Entry  Monday, January 16, 2023, 16:02, Aaron Schmidt, , HP-FEBIAD-CTL, , , , , In progress, HP-FEBIAD tests 
Extra wraps of foil around the center block (6) + 3 full wraps around the shield.
Monday, January 16, 2023, 15:40: Roughing.
Monday, January 16, 2023, 16:10: TP1B on.
Entry  Thursday, February 18, 2021, 15:15, Fernando Maldonado, , , , , , , Done, HLA tests 
Thursday, February 18, 2021, 15:01: With the help of Spencer Kiy, we tested the proper communication from python to epics.
Getting TSP:Q1 PV: successful both from the web application and jupyter notebook.
Setting TSP:Q1 PV: successful from the web application, failed jupyter notebook.
Entry  Friday, February 12, 2021, 12:16, Fernando Maldonado, , , , , , , Problems/Solutions, Grounding collimator cable from outside 20210212_121227.jpg
 Friday, February 12, 2021, 12:13: Since the collimator is not used, Carla and I installed a BNC short outside the cage. See picture.
Entry  Monday, September 09, 2013, 09:14, Anders Mjos, , , , , , , Problems/Solutions, Ground Electrode cleaned Dirty_GE.pdf
Monday, September 16, 2013, 17:04: Cleaned GE. Copper shavings were removed from below the guide pins for the Heat Shield. The shavings were sitting
on top of the aluminum support.
Entry  Monday, August 14, 2023, 12:11, Aaron Schmidt, , LP-SIS, , , 45220-11, 45235-3, , Graphite target test 2 (C2023B) Graphitetesting_Aug102023.xlsx
Graphite experiment insert 1: ID GR-230515, WO#45220-11. https://elog.triumf.ca/TIS/Evaporator_2/622
New disc form. End caps expanded, no Re foil installed. 4 heat shields wrapped around the oven.
Monday, August 14, 2023, 12:04: Roughing.
Entry  Wednesday, August 09, 2023, 14:29, Aaron Schmidt, , LP-SIS, , , 45220-6, 45235-3, In progress, Graphite target test 1 (C2023A) Graphite_target_45220-6.docxGraphitetesting_Aug102023.xlsx
Graphite
experiment 2: ID Gr-230601, WO#45220-6 ( https://elog.triumf.ca/TIS/Evaporator_2/598
Entry  Friday, March 01, 2019, 14:51, Aaron Schmidt, , LP-FEBIAD, , , , , , Gas lines test & Emissions measurement prep gas-lines-changes.jpgGas_line_backing_pump_test_2019.docxTS-2019-03-05-09-45.rgaTS-2019-03-06-08-00.rga
Friday, March 01, 2019, 14:50:
SV5 replaced with a new valve.
SV1 disconnected from the He line and linked to the mini pump line.
Entry  Tuesday, July 17, 2012, 10:10, Anders Mjos, , , , , , , Problems/Solutions, Gas lines leak checked - air supply leak on manifold 
Leak found on the Ne supply line. 1E-4 - 1E-5 range. Replaced fittings. Had to use one brass piece. Leak rate 6E-9 (probably due to Ne response). No
response to He.
Leak rate around low E-8 with regulation valve open.
Entry  Friday, August 10, 2012, 14:08, Rick Maharaj, , , , , , , , Gas line pump 
Gas line vacuum pump reinstalled after fitting was modified to receive a standard swagelok connector. The vacuum line was plumbed using 1/4" copper
tube (not Stainless) for the the ability to flex and manipulate the line for pump removal and and insertion.
Entry  Friday, February 22, 2019, 11:11, Aaron Schmidt, , LP-FEBIAD, , , , , , Gas line backing pump tests 
Backing "mini pump" testing.
-Open gas lines & auto ramp (If using HV, close up the back)
-HV on
Entry  Wednesday, December 02, 2020, 16:18, Fernando Maldonado, , , , , , , Done, Gas delivery system upgrade 
Yesterday, December 1st, I successfully installed and tested the gas system inside the faraday cage.
The changes performed were as follows:

    Remove He gas tank (to make room for new tank)
    Remove calibrated leak to connect new gas line
    Remove convectron
    Reply  Thursday, January 14, 2021, 08:31, Fernando Maldonado, , , , , , , In progress, Gas delivery system upgrade new-gauge.png


    
        
            Fernando Maldonado wrote:
        
        
            
            Yesterday, December 1st, I successfully installed and tested the gas system inside the faraday cage.
Entry  Wednesday, June 07, 2017, 12:49, Aaron Schmidt, , , , , , , , Gas bottles 
 Gas bottles for FEBIAD testing were exchanged yesterday around 1:30. One Neon & one Argon bottle were removed.
Two Neon bottles were added.
Entry  Tuesday, October 10, 2017, 13:10, Aaron Schmidt, , , , , , , , Gas bottles 
Tuesday, October 10, 2017, 09:30:  Install/swap gas bottles. Elog.
Removed smallest Neon leak. Neon Bottle Serial #11231. Leak rate calibrated @ 1.59e-07 atm*CC/sec (02/09/2016)
In use:
Entry  Thursday, December 18, 2014, 14:34, Anders Mjos, , , , , , , Problems/Solutions, GE cooling water lines disconnected 
 In preparation for leak check
Thursday, December 18, 2014, 16:37: Reconnected after leak check
Monday, December 22, 2014, 11:02: Water opened.
Entry  Monday, March 02, 2020, 14:42, Aaron Schmidt, Ta#60, LP-SIS, , , 44139-13, 43515-5, In progress, Full TS testing w/ HV using Ta#60 
Monday, March 02, 2020, 14:36: Roughing.
Monday, March 02, 2020, 15:08: Turbo pumps on.

Remove HV cage (top). Reroute FS#3 back to cool EE
Entry  Tuesday, December 01, 2020, 17:04, Carla Babcock, , , , , , , Problems/Solutions, Found another burned jumper cable 20201201_115557.jpg
Between feedthroughs F (magnet coil) and B (tube heater negative), I found a jumper with two resistors that has been burned up. I am not sure when this
happened, but it would be good to review the overall setup of the service cap wiring in the new year.
The cable connected to feedthrough Q where the multipin sits also looks burned.
Entry  Thursday, January 16, 2014, 15:00, Anders Mjos, , , , , , , Problems/Solutions, Flow and temperature meter Vortex_Flow_Meter_Config.docx
Flow and temperature meter previously installed on cooling circuits. See attachment for details.
Typical values at 95 psi in and 10 psi out. Cyclotron off.

    
        
            Device
Entry  Wednesday, September 07, 2016, 15:51, Aaron Schmidt, , , , , , , , Flexible waterlines test. Flexible_Line_Test.docxTS-2016-09-08-08-47.rga
Wednesday, September 07, 2016, 15:35: Roughing

Thursday, September 08, 2016, 08:33: Turbo pumps started.
Thursday, September 08, 2016, 08:38: Ion gauge on. TP1B @ speed 42 KRPM.
Entry  Monday, September 26, 2011, 16:14, Anders Mjos, , , , , , , Problems/Solutions, Fixed leak on water line for HS, added Kapton insulation Water_Leak.pdfKapton.pdf

    While testing SiC#26 a leak was discovered on the water line to the heat shield. The leak was in the right joint (see attachment). The heat
shield water lines were removed from the test stand and repaired in the Machine Shop. 
    Kapton was added to the FEBIAD coil line to prevent
it from shorting to the target heater line (see attachment).