Tuesday, October 04, 2022, 09:59, Adam Newsome, Maintenance, Target 2, Cooling, T2 cooling package maintenance - mini-shutdown 2022
|
The following maintenance tasks were performed during mini-shutdown of 2022 with the goal of resolving the Fault 14966 (target water flow rate low).
Replace the o-ring, paddle wheel, and shaft on the following flow rate sensors:
Q1 (FGTGT)
Q2
Q4
Replace the demineralizing flow metering valve with a new needle valve (the old one was flaky and appeared |
Tuesday, October 11, 2022, 11:27, Adam Newsome, Maintenance, Target 1, Cooling, T1 inlet pressure transducer replacement
|
A fault was reported June 21, 2022 (Fault
15033) regarding T1 inlet pressure warnings... the pressure reading slowly dropped over time as seen in the attached strip tool screenshot (B1A:T1CS:PGIN).
The pressure reading issue is attributed to a fault pressure transducer. The transducer was replaced on Oct. 11, 2022 my M. Dalla Valle. It is currently |
Monday, January 16, 2023, 09:54, Adam Newsome, Standard Operation, Other, Cooling, T1 and T2 - Cooling Package Drained
|
On Jan. 13, the T1 and T2 cooling package water reservoirs were drained to the BL1A holding tank. Water samples were obtained for each system and provided
to RPG for analysis.
Prior to starting draining, the BL1A holding tank water level was approximately 330L. After draining, the water level was approximately 550L (checked |
Monday, January 16, 2023, 15:01, Adam Newsome, Maintenance, Target 1, Cooling, T1 Cooling Package MRO - 2023 Shutdown
|
T1 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have been completed for T1 (this list will be updated as work progresses): |
Monday, January 16, 2023, 15:04, Adam Newsome, Maintenance, Target 2, Cooling, T2 Cooling Package MRO - 2023 Shutdown 
|
T2 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have been completed for T2 (this list will be updated as work progresses): |
Wednesday, February 01, 2023, 14:23, Albert Kong, Maintenance, Target 1, Cooling, T1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge
|
Maico/Eric/Albert:
The expansion tank in T1 was filled to ~36cm in the morning.
|
Thursday, February 02, 2023, 10:35, Albert Kong, Maintenance, Target 1, Cooling, T1 Cooling Package Draining (Prep for Valve Replacement)
|
Water reservoir in T1 started draining at ~7.30 am, will leave till tomorrow or overnight to fully drain.
(Preparation to replace all leaky valves).
Drained water samples collected for RPG. |
Thursday, February 02, 2023, 15:14, Albert Kong, Maintenance, Target 1, Cooling, T1 Cooling Package: Leaked Valve Inspection
|
A 0.75" SwageLok ball valve that was taken out from the T1 cooling package was inspected (SS-45S12).
All valves in the T1/T2 cooling packages likely leaked due to damage to plastic/rubber sealing components.
|
Wednesday, March 01, 2023, 13:10, Albert Kong, Maintenance, Other, Cooling, T1/T2 Water Cooling Package Heat Exchanger Ball Valve Replacement   
|
3x 3/4" swagelok ball valves (2x at T2 and 1x at T1) were replaced after the water cooling line was shut off at the BL1A tunnels late yesterday.
We were able to relieve pressure from the T2 water cooler + M8 colA/B (they are the same line) at the BL1A tunnel through a drain port but no such
port exists for the T1 heat exchanger line in BL1A. |
Thursday, March 02, 2023, 06:59, maicodallavalle, Maintenance, Target 1, Cooling, Refilled Expasion Tank
|
I have refilled the water package on T1 with DI water. The Expansion Tank is at 37cm. This may change when pump is turned on. |
Thursday, March 02, 2023, 07:04, maicodallavalle, Maintenance, Target 2, Cooling, Refilled Expasion Tank
|
I have filled the water package on T2 with DI water. The expansion tank is at 38.1cm. This may change when the pump is turned on. |
Monday, March 06, 2023, 16:58, Albert Kong, Repair, Target 2, Cooling, M20 O-Ring Replacement and Valve Replacement Leak Check 
|
We replaced tha O-ring on M20 at T2 and brought the target station down to vacuum, which allowed the target water pump to be turned on.
