  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject
  564   Wednesday, January 25, 2017, 09:48 Aaron Schmidt    41882-441751-6DoneOut gas Heat Shield for Target cleaning test

No EE. Insulators, gripper arms, and blank EE plate included

-New grounded 9 pins included in brackets

-TGHT included to out gas Heat shield


Wednesday, January 25, 2017, 09:45: Roughing

Wednesday, January 25, 2017, 10:04: Turbo pumps started.

Wednesday, January 25, 2017, 11:26: Ion gauge & RGA on.


Thursday, January 26, 2017, 08:25: RGA restarted. (Fatal communication error)

Thursday, January 26, 2017, 08:32: Water lines opened. No response on RGA. Vacuum stable @ 1.44e-07T.

Thursday, January 26, 2017, 08:35: Power/sources on.

Thursday, January 26, 2017, 08:37: Auto-ramping TGHT to 580A @ 2A per min. Vacuum @ 1.44e-07T.

  Device Temp
[C]
 Flow
[lpm]
 HS + MSP 23.5 4.02
 TBHT 23.3 3.13
 COIL + EE 23.3 5.18
 TGHT  23.4 5.78

Thursday, January 26, 2017, 13:11: RGA restarted. (Fatal communication error)

Thursday, January 26, 2017, 15:20: RGA restarted. (Fatal communication error)

Thursday, January 26, 2017, 15:26: RGA being shut down. (Fatal communication error)

Thursday, January 26, 2017, 15:31: RGA Restarted.


Friday, January 27, 2017, 08:06: RGA running ok.

  Device Temp
[C]
 Flow
[lpm]
 HS + MSP 30.2 4.06
 TBHT 21.2 3.14
 COIL + EE 21.4 5.11
 TGHT  23.3 5.78

Friday, January 27, 2017, 15:23: Auto-cooling started @ 2A per min.


Monday, January 30, 2017, 08:02: RGA off. Ion Gauge off. Turbo pumps off.

Monday, January 30, 2017, 08:05: Power/sources off. Water lines purged.

Monday, January 30, 2017, 09:09: Venting.

  563   Tuesday, January 24, 2017, 14:14 Aaron Schmidt       Calibrated leak tanks removed
Tuesday, January 24, 2017, 13:30: Calibrated leak tanks of Argon & Neon removed. Both old Neon tanks were re-installed in their place.
  562   Monday, January 23, 2017, 15:30 Aaron Schmidt       Pump down empty chamber.

Monday, January 23, 2017, 15:30: Roughing


Wednesday, January 25, 2017, 09:05: Venting

  561   Friday, January 20, 2017, 08:45 Aaron Schmidt      Problems/SolutionsTSG:TP1A & TSG:BV1A tripped

Friday, January 20, 2017, 08:25: TSG : TP1A and TSG : BV1A were noticed to be tripped around 6am.

Friday, January 20, 2017, 08:42: Bypass to restart TSG : TP1A and TSG : BV1A. TP1A is at speed.

      ------      

Continue to monitor.

  560   Thursday, January 19, 2017, 13:23 Anders Mjos      Problems/SolutionsTSH:UHV1 remvoed

Anders Mjos wrote:

The variable leak rate valve will be used for TM3 HV spark tests in TCS

 Variable leak valve returned yesterday (2017-01-18). New calibrated leaks installed. Ar and Ne. System leak checked OK after.

  559   Wednesday, January 18, 2017, 09:23 Aaron SchmidtTa TestLP-FEBIAD  39530-3 In progressTri-Coil FEBIAD for testing

Wednesday, January 18, 2017, 09:22: Roughing

Wednesday, January 18, 2017, 09:41: Turbo pumps started.

Wednesday, January 18, 2017, 11:01: Ion gauge on.


Thursday, January 19, 2017, 08:15: Water lines opened. No response on RGA. Vacuum stable @ 1.70e-07T.

Thursday, January 19, 2017, 08:55: Power/Sources on. BIAS/EZL/EE @ 30/15/1.5 kV . Coil @ 50 A . Anode @ 200 V.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 24.9 3.99
 TBHT 24.8 3.15
 COIL + EE 24.7 5.16
 TGHT  24.7 5.05

Thursday, January 19, 2017, 08:59: IV4 opened. Auto ramping TGHT / TBHT to 580 / 290 A @ 2A per min.


Friday, January 20, 2017, 08:25: TSG : TP1A and TSG : BV1A were noticed to be tripped around 6am.

