  RH-Meson Hall, Page 15 of 18  Not logged in ELOG logo
IDdown Date Author Category Type Specific Subject Text Attachments
  78   Friday, April 12, 2013, 17:33 Isaac EarleDevelopmentTarget 1CoolingT1 & T2 high-temp limit switch installation, wiring, and commissioning completeInstallation, wiring, and commissioning
of the high temperature limit switches for
the T1 and T2 cooling packages was completed
  
  77   Friday, April 12, 2013, 13:28 Isaac EarleStandard OperationTarget 1CoolingCooling Packages Leak Tight The T1 and T2 expansion tanks were
filled on Monday April 8th.  There was
no change in the level when inspected today
  
  76   Tuesday, April 09, 2013, 17:06 Isaac EarleRepairTarget 1TargetT1 Target Electronics CheckThe T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013.  The response from
  
  75   Tuesday, March 26, 2013, 10:55 Isaac EarleMaintenanceTarget 1TargetT1-MK1 Re-wiring and MRO Complete The following work was performed
on the T1-MK1 target:
- Unused proximity sensor removed
 T1-MK1_Tgt_leak_check.PDF 
  74   Monday, March 18, 2013, 15:17 Isaac EarleMaintenanceTarget 2TargetT2-MK2 Target Maintenance and Re-Wiring- T2-MK2 target moved from beamline to
hot cell (Feb 4th)
- Steel target support shield installed
 IMG_1189.JPGIMG_1194.JPGIMG_1197.JPGIMG_1207.JPGT2-MK2_Tgt_leak_check.PDF 
  73   Wednesday, March 06, 2013, 12:13 Isaac EarleMaintenanceTarget 2CoolingT2 Heat Exchanger MRO- The new tube array was picked up from
Kaltech on Feb 8th (observed vessel holding
60psi on hydro test at their shop)
 7x 
  72   Tuesday, February 05, 2013, 09:50 Isaac EarleMaintenanceTarget 2TargetT2-MK2 target moved from beam line to hot cellThe T2-MK2 target was transported from
the beam line to the RH hot cell.  The
profile monitor was secured in the 'in' position
 IMG_0868.JPG 
  71   Tuesday, January 29, 2013, 15:55 Isaac EarleMaintenanceTarget 2CoolingT2 H.E. Transported to Warm CellFriday Jan 25:
- Both sides of heat exchanger drained,
disconnected, and capped
 IMG_0860.JPGIMG_0864.JPG 
  70   Monday, January 21, 2013, 16:18 Isaac EarleStandard OperationTarget 2TargetT2 Cooling Package Water ReleasedThe T2 cooling package water was drained
to the BL1A active sump, refilled, cycled,
and drained again.  Samples of T2 cooling
  
  69   Monday, January 21, 2013, 11:57 Isaac EarleRepairTarget 2TargetFlask Repair On January 15th, when attempting
to move the T2 target from the beam line
to the hot cell, the latch mechanism on the
 IMG_0818.JPGIMG_0824.JPGIMG_0836.JPGIMG_0838.JPG 
  68   Monday, January 14, 2013, 16:55 Isaac EarleStandard OperationTarget 2TargetTarget Move & Damaged Profile MonitorThe T2-MK1 target (spare T2 target) was
transported from the hot cell to the storage
pit today.  
  
  67   Friday, January 11, 2013, 15:48 Isaac EarleStandard OperationTarget 1TargetBL1A Tunnel Accessed The BL1A tunnel was accessed to drain
and sample T2 cooling package water.  A
puddle of water was noticed in the South
 IMG_0801.JPGIMG_0802.JPG 
  66   Tuesday, January 08, 2013, 10:52 Isaac EarleMaintenanceTarget 2TargetT2-MK1 Target Maintenance- T2-MK1 target transported from storage
pit to hot cell
- Proximity sensor removed
  
  65   Tuesday, January 08, 2013, 09:27 Isaac EarleStandard OperationTarget 2TargetBL1A Air Amplifier turned off for duration of shutdown. The BL1A air amplifier
has been shut down by closing the air supply
  
  64   Monday, December 10, 2012, 15:42 Isaac EarleMaintenanceTarget 1TargetT1-MK2 Target Maintenance- T1-MK2 target moved from storage pit
to hot cell
- Removed unused proximity sensor
  
  63   Thursday, November 22, 2012, 17:22 Isaac EarleStandard OperationTarget 1Active SumpRH Lab Active Sump Released On Wednesday November 21 at approximately
9am the level of the Remote Handling active
sump was inspected and found to be at approximately
  
  62   Tuesday, November 13, 2012, 16:26 Isaac EarleRepairTarget 1TargetManipulator Repair Complete Repair of the west side manipulator
in the west hot cell was completed today.
 Part of the repair was done by entering
  
  61   Wednesday, October 24, 2012, 17:38 Isaac EarleRepairTarget 2TargetT1 & T2 Target Ladder Control System Status During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller
  
  60   Wednesday, October 24, 2012, 17:34 Isaac EarleRepairTarget 1TargetT1-MK2 Target Repair CompleteThe target ladder was detached, old delta
seals removed, sealing surfaces cleaned using
scotchbrite pad and a dremel tool, and delta
  
  59   Friday, September 28, 2012, 15:19 Isaac EarleRepairTarget 1TargetT1-MK2 Delta Seal Leak  After removal of the leaky
target cassette at position 3, plugs were
installed on the target ladder and a leak
  