  Test-Stand, Page 44 of 53  Not logged in ELOG logo
ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O#down Status Subject Text Attachments
  721   Tuesday, May 07, 2019, 13:16 Aaron SchmidtTa#58LP-SISITETM243044-4 In progress9-pin connection configuration (Using Ta#58)Ref:
https://elog.triumf.ca/TIS/Test-Stand/679
Pin configuration between top 9-pin
 HV_Tests_2019_-_AL_-_1.docxTS-2019-05-08-08-12.rgaTS-2019-05-08-14-20.rga 
  723   Wednesday, May 22, 2019, 13:47 Aaron Schmidt       Calibrated MasscorrWednesday, May 22, 2019, 13:44: Calibration
Confirmed.
New Masscorr setup:
  
  728   Friday, June 07, 2019, 16:56 Carla Babcock       TM4 source tray stateTM4 source tray left in test stand over
weekend, just the rouging pumps on. Ready
to be removed Monday morning.
  
  729   Monday, June 10, 2019, 14:34 Aaron Schmidt      DoneRemoved TM4 Source TrayMonday, June 10, 2019, 09:30: TM4 Source
Tray removed - To HC area.
  
  730   Monday, June 10, 2019, 14:35 Aaron Schmidt      DoneOptics Tray / EZL inspection.Monday, June 10, 2019, 13:00: Optics Tray
removed.
Megger'd @ 1000V on EZL and Collimator.
 20190610_135100.jpg20190610_135926.jpg20190610_135045.jpg20190610_135517.jpg 
  732   Thursday, June 13, 2019, 14:05 Aaron Schmidt      DoneSpare TGHT PS installed.Thursday, June 13, 2019, 14:04: Spare TGHT
PS installed /  tested. The old one
is to be sent out for repair.
  
  733   Wednesday, June 19, 2019, 17:25 Fernando Maldonado      DoneThermocouple connectionWednesday, June 19, 2019, 17:13  Ferran
and Fernando tested the 9-pin connector to
have a reading on a thermocouple following
  
  734   Friday, June 21, 2019, 15:12 Aaron SchmidtP2N - 1      P2N - 1 - 2019Friday, June 21, 2019, 14:48: Roughing.
Friday, June 21, 2019, 15:18: Turbo
pumps on.
  
  735   Saturday, June 22, 2019, 17:05 Luca Egoritip2n     DoneTest stand installationI opened the test stand because I forgot
to install tantalum heat shields around the
target. Everything was reinstalled as before
  
  736   Monday, June 24, 2019, 15:41 Fernando Maldonado      Problems/SolutionsTMS:Q3 polarityMonday, June 24, 2019, 15:25: Current quadrupole
polarities:
  
  737   Tuesday, June 25, 2019, 17:19 Fernando Maldonado      Problems/SolutionsBurnt cables on top of the test standTuesday, June 25, 2019, 16:15: While inspecting
the 9-pin connection with Ferran, it was
noticed how two braided cables were burnt
 20190625_154015.jpg20190625_153834.jpg20190625_165001.jpg 
  739   Wednesday, June 26, 2019, 14:41 Carla Babcocknone     Problems/SolutionsIssues with test stand wiring in service cap areaThe wiring on the top of the test stand
was burned, see entry 737.
Probable cause of this is as follows:
 isk4523d_ITSrewiring_June2019.png 
  740   Thursday, June 27, 2019, 09:51 Fernando Maldonado      Problems/SolutionsMelted cables changedSee elog 737 

  
  741   Tuesday, July 02, 2019, 18:25 Fernando Maldonado      DoneBlank on FEBIAD gas line installed Tuesday, July 02, 2019, 18:24: A
blind is installed  on the FEBIAD gas
line (see attached picture)  to
 20190702_182254.jpg 
  742   Thursday, July 04, 2019, 15:15 Aaron SchmidtP2N - 1      P2N - 1 - 2 - 2019Screws instead of rivets on target leg.
Insulator changed.
Thursday, July 04, 2019, 15:14: Roughing
  
  743   Thursday, July 04, 2019, 15:16 Aaron Schmidt      Problems/SolutionsTBHT insulator changedThursday, July 04, 2019, 15:00: TBHT insulator
was swapped out on the source tray side. 
  
  744   Monday, July 08, 2019, 09:20 Luca Egoritip2n1 ITE   In progressp2n heating test(see entry 742)
 
p2n target heated over the weekend
 Capture.PNGCapture1.PNG 
  745   Monday, July 15, 2019, 15:59 Fernando MaldonadoP2N     DoneRe-wiring on service cap.Monday, July 15, 2019, 15:54 : TBHT high
current cables moved to Coil feedthroughs.
Coil high current cables moved to
  
  746   Tuesday, July 16, 2019, 10:28 Fernando MaldonadoP2N      P2N 1200 A testTuesday, July 16, 2019, 10:27: The idea
of this run is to have the full 600 A from
TGHT and the full 600 A from TBHT.
  
  747   Friday, July 19, 2019, 13:48 Fernando Maldonado      Problems/SolutionsRMP0A and FC6 gains signal redirection to another channelAfter submitting a fault report (FR - ISAC
Fault 12461) a Work Permit was issued (WP
- C2019-07-19-1),
  