  RH-Meson Hall, Page 16 of 18  Not logged in ELOG logo
Entry  Tuesday, September 25, 2012, 16:31, Isaac Earle, Repair, Target 1, Target, T1/T2 Controls 
 - The target control software was modified to reference the correct pot. look-up table for the target at T1 (T1-MK1)
 - The target position buttons on the T1 & T2 panels were not working properly and Graham Waters was contacted to investigate
 - Graham power cycled the microprocessor and the TG1 crate which seemed to make things worse (the control software would not even boot up)
Entry  Thursday, September 13, 2012, 18:09, Isaac Earle, Maintenance, Target 1, Cooling, September Shutdown T1 & T2 MRO IMG_0624.JPGIMG_0658.JPG
 The following tasks were performed during the 2012 September Shutdown:
- Both targets moved to position 0 in preparation for testing of profile monitors (portable ladder control box was used for controlling ladder
motors)
Entry  Friday, September 07, 2012, 16:39, Isaac Earle, Repair, Target 1, Target, RH Lab Crane Repaired 
 The "west" button on the crane pendant was broken, and the crane would occasionally continue moving west when the button was released.
 The button was replaced by a Gordon Crane technician, who also did a crane inspection.  The hoist in the target flask is also due for an inspection,
but it was not possible to do it this visit.  Neil Wong will try to have it done next time a crane technician is in.
Entry  Friday, September 07, 2012, 16:35, Isaac Earle, Repair, Target 2, Target, T2-MK1 Target Repair Completed 
 - Profile monitor wiring harness checked by Bill Rawnsley using resistor pack --> OK
 - New profile monitor (0.005" gold coated molybdenum wires) installed & blip tested --> OK
 - Potentiometer checked --> OK
Entry  Wednesday, August 08, 2012, 14:40, Isaac Earle, Repair, Target 1, Target, T1-MK1 Target Repair Complete 
- Re-wired profile monitor was received from Probes Group and installed on the target
- Protect and profile monitors were 'blip' tested, both OK
- Profile monitor actuation and limit switches tested, all OK (monitor starts to travel @ 20psi,
Entry  Friday, July 27, 2012, 14:48, Isaac Earle, Repair, Target 1, Target, T1-MK1 Target Repair Update 
- T1MK1 target transferred from storage pit to hot cell (max field: 4700 μSv/hr
@ 0.5m)
Entry  Monday, July 23, 2012, 16:01, Isaac Earle, Development, Target 1, Target, Target Flask Seismic Restraint Clamps Installed IMG_0427.JPGIMG_0428.JPGIMG_0429.JPG
 Installation of the seismic restraint clamps has been completed for the MK1 and MK2 target flasks in the Remote Handling lab (photos attached).
 Two clamps on the MK1 flask required 3/8" shims due to warpage of the flask baseplate (see photo IMG_0429).
Dragan Mitrovic has been notified so that he can inspect the installation and close the work request.
Entry  Tuesday, July 17, 2012, 15:30, Isaac Earle, Development, Target 1, Cooling, T1 & T2 Expansion Tank Level Warnings Added 
 Mike Mouat and Juan Pon have modified the control system so that the control room will receive a message when the warning or trip level sensors
for the T1 & T2 expansion tanks read "NOT OK".  The message also displays the current water height in the tank.  This will help
with earlier detection of water leaks from the cooling package or from the target ladder in the vacuum volume when the vacuum interlock has been defeated.
Entry  Wednesday, July 11, 2012, 17:51, Isaac Earle, Repair, Target 1, Target, T1 Target Swap 
 BL1A was started yesterday and brought up to 10μA.  A problem was noticed with the T1 protect monitor (the right and bottom plates were not showing any response when the beam was swept
across the monitor).  The protect monitor is new and was installed on the target assembly in February 2012, so this is the first time it has seen
Entry  Monday, July 09, 2012, 17:17, Isaac Earle, Standard Operation, Target 1, Target, BL1A Start-Up Prep 
 - T1 & T2 targets switched to "remote" control
 - Both target ladders were moved to Position 3 (12mm Be)
 - T2 Q1 flow interlock defeat was removed (only required when target ladder is in position zero)
Entry  Friday, July 06, 2012, 16:03, Isaac Earle, Repair, Target 1, Target, T1-MK2 Target Repair Complete T1MK2_-_July_2012.pdf
 Target elevation measurements and beam spot plots were completed on the T1-MK2 target and the target is now fully repaired and ready for use.  It
will be returned to the storage pit when cranes are available.
