, 2023, 13:21: TP1B on. 

Tuesday, August 29, 2023, 13:46: TP1A started. 

Tuesday, August 29, 2023, 14:00: TP1A Tripped.

Tuesday, August 29, 2023, 14:20: TP1B off. 

  981   Thursday, September 28, 2023, 13:42 Aaron Schmidt       Pump down empty chamber

Thursday, September 28, 2023, 13:40: Roughing - BB.


Tuesday, October 10, 2023, 14:08: Venting.

  985   Thursday, November 16, 2023, 09:43 Aaron Schmidt LP-SIS    In progressThermal tests

Aurelia has been testing on the ISAC TS since last week. Thermocouples are installed in the end cap, left side & the ionizer.

No elog was initiated, but much has happened.

Site wide power outage on Friday/Saturday caused problems. The TS was running at that time & was also affected. Reboots occurred on the weekend & testing resumed. IG6 was reset yesterday.

Thursday, November 16, 2023, 09:30: IV4 closed. TP6, TP2, TP1B, TP1A off. IG6 & IG1 off. PS off.


Thursday, November 16, 2023, 13:11: TP6 & TP2 restarted.


Monday, November 20, 2023, 12:06: IV4 closed. IG6 off. TP6 & TP2 off.

Monday, November 20, 2023, 12:42: Venting beamline side.

  987   Tuesday, December 12, 2023, 12:41 Aaron Schmidt      DoneSource Tray / TS inspection

Tuesday, December 12, 2023, 12:39: Visual inspection.

Source tray: OK. Minor cracks on insulator near the coil conductor. Small chip in the upper TBHT insulator as well.

Water blocks: No leaks.

Pumping: TMS:RP2 recently purged. Otherwise all TP & RP OK.

Door seals: OK.

  989   Thursday, January 18, 2024, 10:44 Aaron Schmidt      DoneThermal tests 2

December 18 - January 15. Were not logged. Placed holder. Aurelia's tests. Included thermocouples in the oven & ionizer.