Friday, August 10, 2012, 11:29, Pierre Bricault, NA, , , , N A, NA, In progress, Test FEBIAD
|
The helium bottle was found empty.
Rick will refill it and hook the leak detector on the system to find out
if we have a leak on the line.
|
Monday, August 13, 2012, 10:59, Pierre Bricault, , , , , , , Problems/Solutions, Test FEBIAD
|
This morning I try to contact PS group no one answer. Dan Louie is in vacation.
I went into the can diagnostics panel and reconfigure MB1 power supply.
This worked.
|
Friday, October 31, 2014, 14:57, Anders Mjos, , LP-FEBIAD, , , Tube only, 38307-9, In progress, Test
|
Friday, October 31, 2014, 14:47: Starting turbos
Friday, October 31, 2014, 14:57: Turbos at speed. Vacuum at 2.9E-5 T
Monday, November 03, 2014, 10:08 : Opened HS water circuit. Vacuum stable at 1.7E-7 T
Monday, November 03, 2014, 10:22: Starting auto ramping to 228A on TBHT at 1 A/min
Monday, November 03, 2014, 13:44: Target at temperature. Opening IV4.
Monday, November 03, 2014, 14:45: IV4 closed
Monday, November 03, 2014, 15:00: Starting cool down. 1 A/min |
Monday, March 01, 2021, 16:13, Fernando Maldonado, , , , , , , Done, Temporary RGA installation
|
Monday, March 01, 2021, 16:03: An ExTorr RGA has been installed in the ISAC test stand.
The original SRS 100 is still broken ( e-log 778)
The SRS 100 from the conditioning station will not be available this week. |
Tuesday, May 15, 2012, 16:18, Aurelia Laxdal, SiC#27, HP-SIS, ITE, TM4, , , In progress, Target/Ion source conditioning
|
Did the HV conditioning up to 30kV and started to ramp up the heaters to 580A and 230A. |
Tuesday, February 03, 2015, 14:33, Anders Mjos, Empty, LP-SIS, , , , , In progress, Target with new center block and new EE insulator
|
Also with newly installed RGA
Tuesday, February 03, 2015, 14:33: Roughing
Tuesday, February 03, 2015, 15:05: Turbos started
Tuesday, February 03, 2015, 15:15: Turbos at speed. Vacuum at 3.3E-5 T
Wednesday, February 04, 2015, 13:56: Cooling water on HS circuit on. No response on IG1 or on the RGA (water)
Thursday, February 05, 2015, 09:00: RGA started. Scan 1-100 every 5 min
Thursday, February 05, 2015, 09:02: Opened IV4
Thursday, February 05, 2015, 09:16: Started target heating to 500 / 150 A at 2 / 1 A/min
Thursday, February 05, 2015, 09:24: Opened electrical cage to switch on TGHT PS
Thursday, February 05, 2015, 09:26 : Started target heating to 500 / 150 A at 2 / 1 A/min
Thursday, February 05, 2015, 09:28: BIAS/EZL/EE on and at HV
Thursday, February 05, 2015, 13:21: TGHT voltage limited. Voltage limit increased to 7 V
Thursday, February 05, 2015, 13:53: Continue to 580 A
Thursday, February 05, 2015, 14:25: RGA stopped around 13:34. Started scanning again
Thursday, February 05, 2015, 15:08: Heating to 200 A on TBHT
Friday, February 06, 2015, 10:34: Heating TBHT to 220 A
Friday, February 06, 2015, 11:07: TBHT at 230 A. TGHT at 580 A
Friday, February 06, 2015, 11:50: Cooling down target
Friday, February 06, 2015, 11:56: RGA off
Friday, February 06, 2015, 11:5: BIAS/EZL/EE off
Tuesday, February 10, 2015, 11:34: BIAS/EZL/EE on. Started heating to 580 / 230 A at 4 / 2 A/min. RGA on
Monday, February 16, 2015, 08:46: BIAS/EZL/EE on
Monday, February 16, 2015, 09:13 : Started heating to 580 / 230 A at 4 / 2 A/min. RGA on
Monday, February 16, 2015, 10:10: Opened isolation valve
Monday, February 16, 2015, 14:23: TGHT was found voltage limiting at 7 V. Increased voltage limit to 7.2 V
Temperature read with digital optical pyrometer. Inside target 1800 - 1900 deg C. Outside 1900 - 2000 deg C
Monday, February 16, 2015, 15:50: Starting cool down
Tuesday, February 17, 2015, 08:30: RGA off
Tuesday, February 17, 2015, 08:32: BIAS/EZL/EE off. Isolation valve closed.
