131
|
Monday, December 22, 2014, 14:31 |
Isaac Earle | Maintenance | Target 2 | Water Leak | Drop in T2 water level | This morning at 5:30am the T2 cooling package
expansion tank switched to WARNING LEVEL
NOT OK. There was no change in BL1A |
|
132
|
Monday, January 05, 2015, 15:08 |
Isaac Earle | Standard Operation | Target 2 | Water Leak | Cooling Packages Re-Started; Suspect External Water Leak at T2 Package | Pumping was restored to 1A today by Vacuum
Group and the beam line returned to normal
vacuum levels. Both cooling packages |
|
133
|
Wednesday, January 07, 2015, 17:27 |
Isaac Earle | Repair | Target 2 | Water Leak | Water Leaks at T2 Cooling Package | The T2 cooling package was visually inspected
today after blocks were removed. With
the cooling package off the following leaks |
|
171
|
Thursday, August 27, 2015, 15:47 |
Isaac Earle | Repair | Other | Water Leak | Warm Cell Water Window Seal Replacement Update | Since the previous E-Log the following
tasks have been completed:
- Panel spacer rods installed at |
|
173
|
Monday, September 28, 2015, 11:33 |
Isaac Earle | Repair | Other | Water Leak | Warm Cell Water Window Repair Complete | The warm cell water window tanks were filled
on September 17 after 2 weeks of curing time.
A water leak was found coming from |
|
308
|
Thursday, January 12, 2023, 10:36 |
Adam Newsome | Maintenance | Target 1 | Water Leak | T1 and T2 - Cooling Package Water Leaks - Ball Valves | Upon uncovering the T1 and T2 areas to
prepare for regular cooling package maintenance,
it was discovered that multiple ball valves |
|
318
|
Friday, February 17, 2023, 14:36 |
Albert Kong | Repair | Other | Water Leak | T1/T2 Water Cooling Package Ball Valve Replacement | 5 and 3 Swagelok ball valves were replaced
from the T1 and T2 cooling packages respectively.
These are compression fit valves, |
|