303
|
Friday, September 23, 2022, 10:51 |
Matthew Gareau | Standard Operation | Target 2 | Target | Target T2-MK2 moved to storage pit | The T2-MK2 target was transported from
the east hot cell to the storage pit at position
3. |
|
309
|
Monday, January 16, 2023, 09:54 |
Adam Newsome | Standard Operation | Other | Cooling | T1 and T2 - Cooling Package Drained | On Jan. 13, the T1 and T2 cooling package
water reservoirs were drained to the BL1A
holding tank. Water samples were obtained |
|
330
|
Tuesday, June 06, 2023, 15:42 |
Albert Kong | Standard Operation | Target 1 | Cooling | T1 Heat Exchanger Low Flow Diagnostics | On May 31, the low active water in BL1A
was turned off briefly and upon re-starting,
the flow to the T1 heat exchanger was very |
|
335
|
Monday, December 04, 2023, 09:22 |
Albert Kong | Standard Operation | Target 2 | Cooling | T2 TGT Low Flow | See Cyclotron fault 16553.
"B1A:T2CS:FGTGT readback is
toggling at the warn limit of 3.0 GPM and |
|
336
|
Wednesday, January 10, 2024, 12:25 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 cooling packages drained | Jan 10, 2024:
The cooling packages for T1/T2 was
drained this morning. ~150 L from each of |
|
337
|
Wednesday, January 10, 2024, 12:47 |
Albert Kong | Standard Operation | Target 1 | Target | T1 target ladder exchange (T1-MK1 to hot cell roof, T1-MK2 from pit to station) | T1-MK1 was moved from the target station
to the hot cell roof.
Radiation surveys report 140 mSv/hr |
|
339
|
Monday, January 15, 2024, 16:36 |
Albert Kong | Standard Operation | Target 2 | Cooling | T2 Resin Flask Exchange | The resin flask on the T2 cooling package
was exchanged today (new resin can prepped
in the morning). |
|
340
|
Monday, January 15, 2024, 16:47 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure | The following tasks were completed
in preparation of re-filling the T1 and T2
cooling packages: |
7x |
341
|
Friday, January 19, 2024, 17:07 |
Albert Kong | Standard Operation | Other | Target | T1/T2 Profile Monitor, TGT Ladder, CUNO filter leak, Motor Coupling Inspection, + M9/M20 Blocker Actuation | The following tasks were completed:
Yesterday (Jan 18), the
T1/T2 cooling packages were inspected for |
7x |
342
|
Thursday, February 01, 2024, 11:14 |
Albert Kong | Standard Operation | Target 1 | Hot Cell | T1-MK1 Flush and Purge on Hot Cell | The recently removed T1-MK1 target ladder
was flushed with city water for ~30s at all
target positions. It was then purged with |
|
343
|
Thursday, February 01, 2024, 11:16 |
Albert Kong | Standard Operation | Other | Cooling | Spent resin can rinse, purge, and drying | The recently removed resin can from
the T2 target station was rinsed with city
water and flushed with compressed air for |
|
348
|
Thursday, May 23, 2024, 17:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Target Exchange (+ leak fix, service panel changes, coupler exchange) | On May 23, 2024 two sets of plugs from
position 1 and 3 and a 12mm Be target from
position 5 (serial #109) was removed from |
36x |
350
|
Wednesday, July 17, 2024, 15:05 |
Adam Newsome | Standard Operation | Other | Other | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround for July 2024 was completed
by A. Kong.
Results can be found in the master |
|
351
|
Tuesday, August 06, 2024, 11:35 |
Albert Kong | Standard Operation | Other | BL1A Holding Tank | BL1A and RH Active Sump Draining | The RH active sump was drained (over Jul
31-Aug 01), in total approximately 5500 L
of water was sent to city sewage. |
|
352
|
Thursday, August 22, 2024, 15:16 |
Adam Newsome | Standard Operation | Other | Active Sump | Active sump filled ~600L with grey water from RCR1 sump replacement | During a replacement of the RCR1 active
sump (mechanical services group), approximately
600L of non-active grey water was released |
|
354
|
Monday, September 09, 2024, 16:31 |
Albert Kong | Standard Operation | Other | Active Sump | Active Sump High Level Sensor Testing | The active sump high level sensor was tested
and correctly alarmed locally. However the
alarm in the MHESA RCR lab did not make any |
|
356
|
Wednesday, October 30, 2024, 15:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Electrical Check on Hot Cell | T1-MK1 electrical checks were completed
on the hot cell. Specifically the profile
and protect monitors were checked (assistance |
7x |
358
|
Friday, January 10, 2025, 18:36 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 cooling packages drained | The T1 and T2 cooling packages were drained
starting at 14:36, by 14:48 both expansion
tanks had dried, meaning the draining rate |
|
10
|
Friday, January 13, 2012, 17:04 |
Isaac Earle | Repair | Target 2 | Target | Broken Part found on M20 Beam Blocker | While wrapping up vacuum seal bearing
replacement on the M20 beam blocker I found
a piece of hard black material approximately |
|
11
|
Wednesday, January 18, 2012, 12:01 |
Isaac Earle | Repair | Target 2 | Target | Broken M20BB Bearing Removed, New Design Complete | The broken M20 beam blocker plastic
shaft bearing was removed. Measurements
of the bearing as well as the shielding disc |
|