Tuesday, February 17, 2015, 08:34: Turbos off
Tuesday, February 17, 2015, 13:58: Venting |
Monday, October 03, 2011, 14:46, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target stored under vacuum
|
Anders Mjos wrote: |
Aurelia Laxdal wrote: |
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum and the water is still on.
|
Monday, October 03, 2011, 13:45: Venting.
|
Monday, October 03, 2011, 14:45
- Target was visually inspected and found to be ready to go online.
- No burn marks found on the 9-pin connectors.
- Pumping down. Target will be stored under vacuum for now. Target is scheduled to go to Hot Cell on Oct. 20th. Electrical connections (target/tube heater + coil) are not connected
|
Wednesday, October 12, 2011, 13:14, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target removed
|
Anders Mjos wrote: |
Anders Mjos wrote: |
Aurelia Laxdal wrote: |
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum and the water is still on.
|
Monday, October 03, 2011, 13:45: Venting.
|
Monday, October 03, 2011, 14:45
- Target was visually inspected and found to be ready to go online.
- No burn marks found on the 9-pin connectors.
- Pumping down. Target will be stored under vacuum for now. Target is scheduled to go to Hot Cell on Oct. 20th. Electrical connections (target/tube heater + coil) are not connected
|
Wednesday, October 12, 2011, 13:15: Venting
Wednesday, October 12, 2011, 14:15: Target brought back to lab for inspection and final check. |
Thursday, May 17, 2012, 08:36, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , Done, Target removed
|
Thursday, May 17, 2012, 08:36: Turbo pumps switched off in preparation of target removal.
Thursday, May 17, 2012, 08:51: Purging cooling lines.
Thursday, May 17, 2012, 08:55: Venting.
Thursday, May 17, 2012, 09:21: Target removed |
Friday, September 23, 2011, 16:42, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, Target ready to be heated
|
Friday, September 23, 2011, 16:4: Target installed and roughing started.
Friday, September 23, 2011, 17:12: Started turbo pumps.
Monday, September 26, 2011, 09:00: Opened up water flow. Vacuum rose from 3e-6 to 3e-5 torr in 30 s. Closed water flow.
Monday, September 26, 2011, 09:00: Venting for leak check.
Monday, September 26, 2011, 10:20: Pressurized water lines with 120 PSI He. Leak detected on right water line connection to heat shield.
Monday, September 26, 2011, 12:00: Leak repaired. Pumping down. Kapton added on target heater cooling line to prevent short with cooling line for FEBIAD coil.
Monday, September 26, 2011, 12:47: Started turbo pumps.
Monday, September 26, 2011, 15:45: Opened up water flow. Vacuum stable at 3.5e-6 torr.Target ready to be heated. |
Thursday, October 13, 2011, 15:42, Anders Mjos, Training , HP-FEBIAD, , , , , Problems/Solutions, Target ready to be heated
|
Rick Maharaj wrote: |
test stand vented
|
Thursday, October 13, 2011, 15:40: Pumping down
Friday, October 14, 2011, 10:00: Cooling water is on. Pressure increase from 8e-7 to 3e-6 torr. Venting.
Friday, October 14, 2011, 11:10: Replaced seals on cooling lines with new silver plated SS seals. Pumping down.
Friday, October 14, 2011, 13:25: Cooling water is on. Vacuum at 1.35e-6 torr.
Monday, October 17, 2011, 09:00: Vacuum at 5.4e-7 torr. target ready to be heated. |
Thursday, May 31, 2012, 15:43, Anders Mjos, Ta#38, LP-SIS, ITW, TM1, , , In progress, Target ready to be heated
|
Thursday, May 31, 2012, 15:42: Roughing
Thursday, May 31, 2012, 16:01 : Starting turbos
Thursday, May 31, 2012, 16:08 : Turbos at speed. Vacuum 1.7 E-5
Friday, June 01, 2012, 08:08: Cooling water opened. Vacuum stable at 5.7E-7. Target ready to be heated and biased. |
Friday, October 26, 2012, 08:29, Anders Mjos, TiC#3, LP-SIS, ITW, TM1, , , Done, Target ready for conditioning
|
Anders Mjos wrote: |
Thursday, October 25, 2012, 13:00: Roughing
Thursday, October 25, 2012, 13:19 : Turbos on
Thursday, October 25, 2012, 13:28 : Turbos at speed
Thursday, October 25, 2012, 13:29 : Vacuum at 1.6E-5 T
|
Friday, October 26, 2012, 08:29: Opened water. Vacuum stable at 1.8E-7 T |
Monday, October 03, 2011, 10:53, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target is ready to be removed.
|
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum and the water is still on. |
Friday, January 11, 2013, 11:02, Anders Mjos, RFQ empty, , , , , , , Target installed, pumping down
|
Target installed with 120 in lbs torque on target legs and on central support.