Friday, January 20, 2017, 08:42: Bypass to restart TSG : TP1A and TSG : BV1A. TP1A is at speed.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 34.1 3.99
 TBHT 25.0 3.19
 COIL + EE 24.7 5.19
 TGHT  26.5 5.05

 

Friday, January 20, 2017, 11:48:  Auto ramping  TBHT to 320 A @ 2A per min.

Friday, January 20, 2017, 15:51: Coil @ 100A


Saturday, January 21, 2017, 11:00: Increased TB HT voltage limit to 2.75 V. TBHT current went back up from 313 to 319 A. -AM


Monday, January 23, 2017, 10:08: Argon Valve closed.

Monday, January 23, 2017, 10:33: Neon Valve closed.

Monday, January 23, 2017, 11:00: Auto-cooling @ 4A per min. Coil reduced from 100 A to 50 A

Monday, January 23, 2017, 13:32: Power/sources off.

Monday, January 23, 2017, 13:35: RGA off. IV4 closed. Ion gauge off. Turbo pumps off.

 Monday, January 23, 2017, 14:45: Venting

  558   Tuesday, January 03, 2017, 08:27 Aaron Schmidt       Pump down empty chamber. (Restart. Post holidays)

Tuesday, January 03, 2017, 08:26: TSG : RP1 & TMS : RP2 restarted.


Wednesday, January 04, 2017, 11:18: TSG : PV1 & TMS : PV2 opened.

Wednesday, January 04, 2017, 11:19: TSG : BV1A & TSG : BV1B opened. TMS : BV2 & TMS : BV6 open.

Wednesday, January 04, 2017, 11:25: Turbo pumps TSG : TP1A & TP1B on. Monitor startup.

Wednesday, January 04, 2017, 11:31: TSG : IG1 on. TP1B @ speed.

Wednesday, January 04, 2017, 11:34: TSG : TP1A @ speed

Wednesday, January 04, 2017, 11:35: Turbo pumps TMS : TP2 & TP6 on. Monitor Startup.

Wednesday, January 04, 2017, 11:40: Both Turbo pumps @ speed. TMS : IG6 on.


Friday, January 13, 2017, 08:49: Ion gauge off, Turbos off.


Wednesday, January 18, 2017, 08:28: Venting.

  557   Wednesday, November 30, 2016, 10:16 Aaron Schmidt       Pump down empty chamber. (Close off for holidays)

Wednesday, November 30, 2016, 10:16: Roughing

Wednesday, November 30, 2016, 11:05: Turbo pumps on.

Wednesday, November 30, 2016, 11:13: Ion gauge on.


Thursday, December 15, 2016, 09:19: TMS : IG6 off. TSG : IG1 off.

Thursday, December 15, 2016, 09:20: TMS : BV6 & BV2 off. TSG : BV1A, & BV1B off. Turbo pumps TMS : TP6 & TP2 off. TSG : TP1B & TP1A off.


Friday, December 16, 2016, 07:59: Roughing pumps shut down. Test stand closed for the holidays.

  556   Wednesday, November 30, 2016, 07:25 Aaron Schmidt       Camera Container test 3.

Wednesday, November 30, 2016, 07:23: Venting

Wednesday, November 30, 2016, 08:35: Roughing.

Wednesday, November 30, 2016, 09:01: RGA on. Turbos @ speed. Ion gauge on.

Wednesday, November 30, 2016, 09:35: RGA off. Ion gauge off. Turbo pumps off.

Wednesday, November 30, 2016, 09:47: Turbo pumps were internally vented. Venting continued.

  555   Tuesday, November 29, 2016, 11:20 Anders Mjos      Problems/SolutionsTSH:UHV1 remvoed

The variable leak rate valve will be used for TM3 HV spark tests in TCS

  554   Monday, November 28, 2016, 15:39 Aaron Schmidt      In progressPump down empty chamber/Check Exhaust

Monday, November 28, 2016, 15:35: Begin roughing. Monitor exhaust mesh cover. 

*Cover was found on the ground earlier today and re-attached*

 Monday, November 28, 2016, 15:55: Exhaust mesh OK. Roughing continued.


Tuesday, November 29, 2016, 14:55: Test partially vented. @ around 550 T. Roughing restarted. Test delayed until tomorrow.


Wednesday, November 30, 2016, 07:23: Venting

  553   Friday, November 25, 2016, 14:28 Anders Mjos       Camera Container test 2

Friday, November 25, 2016, 14:28: Roughing

Friday, November 25, 2016, 14:47: Turbos started

Friday, November 25, 2016, 14:56: Turbos at speed. Vacuum at 6.4E-6 T. RGA on


Monday, November 28, 2016, 08:45: Ion gauge & Turbo pumps off.

Monday, November 28, 2016, 15:02: Venting.