A copy of the elevations measurements and beam spot plots is attached.
Entry  Tuesday, July 03, 2012, 13:23, Isaac Earle, Standard Operation, Target 2, Target, T2 Plug Block Replaced & Beam Blockers Tested 
The T2 plug block was replaced and the M9 and M20 beam blockers were tested.  The plug block did not interfere with the travel of the beam blockers.
 There was no change in the T2 vacuum during BB actuation.
Initially there was some confusion about how to actuate the beam blockers.  The following was learned:
Entry  Friday, June 29, 2012, 14:18, Isaac Earle, Repair, Target 1, Target, Manipulator Repair Complete 
 Repair of the west side hot cell manipulator was completed and the manipulator was re-installed into the cell.  The z-motion slave tapes,
upper counterweight tapes, and lower counterweight tapes were replaced on both sides.
100cpm contamination was found on the slave arm from a wet wipe.  No contamination was found in the lab.
Entry  Tuesday, June 26, 2012, 09:05, Isaac Earle, Maintenance, Target 1, Cooling, T1 & T2 Target Water Flow Transducers Serviced T1_&_T2_water_flow.jpg
 The target water outlet flow transducers on the T1 and T2 cooling packages were serviced (new shaft, paddle wheel, & o-ring) to address a noisy
signal.  The service corrected the noisy signal.  Additionally, it appears the worn parts were causing the transducers to read high, as both
dropped approximately 1 gallon/minute after the service.  Both transducers would occasionally trip the high flow warning (8.5gpm), and should now
Entry  Friday, June 22, 2012, 13:54, Isaac Earle, Maintenance, Target 2, Target, Air Amplifier Rebuild Complete 
A full rebuild of the upper air amplifier was completed.  New anodized aluminum barrels were installed (replacing the old brass design), as well
as new pilot valves, piston seals, bearings, and o-rings.  
The amplifier is operating smoothly with a cycle period of 25.6 seconds, compared to 14.8s before rebuild (based on 8 cycle measurents at 110psi
Entry  Friday, June 22, 2012, 13:48, Isaac Earle, Development, Target 1, Cooling, T1 & T2 Expansion Tank Level Sensor Recording Enabled 
Mike Mouat enabled recording for T1 and T2 expansion tank warning and trip level sensors on XTPAGE/XSTRIP.
XSTRIP output is in discreet integers as follows:
2 = Both sensors OK
Entry  Thursday, June 21, 2012, 13:38, Isaac Earle, Standard Operation, Target 2, Cooling, T2 Water Package Started 
 The T2 water package was reconnected to the target and started after being shut-off since April 12, 2012.  The M9 and M20 groups do not anticipate
having to vent the T2 volume, so the package will be left running in preparation for BL1A start-up in early July.  There was no change in T2 vacuum
levels during start-up, and therefore no water leaks into the vacuum volume.
Entry  Monday, June 18, 2012, 16:27, Isaac Earle, Repair, Target 1, Target, T1-MK2 Profile and Protect Monitor Electronics Check 
 Bill Rawnsley and Mike Russell performed a 'blip' test on the T1-MK2 profile monitor and protect monitors today.  A possible bad wire at  #9
location in the vertical array on the profile monitor was found (this is two wires above center).  Bill did not think this was a serious concern and
beam tuning can be (and has been done in the past) with wires missing.  Otherwise the responses were normal for both monitors and the scope readings
Entry  Friday, June 08, 2012, 17:01, Isaac Earle, Repair, Target 1, Target, T1-MK2 Leak Repair Update 
 A leak check was performed on the T1-MK2 target in the hot cell today and confirmed successful leak-free installation of the new water supply tubes,
delta seal retaining rings, and delta seals on the upper slide plate.  The remaining tasks are to install delta seals on the lower slide plate and
have the protect monitor and profile monitor electronics checked by diagnostics group.
Entry  Friday, June 08, 2012, 16:52, Isaac Earle, Repair, Target 1, Target, Broken Manipulator Tape Update 
 The broken tape on the west side hot cell manipulator was found to be one of two "Z motion slave tapes".  The manipulator can still
function normally with only one, however the remaining tape will see twice the load as usual.  It was decided that repair of the manipulator may be
delayed until after the T1-MK2 target repair job is complete.  Lifting of heavy objects using the west side manipulator will be avoided until after