Friday, January 11, 2013, 11:01: Roughing
Friday, January 11, 2013, 11:25: Start turbos - SR
Friday, January 11, 2013, 11:34: turbos at speed - SR
Friday, January 11, 2013, 11:35: vacuum at 1.2E-5T - SR
|
Wednesday, January 16, 2013, 01:06, Sebastian Raeder, RFQ empty, , , , , , , Target installed - pumping down
|
RFQ empty target installed
Wednesday, January 16, 2013, 01:05: roughing started
Wednesday, January 16, 2013, 01:34: turbos started
Wednesday, January 16, 2013, 01:43: turbos at speed
Wednesday, January 16, 2013, 01:44: vacuum at 1.7E-5T |
Thursday, August 16, 2012, 16:56, Anders Mjos, , , , , , , Problems/Solutions, Target heater PS disconnected from controls.
|
As per Ray Dube for the FEBIAD anode bias test. The PS will need to be reconnected before a target is run. |
Wednesday, January 25, 2017, 14:57, Aaron Schmidt, , , , , 42218-11, 41751-6, Done, Target cleaning test LP-SIS Full Clean
|
Target Test (Fully Cleaned vs Crystal Clean only).
For all tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.
-Start Roughing by 10:10am +/- 1 minute.
-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A
ALL START TIMES MUST BE CONSISTENT.
***Pre-outgassed*** Heat Shield W.O# 41751-6: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.
HP-SIS Target # 42218-11: Full Clean. Crystal Clear, Acetone, & Methanol used.
Thursday, February 09, 2017, 09:44: HS removed from test stand. Exchange target.
Thursday, February 09, 2017, 10:04: Target # 42218-11 placed into test stand. Door open for 20 minutes.
Thursday, February 09, 2017, 10:10: Roughing.
Thursday, February 09, 2017, 10:10: Doors sealed for roughing.
Thursday, February 09, 2017, 10:11: BV1B OPEN. Opened @ 428T.
Thursday, February 09, 2017, 10:29: Both Turbo pumps started.
Thursday, February 09, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.
Thursday, February 09, 2017, 10:37: TP1A @ speed 38 KRPM.
Thursday, February 09, 2017, 10:40: RGA on. Vacuum @ 1.45E-05T.
Thursday, February 09, 2017, 10:47: Strip tool Vacuum.Current restarted.
Thursday, February 09, 2017, 15:34: Check. Vacuum @ 3.97E-07T.
***NOTE: Small water anomaly on RGA affecting Vacuum***
***NOTE: Small water anomaly on RGA affecting Vacuum*** Continues. Monitor through heating.
Friday, February 10, 2017, 08:06: Water lines opened. No response on RGA. Vacuum stable @ 3.24E-07T.
Friday, February 10, 2017, 08:08: Power/Sources on.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
24.4 |
4.02 |
TBHT |
24.2 |
3.22 |
COIL + EE |
24.2 |
5.26 |
TGHT |
24.4 |
5.90 |
08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.
10:00: Check. Vacuum @ 3.68-4.87E-07T. (Anomaly variant)
11:40: Check. Vacuum @ XE-07T.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
34.6 |
4.12 |
TBHT |
25.5 |
3.21 |
COIL + EE |
25.5 |
5.29 |
TGHT |
27.3
|
5.88 |
Check. Vacuum @ 4.41E-07T.
Auto-cooling started @ 2A per min. Vacuum @ 4.25E-07T.
Tuesday, February 14, 2017, 08:22: Power/sources off.
Tuesday, February 14, 2017, 08:23: Water lines purged.
Tuesday, February 14, 2017, 08:26: RGA off. Ion Gauge off. Turbo pumps off. |
Wednesday, January 25, 2017, 14:56, Aaron Schmidt, , , , , 42218-14, 41751-6, Done, Target cleaning test LP-SIS CC Clean
|
Target Test (Fully Cleaned vs Crystal Clean only).
For all tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.
-Start Roughing by 10:10am +/- 1 minute.
-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A
ALL START TIMES MUST BE CONSISTENT.
***Pre-outgassed*** Heat Shield W.O# 41751-6: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.
LP-SIS Target # 42218-14: Crystal Clean only.
Tuesday, February 07, 2017, 09:48: HS removed from test stand. Exchange target.
