  Test-Stand, Page 41 of 53  Not logged in ELOG logo
Entry  Wednesday, February 10, 2021, 09:49, Aaron Schmidt, , LP-SIS, , , 44691-8, 44378-2 / 44378-3, Failed, Energy spread calibration with SIS spark_inside_chamber_roof.pngspark_inside_chamber_front_view.png
Note* target has a ring on the TGHT - Right leg. EE & PE placed. Target to HS OL - OK.
Wednesday, February 10, 2021, 09:37: Roughing.
Wednesday, February 10, 2021, 09:45: Bypass / Force applied on IG1 to test Anode.
Entry  Monday, February 01, 2021, 08:38, Fernando Maldonado, , LP-SIS, , , 44139-10 , 44378-2 , Failed, Energy spread calibration ESC_-_Jan_29_start.docxESC_-__Feb_3_start.docxER-580-230-30kV-m7.txtEr-580-230-30kV-m133.txt
Monday, February 01, 2021, 08:38 : The anode seems to be shorted but we can still test the  amount of dispersion at the image position, and
correlate with energy spread.
Monday, February 01, 2021, 11:27: Bias/EZL/EE @ 30/0/1.5 kV. 
Entry  Monday, June 04, 2012, 11:40, Anders Mjos, , , , , , , In progress, Empty chamber 
HS water lines blanked.
Monday, June 04, 2012, 11:40: Roughing.
Monday, June 04, 2012, 11:58: Starting turbos. 
Entry  Monday, June 16, 2014, 09:12, Anders Mjos, , , , , , , In progress, Empty chamber 
Monday, June 16, 2014, 09:12: Roughing

Tuesday, June 17, 2014, 14:38: Venting 
Entry  Tuesday, July 08, 2014, 09:05, Anders Mjos, , , , , , , In progress, Empty chamber 
Tuesday, July 08, 2014, 09:05: Roughing
Tuesday, July 08, 2014, 13:23: Starting turbos
Tuesday, July 08, 2014, 13:30 : Turbos at speed
Entry  Wednesday, July 23, 2014, 14:34, Anders Mjos, , , , , , , In progress, Empty chamber 
Wednesday, July 23, 2014, 14:34: Roughing
Wednesday, July 23, 2014, 15:03: Starting turbos.
Wednesday, July 23, 2014, 15:11: Turbos at speed
Entry  Tuesday, March 24, 2015, 09:50, Anders Mjos, , , , , , , In progress, Empty chamber 
Roughed down on Friday 20th
Tuesday, March 24, 2015, 09:49: Turbos started
Tuesday, March 24, 2015, 09:59: Turbos at speed. Vacuum at 2.8E-6 T
Entry  Monday, May 02, 2022, 14:10, Aaron Schmidt, , P2N-SIS, , , , , , Empty Chamber PS test. 
No P2N is loaded. Testing the power supplies.
Tuesday, May 03, 2022, 10:07
In the past few days, the ITS has been reconfigured for P2N operation:
Entry  Monday, June 28, 2021, 09:22, Aaron Schmidt, , , , , , , , Empty Chamber 
Monday, June 28, 2021, 09:22: Roughing.
Monday, June 28, 2021, 10:10: TP1B on.
Monday, June 28, 2021, 10:22: TP1A on (Tripped)
Entry  Tuesday, July 16, 2013, 15:39, Anders Mjos, , , , , , , , Empty 
Tuesday, July 16, 2013, 15:39: Roughing
Tuesday, July 16, 2013, 16:01: Starting turbos.
Tuesday, July 16, 2013, 16:10: Turbos at speed.
Entry  Tuesday, October 11, 2016, 14:55, Anders Mjos, , , , , , , In progress, Empty 
Breaker tripped during roughing. Removed exhaust line during first 2 min.
Tuesday, October 11, 2016, 14:55: Turbos at speed. Vacuum at 1.0E-6 T

Wednesday, October 12, 2016, 12:09: Ion gauge & Turbo pumps off.
Entry  Friday, August 12, 2016, 14:40, Aaron Schmidt, , , , , , , Problems/Solutions, Emittance scanner communications 
Wednesday, July 27, 2016, 16:06:  Spark around 15:10 or 16:05
Emittance rig communications affected.
Enter 100 on Dac -- Reads: -500
Entry  Friday, June 24, 2016, 08:07, Aaron Schmidt, , , , , , , , Emittance scanner check/repair. 
Friday, June 24, 2016, 08:06: Ion gauge IG6 OFF. Turbo pumps TP6 and TP2 off.
Friday, June 24, 2016, 09:58: Venting.
Friday, June 24, 2016, 10:17: Remove emittance scanner for inspection.
Entry  Wednesday, July 06, 2016, 10:42, Anders Mjos, , , , , , , Problems/Solutions, Emittance scanner check/repair. 
Dave Morris increased the current from ~ 1 A to ~2.5 A. This seem to solve the problem with the in/out drive of the emittance meter
Entry  Wednesday, June 06, 2018, 14:01, Aaron Schmidt, , , , , , , Problems/Solutions, Emittance scanner (E-rig) communication issues. 
Wednesday, June 06, 2018, 13:50:
It was noted yesterday during the TM2 Source HV tests that the E-rig was not running accordingly through the beam.
Upon turning on the PS, there a 45 second or so delay before the needle drops to the right at +500V and the PS no longer responds. (similar issue
Entry  Wednesday, March 04, 2020, 17:15, Fernando Maldonado, , , , , , , Problems/Solutions, Emittance rig communication 
Wednesday, March 04, 2020, 17:13: EPICS page indicated a sucesful scan but data was empty.
Wednesday, March 04, 2020, 17:13: Power suppply didn't respond to the voltage sweep
Wednesday, March 04, 2020, 17:14: Problem most likely similar to elog entry 531.
Entry  Wednesday, March 10, 2021, 14:57, Aaron Schmidt, , HP-FEBIAD, , , , 42752-5, In progress, Emittance meter test with FEBIAD 
Wednesday, March 10, 2021, 14:54: Roughing.
Wednesday, March 10, 2021, 14:57: BV1A open.

Thursday, March 11, 2021, 09:41: TP1B on. 
Entry  Wednesday, February 05, 2014, 11:27, Anders Mjos, , , , , , , Problems/Solutions, Emittance Rig installation Spacers_Installed.jpgEmittance_Rig_Inside.jpgEmittance_Rig_Outside.jpg
Wednesday, February 05, 2014, 11:27 : Stopped turbos

    2x spacers ITD0468 1/8" THK installed to shift the wire scanner screen closer to the wire scanner. (ITD0469 1/16" THK spacers
not used).
    Emittance Rig installed. Manually actuated from out -> in -> out position. No interference observed.
    Replaced two
Entry  Friday, March 21, 2014, 14:12, Anders Mjos, , , , , , , Problems/Solutions, Elevated backing pressure on ISAC Test Stand TMS:RP2 TMSCG2_2014-03-21.png
The performance of the roughing pump has gradually gone down. Notably after the system has been vented. See attached screenshot from the archiver.
E-fault 7258.
 
    Reply  Thursday, June 12, 2014, 09:28, Anders Mjos, , , , , , , Problems/Solutions, Elevated backing pressure on ISAC Test Stand TMS:RP2 


    
        
            Anders Mjos wrote:
        
        
            
            The performance of the roughing pump has gradually gone down. Notably after the system has been vented.