Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Meson Hall, Page 5 of 19  Not logged in ELOG logo
Entry  Friday, September 23, 2022, 10:51, Matthew Gareau, Standard Operation, Target 2, Target, Target T2-MK2 moved to storage pit Storage_location_state_as_of_Sept_23_2022_(after_target_moves).jpg
The T2-MK2 target was transported from the east hot cell to the storage pit at position 3.
As was noted in the past, position 3 is difficult to align. The flask alignment pins prevent the flask from positioning in the correct location,
and it is required to have the flask just above the pins to ensure that the pins did not restrict the flask movement.
Entry  Monday, January 16, 2023, 09:54, Adam Newsome, Standard Operation, Other, Cooling, T1 and T2 - Cooling Package Drained 
On Jan. 13, the T1 and T2 cooling package water reservoirs were drained to the BL1A holding tank. Water samples were obtained for each system and provided
to RPG for analysis. 
Prior to starting draining, the BL1A holding tank water level was approximately 330L. After draining, the water level was approximately 550L (checked
Entry  Tuesday, June 06, 2023, 15:42, Albert Kong, Standard Operation, Target 1, Cooling, T1 Heat Exchanger Low Flow Diagnostics Picture1.pngPicture2.png
On May 31, the low active water in BL1A was turned off briefly and upon re-starting, the flow to the T1 heat exchanger was very close to the reported
warn limit (~6 gpm). 
 
Entry  Monday, December 04, 2023, 09:22, Albert Kong, Standard Operation, Target 2, Cooling, T2 TGT Low Flow T2FlowAlwaysCloseTo3GPM.pngT2TGTWaterTempOK.pngWarnTripLevels.pngFlowWarnTripLevels.pngPicture1.png
 See Cyclotron fault 16553. 
"B1A:T2CS:FGTGT readback is toggling at the warn limit of 3.0 GPM and over the last week has started crossing over the trip threshold of 2.8
GPM, tripping off the water package. Initial Action Taken: 1A is scheduled to take beam on December 13."
Entry  Wednesday, January 10, 2024, 12:25, Albert Kong, Standard Operation, Other, Cooling, T1/T2 cooling packages drained T1T2EPICSPages.PNGIMG_3943.JPEGIMG_4231.JPEG
Jan 10, 2024:
The cooling packages for T1/T2 was drained this morning. ~150 L from each of the cooling package reservoirs + expansion tank was drained to the
BL1A holding tank. The holding tank held ~400 L initially and is therefore now filled to ~700 L (out of a 800 L capacity). We will likely drain the holding
Entry  Wednesday, January 10, 2024, 12:47, Albert Kong, Standard Operation, Target 1, Target, T1 target ladder exchange (T1-MK1 to hot cell roof, T1-MK2 from pit to station) T1_and_T2_Beryllium_Target_Beamtime_Spreadsheet_-_(10Jan2024).xlsxMeson_Hall_Storage_Pit_Target_Device_Location_Record_-_(10Jan2024).pptmVacuumAt2.56PM.PNG
T1-MK1 was moved from the target station to the hot cell roof. 
Radiation surveys report 140 mSv/hr at 0.5m for the bare T1-MK1 target ladder.
On the hot cell roof, fields are 220uSv/h at 0.5m.
Entry  Monday, January 15, 2024, 16:36, Albert Kong, Standard Operation, Target 2, Cooling, T2 Resin Flask Exchange IMG_3836.JPEGIMG_3844.JPEGIMG_3856.JPEG
The resin flask on the T2 cooling package was exchanged today (new resin can prepped in the morning). 
The newly installed resin flask was placed slightly off-set from the marking on the platform to ensure that the braided hose will clear the blocks
when replaced at the end of shutdown.
Entry  Monday, January 15, 2024, 16:47, Albert Kong, Standard Operation, Other, Cooling, T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure 7x
 The following tasks were completed in preparation of re-filling the T1 and T2 cooling packages:

    All valves were returned to the 'open' configuration (note, compressed air to collimators at T1 is to remain closed - rotating collimator
no longer in use || also note, odd handle configuration at T1 panel when all valves are open - see attached).
    Leaks from valves were checked,
Entry  Friday, January 19, 2024, 17:07, Albert Kong, Standard Operation, Other, Target, T1/T2 Profile Monitor, TGT Ladder, CUNO filter leak, Motor Coupling Inspection, + M9/M20 Blocker Actuation 7x
 The following tasks were completed:

    Yesterday (Jan 18), the T1/T2 cooling packages were inspected for leaks and some moisture was found underneath the CUNO filters behind
the resin cans on both T1/T2. It was determined that the source of the leak was a loose fitting on the drain valves of the CUNO filter housing (see photo).
Entry  Thursday, February 01, 2024, 11:14, Albert Kong, Standard Operation, Target 1, Hot Cell, T1-MK1 Flush and Purge on Hot Cell IMG_3950.JPEGIMG_3975.JPEGIMG_3973.JPEGIMG_3971.JPEGT1&T2_Pump-Down_and_Leak_Check_Record_05_FEB_2024.pdf
The recently removed T1-MK1 target ladder was flushed with city water for ~30s at all target positions. It was then purged with compressed air at ~5
psi for ~1 minute at all target positions. We then left the target ladder in pos5 to fully extend the bellows and allow it to dry overnight.
This ELOG will be updated as we progress with work done to dry the target ladder and eventually exchange the spent targets.
Entry  Thursday, February 01, 2024, 11:16, Albert Kong, Standard Operation, Other, Cooling, Spent resin can rinse, purge, and drying 
 The recently removed resin can from the T2 target station was rinsed with city water and flushed with compressed air for 1 cycle. 
We will run it through a few more cycles before proceeding with drying under the fume extractor, at which point this ELOG will be updated. 
UPDATE (Feb 08, 2024): The T2 resin can underwent 3 more air cycles. Today it was moved under the fume extractor with the lid cracked open and
Entry  Thursday, May 23, 2024, 17:10, Albert Kong, Standard Operation, Target 1, Target, T1-MK1 Target Exchange (+ leak fix, service panel changes, coupler exchange) 36x
On May 23, 2024 two sets of plugs from position 1 and 3 and a 12mm Be target from position 5 (serial #109) was removed from T1-MK1 in the Meson Hall
remote handling hot cell.
The plugs and spent target are kept in the secondary hot cell (East) on the lift table for future beamspot imaging and to cool down prior to disposal.
Entry  Wednesday, July 17, 2024, 15:05, Adam Newsome, Standard Operation, Other, Other, Safety Walkaround Complete - Meson Hall HC/WC Area 
A safety walkaround for July 2024 was completed by A. Kong.
Results can be found in the master
spreadsheet
Entry  Tuesday, August 06, 2024, 11:35, Albert Kong, Standard Operation, Other, BL1A Holding Tank, BL1A and RH Active Sump Draining IMG_0173.JPEGIMG_0170.JPEGIMG_0185.JPEG
The RH active sump was drained (over Jul 31-Aug 01), in total approximately 5500 L of water was sent to city sewage.
We also tried to divert water from the BL1A holding tank to the active sump, and learned that we cannot run back-flow through the sump pump. The
valving configuration used here was V10, V1, SV1, V6 open - V2, V3 closed. (Note solenoid valve SV1 does not serve a purpose and energizing/powering-down
Entry  Thursday, August 22, 2024, 15:16, Adam Newsome, Standard Operation, Other, Active Sump, Active sump filled ~600L with grey water from RCR1 sump replacement 
During a replacement  of the RCR1 active sump (mechanical services group), approximately 600L of non-active grey water was released into the RH active
sump. At this time, this should be all of the water in the RH sump (approximately 600L total). 
Entry  Monday, September 09, 2024, 16:31, Albert Kong, Standard Operation, Other, Active Sump, Active Sump High Level Sensor Testing 
The active sump high level sensor was tested and correctly alarmed locally. However the alarm in the MHESA RCR lab did not make any sound and no notification
was recieved at the main control room. After some investigation, it is believed that the RCR lab alarm 'had already produced a notification at the control
room and so no new notification was produced by testing the remote handling sump. Alternatively, the RCR sump alarm may have been silenced in the control
Entry  Wednesday, October 30, 2024, 15:10, Albert Kong, Standard Operation, Target 1, Target, T1-MK1 Electrical Check on Hot Cell 7x
T1-MK1 electrical checks were completed on the hot cell. Specifically the profile and protect monitors were checked (assistance from Micheal Donohoe
and Holden Jones from 'probes group'/accelerator systems).
Reference WP C2024-10-30-3.
Entry  Friday, January 10, 2025, 18:36, Albert Kong, Standard Operation, Other, Cooling, T1/T2 cooling packages drained CALCS_T1_T2_cooling_system_drain_speed.htmlTritium_Sample_and_Analysis_Form_-_T1_Cooling_Package_-_2025-01-10.pdfTritium_Sample_and_Analysis_Form_-_T2_Cooling_Package_-_2025-01-10.pdfIMG_0942.JPEG
The T1 and T2 cooling packages were drained starting at 14:36, by 14:48 both expansion tanks had dried, meaning the draining rate for both tanks were
~80L/hr, generally it will only take 2 hours to fully drain the system.
Tritium samples were collected after allowing the system to drain for ~5 minutes to clear out water in the drain lines and actually collect samples
Entry  Monday, January 27, 2025, 12:53, Albert Kong, Standard Operation, Other, Target, T1-MK1 Moved to Storage Pit #4, M9BB Servicing in Hot Cell, T2-MK1 Servicing in Hot Cell, T2-MK2 from Storage Pit #3 to Station 13x
DRAWINGS UPLOADED IN PDF, DOWNLOAD TO VIEW ALL DRAWINGS, PREVI
---------------------------------------------
Jan 27:
Entry  Monday, February 10, 2025, 16:52, Albert Kong, Standard Operation, Target 1, Cooling, T1\T2 Cooling Packages Refill and Restart 6x
The T1 cooling package was refilled to ~38cm and restarted. Shortly after restarting reservoir level dropped and settled to 37.8cm.
No visible leaks when viewed from the Meson Hall south walkway,level seems steady after ~1 hour of operation, water conductivity also returned
to normal after a few minutes of flow.
ELOG V2.9.2-2455