Tuesday, February 07, 2017, 10:07: Target # 42218-14 placed into test stand. Door open for 19 minutes.
Tuesday, February 07, 2017, 10:10: Roughing.
Tuesday, February 07, 2017, 10:10: Doors sealed for roughing.
Tuesday, February 07, 2017, 10:11: BV1B OPEN. Opened @ 430T.
Tuesday, February 07, 2017, 10:29: Both Turbo pumps started.
Tuesday, February 07, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.
Tuesday, February 07, 2017, 10:37: TP1A @ speed 38 KRPM.
Tuesday, February 07, 2017, 10:39: RGA on. Vacuum @ 1.49E-05T.
Tuesday, February 07, 2017, 15:30: Check. Vacuum @ 3.26E-07T.
Wednesday, February 08, 2017, 08:12: Water lines opened. No response on RGA. Vacuum stable @ 1.29E-07T.
Wednesday, February 08, 2017, 08:14 : Power/Sources on.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
20.8 |
4.06 |
TBHT |
20.5 |
3.17 |
COIL + EE |
20.6 |
5.27 |
TGHT |
20.7 |
5.88 |
Wednesday, February 08, 2017, 08:30: Auto ramping TGHT / TBHT to 580 / 200 A @ 2A per min.
Wednesday, February 08, 2017, 10:00: Check. Vacuum @ 3.33E-07T.
Wednesday, February 08, 2017, 11:40: Check. Vacuum @ 1.70E-07T.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
30.2 |
4.06 |
TBHT |
21.0 |
3.17 |
COIL + EE |
21.1 |
5.22 |
TGHT |
21.3
|
5.82 |
Wednesday, February 08, 2017, 13:30: Check. Vacuum @ 3.53E-07T.
Wednesday, February 08, 2017, 15:30: Auto-cooling started @ 2A per min. Vacuum @ 3.88E-07T.
***NOTE: Small water anomaly on RGA affecting Vacuum***
***NOTE: Small water anomaly on RGA affecting Vacuum continues***
Thursday, February 09, 2017, 08:08: Sources/power off.
Thursday, February 09, 2017, 08:10: Water lines purged.
Thursday, February 09, 2017, 08:11: RGA off.
Thursday, February 09, 2017, 09:00: Venting |
Monday, July 17, 2017, 10:04, Aaron Schmidt, , HP-SIS, , , 42218-10, 42738-1, , Target cleaning test HP-SIS Full Clean
|
Target Test (Fully Cleaned vs Crystal Clean only).
For all tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
- Ensure previous test turbos are off by 8:15 and started venting by 9:15am to meet timeline.
-Start Roughing by 10:10am +/- 1 minute.
-TGHT / TBHT ramping starts @ 8:30am. 2A per min to 580A / 200A
ALL START TIMES MUST BE CONSISTENT.
***Pre-outgassed*** Heat Shield W.O# 42738-1: Includes insulators, new Al grounded 9-pin, bracket, & gripper arms. Blank/Plate. No source cup/EE.
HP-SIS Target # 42218-10: Full Clean. Crystal Clear, Acetone, & Methanol used.
Thursday, July 27, 2017, 09:49: HS removed from test stand. Exchange target.
Thursday, July 27, 2017, 10:07: Target # 42218-10 placed into test stand. Door open for 20 minutes.
Thursday, July 27, 2017, 10:10: Roughing.
Thursday, July 27, 2017, 10:10: Doors sealed for roughing.
Thursday, July 27, 2017, 10:13 BV1B OPEN. Opened @ 230T.
Thursday, July 27, 2017, 10:29: Both Turbo pumps started.
Thursday, July 27, 2017, 10:34: Ion gauge on. TP1B @ speed 42 KRPM.
Thursday, July 27, 2017, 10:37: TP1A @ speed 38 KRPM.
Thursday, July 27, 2017, 10:40: RGA on. Vacuum @ 1.42T.
Thursday, July 27, 2017,15:00: Check. Vacuum @ 5.51e-07T.
Thursday, July 27, 2017, 15:02: Waterlines opened. No response on RGA. Vacuum @ 5.42e-07T
Thursday, July 27, 2017, 15:05: Power on.
Friday, July 28, 2017, 08:30: Ramping started
Monday, July 31, 2017, 07:56: Ramping down
Monday, July 31, 2017, 14:25: Power supplies off. RGA off.
Tuesday, August 15, 2017, 06:48: Ion gauge, Turbo pumps off.
Tuesday, August 15, 2017, 06:50: power off. Waterlines purged.
Tuesday, August 15, 2017, 07:55: Venting. |
|