Monday, November 28, 2016, 15:32: Camera removed & bagged.

  552   Thursday, November 24, 2016, 10:39 Aaron Schmidt      Problems/SolutionsTMS:TP2

Thursday, November 24, 2016, 08:05: Whining sound (high pitch) heard from TMS:TP2

Thursday, November 24, 2016, 10:37: Sound fades in and out roughly every 3-5 minutes. Vacuum group notified. Monitor.

Thursday, November 24, 2016, 15:21: Vent tomorrow AM as per Vacuum group. Edi.

Thursday, November 24, 2016, 15:38: Turbo  pumps TMS:TP6 & TMS:TP2 were turned of. Backing valves closed. Ion gauge IG6 also off.

Thursday, November 24, 2016, 16:34: Two short vent bursts. - AM


Friday, November 25, 2016, 10:21: Venting -AM

Friday, November 25, 2016, 11:00: Pump being replaced

 Friday, November 25, 2016, 14:01: Roughing

Friday, November 25, 2016, 14:40: Turbos started.

Friday, November 25, 2016, 14:45: Turbos at speed. Vacuum at 1.9E-5 T

*** Note *** : One of the copper cooling lines was leaking. The line was fixed. Monitor.


Monday, November 28, 2016, 08:47: Turbo pump operating well. No leaks detected on cooling lines.

  551   Thursday, November 24, 2016, 10:36 Aaron Schmidt       Camera Container test 1.

Thursday, November 24, 2016, 10:15: Discuss w/ Aurelia. Camera container filled with Argon. Place under Vacuum, monitor w/ RGA.

Thursday, November 24, 2016, 11:43:Pump down started. Camera and case placed near RGA.

Thursday, November 24, 2016, 12:42: Turbo pumps started

Thursday, November 24, 2016, 12:51: Turbo pumps at speed. RGA on

*Note: Nitrogen Anomaly noted on RGA and in report.*


Friday, November 25, 2016, 10:11 : Stopped turbos. RGA off. -AM

Friday, November 25, 2016, 11:10: Venting -AM

  550   Wednesday, November 16, 2016, 10:50 Aaron Schmidt       Pump down empty chamber.

Wednesday, November 16, 2016, 10:50: Begin roughing.

Wednesday, November 16, 2016, 11:52: Turbo pumps on.

*Note* Unusual sound noticed right at the start up of TSG : TP1B. It was first noticed prior to venting UC#18. The sound only lasts 10-15 seconds within a minute of starting the pump. An odd whine with tapping sound. Operation is otherwise normal, but will continue to monitor the pump.

Wednesday, November 16, 2016, 11:57: Ion gauge on.

Wednesday, November 16, 2016, 12:03: Both pumps are at speed


Thursday, November 24, 2016, 10:08: Ion gauge & Turbo pumps off.

Thursday, November 24, 2016, 11:07: Venting.

  549   Thursday, October 27, 2016, 13:37 Aaron SchmidtUC#18LP-SISITWTM2 41751-3In progressConditioning Heat shield for UC#18

Thursday, October 27, 2016, 13:36: Roughing.

Thursday, October 27, 2016, 14:27: Turbo pumps started.

Thursday, October 27, 2016, 14:33: Ion gauge on.

Thursday, October 27, 2016, 14:35: Both Turbo pumps at speed.

Thursday, October 27, 2016, 16:00: RGA on.


Friday, October 28, 2016, 07:57: Water lines opened. No response on RGA. Vacuum stable @ 2.80e-07T.


Monday, October 31, 2016, 09:42: Power/sources on.

 Monday, October 31, 2016, 09:43: Auto-ramping TGHT to 500 A @ 2A per min.

Device Temp
[C]
 Flow
[lpm]
 HS + MSP 26.3 3.88
 TBHT 26.1 3.10
 COIL + EE 26.0 5.03
 TGHT 26.0 5.67

Monday, October 31, 2016, 14:46: TGHT @ 500 A, looks ok. Auto-ramping TGHT to 580 A @ 2A per min.

Monday, October 31, 2016, 15:28: TGHT @ 580 A. 


Device Temp
[C]
 Flow
[lpm]
 HS + MSP 35.3 3.96
 TBHT 26.1 3.08
 COIL + EE 26.1 5.05
 TGHT 28.2 5.67

Wednesday, November 02, 2016, 08:23: Auto-cooling TGHT @ 2A per min.

Wednesday, November 02, 2016, 13:15: Auto-cooling complete.


Thursday, November 03, 2016, 08:40: Sources/power off.

Thursday, November 03, 2016, 08:42: Water lines purged.


