604
|
Monday, August 21, 2017, 16:20 |
Anders Mjos | | | | | | | Problems/Solutions | TBHT power supply removed |
|
|
603
|
Thursday, August 17, 2017, 12:45 |
Anders Mjos | | | | | | | Problems/Solutions | TBHT power supply removed | The Xantrex 10V 600 A power supply
for the TBHT has been moved to ITE to replace
the failed TGHT power supply |
|
602
|
Tuesday, August 15, 2017, 08:41 |
Aaron Schmidt | Ta#55 | LP-SIS | | | 42218-11 | 42738-2 | In progress | TBHT sight in test | Heat TGHT to 580 A & TGHT to
200 A for view port test.
Tuesday, August 15, 2017, 08:40: |
|
601
|
Thursday, August 03, 2017, 17:00 |
Anders Mjos | | | | | | | Problems/Solutions | Vacuum system tripped on power interruption | Thursday, August 03, 2017, 17:00:
Restarted TPs |
|
600
|
Wednesday, July 19, 2017, 09:13 |
Aaron Schmidt | Ta Targets | | | | | | Done | Ion Peaks | Attached is a recent list of Ta targets
with their extracted ions peaks. |
|
599
|
Monday, July 17, 2017, 10:04 |
Aaron Schmidt | | HP-SIS | | | 42218-10 | 42738-1 | | Target cleaning test HP-SIS Full Clean | |
|
598
|
Monday, July 17, 2017, 09:58 |
Aaron Schmidt | | HP-SIS | | | 42218-8 | 42738-1 | | Target cleaning test (Long) HP-SIS CC Clean | |
|
597
|
Monday, July 17, 2017, 09:55 |
Aaron Schmidt | | | | | 41882-4 | 42738-1 | In progress | Out Gas HS for Target Cleaning Test | -No EE. Insulators, gripper arms,
and blank EE plate included |
|
596
|
Monday, July 10, 2017, 13:27 |
Aaron Schmidt | Ta#53 | HP-SIS | ITW | TM2 | 42218-6 | 41751-6 | In progress | Conditioning Ta#53 | Monday, July 10, 2017, 14:03: Roughing.
Monday, July 10, 2017, 14:27: Turbo
pumps started. |
7x |
595
|
Thursday, July 06, 2017, 13:16 |
Aaron Schmidt | Ta#55 | LP-SIS | | | 42218-11 | 42738-2 | In progress | Conditioning Ta spare for Ta#52 | Thursday, July 06, 2017, 13:56: Roughing.
Thursday, July 06, 2017, 14:25: Turbo
pumps started. |
10x |
594
|
Friday, June 30, 2017, 13:31 |
Aaron Schmidt | Ta#53 | HP-SIS | ITW | TM2 | 42218-6 | 41751-6 | In progress | Conditioning Ta#53 | Friday, June 30, 2017, 13:48: Roughing.
Friday, June 30, 2017, 14:26: Turbo
pumps on. |
|
593
|
Friday, June 16, 2017, 11:23 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. | Friday, June 16, 2017, 11:22: roughing.
Friday, June 16, 2017, 14:28: Turbo
pumps on |
|
592
|
Friday, June 09, 2017, 13:28 |
Aaron Schmidt | Ta#52 | LP-SIS | ITE | TM4 | 42218-14 | 41751-8 | In progress | Conditioning Ta#52 | Friday, June 09, 2017, 13:27: Roughing.
Friday, June 09, 2017, 14:09: Turbo
pumps on. |
8x |
591
|
Wednesday, June 07, 2017, 12:49 |
Aaron Schmidt | | | | | | | | Gas bottles | Gas bottles for FEBIAD testing were
exchanged yesterday around 1:30. One Neon
& one Argon bottle were removed. |
|
590
|
Tuesday, June 06, 2017, 09:22 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Tuesday, June 06, 2017, 09:21: roughing.
Friday, June 09, 2017, 08:50:
Ion gauge off. Turbo pumps off. |
|
589
|
Saturday, June 03, 2017, 09:34 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Cathode bias configuration |
|
|
588
|
Friday, June 02, 2017, 15:57 |
Aaron Schmidt | SiC#36 | HP-FEBIAD-CTL | ITW | TM2 | 41369-10 | 42132-6/9 | | Conditioning SiC#36 | Friday, June 02, 2017, 15:20: Coil loose
(Remove lid, Tighten and place lid again)
Friday, June 02, 2017, 15:52: Roughing |
9x |
587
|
Wednesday, May 24, 2017, 11:12 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Anode bias configuration | The Test Stand has been configured
for Anode bias. John Chow changed the power
supply and the electrical connections have |
|
586
|
Monday, May 22, 2017, 09:43 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | | Tri-Coil CTL-FEBIAD test IV | Monday, May 22, 2017, 09:41: Roughing.
Monday, May 22, 2017, 10:00: Turbo
pumps started. |
|
585
|
Wednesday, May 17, 2017, 10:17 |
Anders Mjos | | HP-FEBIAD-CTL | | | | | Problems/Solutions | Sparking between new coil line and ground electrode | Wednesday, May 17, 2017, 10:17: Sparking
around 20 kV. Will need to vent to increase
gap between water lines. |
|
|