ID Date Authorup Category Type Specific Subject Text Attachments
  123   Thursday, November 06, 2014, 17:18 Ron KuramotoRepairTarget 2Cooling1AT2 Collimator B, faulty Thermister water out temperature On 14Oct2014, the 1AT2 Collimator B water
outlet temperature rose to 100o
C. 
  
  124   Thursday, November 06, 2014, 17:22 Ron KuramotoRepairTarget 2Cooling1AT2, faulty Thermister water out temperture

    

       
            
  
  176   Friday, October 02, 2015, 17:25 Ron KuramotoStandard OperationTarget 1TargetRaise Target to lower Rad levels for 1AM7 repairToday the T1MK2 target was moved from Position
4 to Position 0 to lower the Rad fields for
the 1AM7 repair in the 1A Tunnel. The Rad
  
  259   Wednesday, March 04, 2020, 13:42 Ron KuramotoRepairOtherOtherB/L 1A vacuum air leak repair A 4” Marmon aluminum blank-off
flange and o-ring were replaced on the south
port of the T1 target monolith vacuum vessel. This
 1AT1_Vacuum_Leak_Repair-Feb2020.pdf 
  248   Friday, January 25, 2019, 10:53 maicodallavalleRepairOtherCyclotron electricalCyclotron Elevating system Motor electrical wire repairs2018 Cyclotron lid up problem. Station
#9 was  found to  have the motor
wires along the beam plain had damaged wire
  
  321   Thursday, March 02, 2023, 06:59 maicodallavalleMaintenanceTarget 1CoolingRefilled Expasion TankI have refilled the water package on T1
with DI water. The Expansion Tank is at 37cm.
This may change when pump is turned on.
  
  322   Thursday, March 02, 2023, 07:04 maicodallavalleMaintenanceTarget 2CoolingRefilled Expasion TankI have filled the water package on T2 with
DI water. The expansion tank is at 38.1cm.
This may change when the pump is turned on.
  