Message ID: 266     Entry time: Friday, January 11, 2013, 11:02
Author: Anders Mjos 
Target/No.#: RFQ empty 
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status:  
Subject: Target installed, pumping down 

Target installed with 120 in lbs torque on target legs and on central support.

Friday, January 11, 2013, 11:01: Roughing

Friday, January 11, 2013, 11:25: Start turbos - SR

Friday, January 11, 2013, 11:34: turbos at speed - SR

Friday, January 11, 2013, 11:35: vacuum at 1.2E-5T - SR

 