Monday, November 07, 2016, 08:08: RGA off. Ion gauge off. Turbo pumps off.


Tuesday, November 08, 2016, 08:07: Turbo pumps restarted. Removal not yet required.

Tuesday, November 08, 2016, 08:13: Ion gauge switched on.


Wednesday, November 16, 2016, 08:05: Ion Gauge off. Turbo pumps off.

Wednesday, November 16, 2016, 09:45: Venting.

  548   Monday, October 24, 2016, 16:02 Aaron Schmidt      Problems/SolutionsPump down empty chamber/Clean Exhaust/Test

Monday, October 24, 2016, 15:45: Remove metal mesh covering roughing pump exhaust.

Clean out mesh (3/4"-5/8" thick w/ layers of dust/material).

Monday, October 24, 2016, 15:52: Roughing 710.0 T.

Monday, October 24, 2016, 15:54: BV1B opened.

Monday, October 24, 2016, 16:00: Rouging 2.0 T.

Monday, October 24, 2016, 16:10: Turbo pumps available.


Tuesday, October 25, 2016, 08:08: Venting.

Tuesday, October 25, 2016, 08:40: Doors open.

Tuesday, October 25, 2016, 08:50: Roughing.

Tuesday, October 25, 2016, 08:51: Doors sealed for roughing.

Tuesday, October 25, 2016, 08:52: BV1B opened.

Tuesday, October 25, 2016, 09:10: Turbo pumps available & started.

Tuesday, October 25, 2016, 09:20: Ion gauge on.


Thursday, October 27, 2016, 08:35: Ion Gauge & Turbo pumps off.

Thursday, October 27, 2016, 11:44: Venting.

  547   Tuesday, October 18, 2016, 13:29 Aaron SchmidtTa#50LP-SISITETM441790-541751-1In progressConditioning Ta#50

Tuesday, October 18, 2016, 13:22: Roughing.

Tuesday, October 18, 2016, 13:46: Turbo pumps started.

Tuesday, October 18, 2016, 13:52: Ion gauge on.

Tuesday, October 18, 2016, 13:54: Both turbo pumps at speed.

Tuesday, October 18, 2016, 15:05: RGA on.


Wednesday, October 19, 2016, 08:46: Power/Sources on

Wednesday, October 19, 2016, 08:49: Waterline opened. No response on RGA. Vacuum stable @4.40E-7T

Wednesday, October 19, 2016, 08:57: BIAS / EZL / EE @ 30 / 13 / 1.5 kV .

Wednesday, October 19, 2016, 08:58 : IV4 opened.

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 27.9 3.90
 TBHT 27.7 3.06
 COIL + EE 27.6 5.08
 TGHT  27.7 5.70

Wednesday, October 19, 2016, 09:01: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.

Wednesday, October 19, 2016, 11:50: TMS:FC0 moved out & TMS:RPM0B began scanning continuously on their own. Monitor.

Wednesday, October 19, 2016, 14:45: RGA Restarted.

Wednesday, October 19, 2016, 15:25: RGA Restarted (Unable to save 14:45 Startup)


Friday, October 21, 2016, 13:27: Auto Cooling @ 2A per min

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 37.3 3.92
 TBHT 28.2 3.07
 COIL + EE 27.9 5.07
 TGHT  29.8 5.62

Friday, October 21, 2016, 15:39: IV4 Closed


Monday, October 24, 2016, 09:10:

 Device Temp
[C]
 Flow
[lpm]
 HS + MSP 28.1 3.95
 TBHT 28.2 3.10
 COIL + EE 27.7 5.04
 TGHT  27.7 5.70

Monday, October 24, 2016, 09:10: Power/Sources off.

Monday, October 24, 2016, 09:20: Water lines purged.

Monday, October 24, 2016, 09:21: RGA off.

Monday, October 24, 2016, 09:23: Ion gauge & Turbo pumps off

Monday, October 24, 2016, 12:54: Venting.

  546   Friday, October 14, 2016, 13:17 Anders Mjos      Problems/SolutionsPowerbump tripped off turbos

Friday, October 14, 2016, 13:17: Restarted pumps

Friday, October 14, 2016, 13:4: Another trip: restarted pumps


Tuesday, October 18, 2016, 12:12: Venting.

  545   Tuesday, October 11, 2016, 14:55 Anders Mjos      In progressEmpty

Breaker tripped during roughing. Removed exhaust line during first 2 min.

Tuesday, October 11, 2016, 14:55: Turbos at speed. Vacuum at 1.0E-6 T


Wednesday, October 12, 2016, 12:09: Ion gauge & Turbo pumps off.

Wednesday, October 12, 2016, 13:52: Venting