After turning the pump on, we inspected the replaced valves for any leaks and found none - the flow on the demineralizing line was adjusted to
1.2GPM (also done at T1) by turning the needle valve. |
Tuesday, June 06, 2023, 15:42, Albert Kong, Standard Operation, Target 1, Cooling, T1 Heat Exchanger Low Flow Diagnostics 
|
On May 31, the low active water in BL1A was turned off briefly and upon re-starting, the flow to the T1 heat exchanger was very close to the reported
warn limit (~6 gpm).
|
Tuesday, July 18, 2023, 09:14, Adam Newsome, Other, Target 1, Cooling, T1 Cooling Package: target flow (FGTGT) sensor noise issues 
|
Between 1:00 pm and 6:00 pm on July 17, 2023, the T1 target cooling water flow rate sensor exhibited some noise which resulted in it dropping below the
warning/trip limit. The control room requested that the threshold values be lowered - permission was granted. The thresholds were set to 2.3 gpm for both
warn and trip levels. See attached screenshot from EPICS sensor data. The occasional spikes and dips continued throughout the night fairly consistently. |
Thursday, August 03, 2023, 10:33, Albert Kong, Repair, Target 2, Cooling, T2 Expansion Tank Water Level Low (Leak Identified) 7x
|
The water level in the T2 cooling system expansion tank dropped to below the trip treshold of 20 cm (ref Cyclotron fault #16123), requiring the beam
to be 'defined' off (see attached image).
Some calculations (see attached .html) show that over the period in which the tank level was dropping (from July 12 - Aug03, 2023) approximatley |
Monday, December 04, 2023, 09:22, Albert Kong, Standard Operation, Target 2, Cooling, T2 TGT Low Flow    
|
See Cyclotron fault 16553.
"B1A:T2CS:FGTGT readback is toggling at the warn limit of 3.0 GPM and over the last week has started crossing over the trip threshold of 2.8
GPM, tripping off the water package. Initial Action Taken: 1A is scheduled to take beam on December 13." |
Wednesday, January 10, 2024, 12:25, Albert Kong, Standard Operation, Other, Cooling, T1/T2 cooling packages drained  
|
Jan 10, 2024:
The cooling packages for T1/T2 was drained this morning. ~150 L from each of the cooling package reservoirs + expansion tank was drained to the
BL1A holding tank. The holding tank held ~400 L initially and is therefore now filled to ~700 L (out of a 800 L capacity). We will likely drain the holding |
Thursday, January 11, 2024, 15:10, Albert Kong, Maintenance, Other, Cooling, T1/T2 Cooling Pkg. Proteus Paddle Wheel Maintenance, CUNO Filter Replacement, and Fitting Inspection
|
The following tasks were performed:
All electrical, water, and pneumatic connections to the T1 target was reconnected.
3x and 2x CUNO filters for T1 and T2
respectively were changed (O-ring for the housings were not changed).
All hansen fittings on the front mounting plates of the T1 and T2 cooling |
Monday, January 15, 2024, 16:36, Albert Kong, Standard Operation, Target 2, Cooling, T2 Resin Flask Exchange  
|
The resin flask on the T2 cooling package was exchanged today (new resin can prepped in the morning).
The newly installed resin flask was placed slightly off-set from the marking on the platform to ensure that the braided hose will clear the blocks
when replaced at the end of shutdown. |
Monday, January 15, 2024, 16:47, Albert Kong, Standard Operation, Other, Cooling, T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure 7x
|
The following tasks were completed in preparation of re-filling the T1 and T2 cooling packages:
All valves were returned to the 'open' configuration (note, compressed air to collimators at T1 is to remain closed - rotating collimator
no longer in use || also note, odd handle configuration at T1 panel when all valves are open - see attached).
Leaks from valves were checked, |
|