Thursday, November 06, 2014, 17:22, Ron Kuramoto, Repair, Target 2, Cooling, 1AT2, faulty Thermister water out temperture
Thursday, November 06, 2014, 17:18, Ron Kuramoto, Repair, Target 2, Cooling, 1AT2 Collimator B, faulty Thermister water out temperature
Thursday, October 16, 2014, 17:44, Ron Kuramoto, Repair, Target 2, Water Leak, 1A Tunnel T2 Cu-ALCW water leak repair
6x
Thursday, September 11, 2014, 15:36, Ron Kuramoto, Repair, Target 2, Water Leak, 1A Tunnel T2 Cu-ALCW water leak
Wednesday, August 13, 2014, 16:34, Isaac Earle, Repair, Target 1, Other, Amplified Air Leak Narrowed Down to T1 Area
Monday, August 11, 2014, 16:57, Isaac Earle, Repair, Target 2, Other, Air Amplifier Increased Cycle Rate
Wednesday, July 02, 2014, 16:56, Isaac Earle, Repair, Target 1, Cooling, T1-P2 and T2-P1 pressure transducers replaced.
Tuesday, June 03, 2014, 22:56, Isaac Earle, Standard Operation, Target 2, Target, T2 Target Position Moves (Development Shift)
Wednesday, May 14, 2014, 20:36, Grant Minor, Development, Target 2, Target, Target exercised to position 0, then back to 2.0 mm above position 4
Monday, May 05, 2014, 15:46, Isaac Earle, Repair, Target 2, Target, T2 Protect Returned to B/L
Friday, May 02, 2014, 15:49, Isaac Earle, Repair, Target 2, Target, T2 Protect Monitor Elevation Correction
Monday, April 14, 2014, 15:30, Isaac Earle, Standard Operation, Target 2, Target, T2 Target Moved to Position 4
Thursday, April 03, 2014, 16:35, Isaac Earle, Standard Operation, Target 1, Cooling, T1 Cooling Package Started
Thursday, April 03, 2014, 13:43, Isaac Earle, Standard Operation, Target 2, Target, T2 Profile Monitor OK
Thursday, April 03, 2014, 10:19, Isaac Earle, Standard Operation, Target 2, Cooling, T2 Cooling Package Resin Can Replaced
Tuesday, April 01, 2014, 10:17, Isaac Earle, Repair, Target 2, Target, T2 Profile Monitor Actuation - Fault Report
Friday, March 28, 2014, 13:59, Isaac Earle, Maintenance, Target 2, Cooling, T2 P1 Transducer and T2 Q1 Flow Meter Replaced
Tuesday, March 25, 2014, 18:24, Isaac Earle, Development, Target 2, Water Leak, Water Detecting Sensor Install at T1 & T2
9x
Monday, March 24, 2014, 18:14, Isaac Earle, Standard Operation, Target 2, Cooling, T2 Cooling Package & Air Amplifier Started
Tuesday, March 11, 2014, 13:50, Isaac Earle, Repair, Target 2, Target, T2 Protect Monitor Returned to Beam Line