464
|
Thursday, September 17, 2015, 14:05 |
Anders Mjos | Test Target | LP-SIS | | | | | In progress | New centre block test |
|
|
|
463
|
Monday, September 14, 2015, 08:38 |
Anders Mjos | | | | | | | Problems/Solutions | RP2 increased pressure | e-fault submitted and vacuum group
(Edi) notified.
Monday, September 14, 2015, 09:33: |
|
|
462
|
Friday, September 11, 2015, 11:43 |
Anders Mjos | Ta#46 | HP-SIS | ITE | TM4 | | | Done | Ta#46 conditioning | EE is ST-200 material (AlN)
Friday, September 11, 2015, 11:0:
Roughing |
|
|
461
|
Wednesday, September 09, 2015, 08:54 |
Anders Mjos | | | | | | | In progress | Venting | Wednesday, September 09, 2015, 08:53:
Turbos stopped
Friday, September 11, 2015: |
|
|
460
|
Saturday, August 29, 2015, 14:33 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted IOC after power outage | Saturday, August 29, 2015, 15:50:
Turbos started |
|
|
459
|
Monday, August 10, 2015, 18:01 |
Anders Mjos | | LP-SIS | | | | | In progress | Testing new center block target | Installed thermocouples:
T1: TGHT tube left side, inside
T2: TBHT restraint |
|
|
458
|
Tuesday, August 04, 2015, 13:37 |
Anders Mjos | | | | | | | Problems/Solutions | Equipment for outgassing measurements removed | |
|
|
457
|
Monday, July 13, 2015, 17:19 |
Anders Mjos | | LP-SIS | | | | | In progress | SIS Cup insulator clamping test | Monday, July 13, 2015, 17:09: Roughing
Monday, July 13, 2015, 17:51: Turbos
started |
|
|
456
|
Monday, July 06, 2015, 14:26 |
Anders Mjos | | | | | | | | Pumping down empty chamber | Monday, July 06, 2015, 14:26: Roughing
Wednesday, July 08, 2015,
09:26: Venting |
|
|
455
|
Monday, July 06, 2015, 09:29 |
Anders Mjos | | | | | | | Problems/Solutions | Replaced out gassing gauge on the backing line | |
|
|
454
|
Tuesday, June 30, 2015, 14:51 |
Anders Mjos | ZrC#7 | LP-SIS | | TM2 | 41177-2 | | In progress | ZrC#7 Conditioning 2 | Tuesday, June 30, 2015, 14:51: Roughing
Tuesday, June 30, 2015, 16:14: Started
turbos. CG1 at 0.075 T |
|
|
453
|
Monday, June 29, 2015, 16:51 |
Friedhelm Ames | | | | | | | Problems/Solutions | TSG:BV1B closed | found TSG:TP1B tripped off. Closed TSG:BV1B
as pressure at TSG:iG1 was rising. Pressure
is coming down again. |
|
|
452
|
Thursday, June 25, 2015, 09:00 |
Anders Mjos | | LP-FEBIAD | | TM2 | | | | TM2 FEBIAD Test | Thursday, June 25, 2015, 09:00: Water on
HS. No vacuum response.
Thursday, June 25, 2015, 11:48: Started |
|
|
451
|
Monday, June 22, 2015, 15:49 |
Anders Mjos | | | | | | | In progress | Installed new 9-pin feed through | No wires connected yet.
Monday, June 22, 2015, 15:48: Roughing
Tuesday, June 23, 2015, 09:05: |
|
|
450
|
Monday, June 15, 2015, 14:09 |
Anders Mjos | ZrC#7 | LP-SIS | | TM2 | 41177-1 | | In progress | ZrC#7 Conditioning | Monday, June 15, 2015, 14:05 Roughing
Monday, June 15, 2015, 14:39: Turbos
started. |
|
|
449
|
Monday, June 15, 2015, 14:07 |
Anders Mjos | | | | | | | Problems/Solutions | Test Stand Source Tray installed | Monday, June 15, 2015
Remaining items to do
ANODE wire not yet attached
|
|
|
448
|
Wednesday, June 03, 2015, 09:35 |
Anders Mjos | | | | | | | Problems/Solutions | PLC upgrade | Wednesday, June 03, 2015, 09:35: TP6 and
TP2 off
Wednesday, June 03, 2015, 10:15: |
|
|
447
|
Wednesday, May 27, 2015, 14:19 |
Anders Mjos | | LP-FEBIAD | | TM2 | | | In progress | Re-testing new TM2 Source Tray | Wednesday, May 27, 2015, 14:19: Roughing
Wednesday, May 27, 2015, 14:50: Turbos
started |
|
|
446
|
Monday, May 25, 2015, 14:40 |
Anders Mjos | SiC#31 | HP-SIS | ITW | TM4 | 38817-7 | | In progress | SiC#31 Conditioning | Monday, May 25, 2015, 14:35: Rouging
Monday, May 25, 2015, 15:05: Turbos
started. |
|
|
445
|
Thursday, May 21, 2015, 17:38 |
Anders Mjos | | | | | | | Problems/Solutions | Installed equipment for measuring outgassing rate | A gauge and a valve was installed
on the roughing line to the large turbo pump |
|
|