Entry  Tuesday, April 16, 2019, 15:35, Keith C Ng, Repair, Other, M9, M9 project post shutdown summary 
 Completed work at m9 beam line:
- Removed existing service stand and associated cable and water services. Legacy b1 water services still need to be removed for future magnet installation.
Old service stand is currently in warm cell waiting for disposal.
Entry  Friday, February 28, 2020, 09:06, Isaac Earle, Development, Other, M9, M9 Q1Q2 service stand floor plate installed M9_service_stand_floor_plate_TB23351.png
 The M9 service stand floor plate (TB23351) was installed in the M9 pit yesterday.  Prior to installation all 5 threaded inserts were tested
using a 1/2"-13 stud tool on an RH pole.  The west most hole (shown in red below) had damaged threads and the stud could only be threaded in
2 turns.  All other locations (shown in green) had usable threads with 6-8 full turns possible with the stud tool.  The plate was installed using
Entry  Wednesday, March 11, 2020, 10:29, Isaac Earle, Development, Other, M9, M9 Q1Q2 service stand foot plate installed 
 The M9 Q1Q2 "foot" plate (TB23363) has been installed over the floor plate.  A nominal gap between the plates of 1/2" was set
before lowering the plate, it was then leveled using the three adjustment bolts resulting in a larger gap.  After leveling, the plate was lifted to
remove the spirit levels and lock the position of the leveling bolts.  The plate was then re-lowered and the tiedown bolt assemblies (TB23383) were
Entry  Monday, April 06, 2020, 15:02, Isaac Earle, Standard Operation, Target 2, M9, M9 beam blocker returned to beamline 
The M9 beam blocker was returned to the beamline today using the RH shielded transport flask.  The top flange o-ring was replaced before installation.
After installation the "Lift T" assembly was removed, and electrical cable and air supply connected.  Correct functionality of the
limit switches was confirmed with the control room.  Actuation of the beam blocker could not be tested at this time because control takes place through
Entry  Tuesday, June 09, 2020, 17:01, Isaac Earle, Development, Other, M9, Cables and helium leak check line installed to M9 service stand 
 The 10-pin thermal switch wire, 2-pin steering wire for Q2, and a 1/4" copper tube for remote helium leak check were installed through the
service chase with the power cables and connected to the M9 service stand.  Approximately 10m of extra cable (2-pin and 10-pin) was coiled and left
in the cooler section of the service chase after the first sharp bend.  The cables and the tubing are currently run as far as the vertical cable tray
Entry  Wednesday, June 10, 2020, 08:58, Isaac Earle, Development, Other, M9, T2-M9 and M9-B1 flange scan data 2017-03-28_meson_hall_t2_with_import_of_2015_data.xit642019-25-01_meson_hall_t2_data.xit64
 Laser tracker scan data from 2017 and 2019 attached as a backup.  Original files from Beamlines Group who also keep copies on \\trwindata\experimental
support\alignment\T2-M9_data
Entry  Friday, June 12, 2020, 13:54, Isaac Earle, Development, Other, M9, M9 Q1Q2 water header installed 2.jpg1.jpg
The Q1Q2 water header (TB23481) was mounted this morning as per installation drawing TB23400.
Heat shrink tubing was applied to the B1 power cables (two positive, two negative) over the length of cable in the highest field which was showing
some signs of radiation damage on the insulation.  The tubing used was McMaster-Carr PN 75665K932 (Clear PTFE, 4:1 shrink ratio, 1.0" ID before
Entry  Tuesday, July 07, 2020, 13:22, Isaac Earle, Development, Other, M9, M9 Q1Q2 8.jpg1.jpg4.jpg6.jpg
 The M9 Q1Q2 magnet assembly lift beam has been installed according to drawing TB23401.  The side-to-side as well as beam-axis direction adjustment
features were tuned so that the assembly is level when lifted.
 
Entry  Tuesday, July 07, 2020, 15:13, Isaac Earle, Development, Other, M9, M9 Q1Q2 service stand Lemo connector wiring Lemo_pin_wiring.PNG
The diagram below shows the wiring for the two connectors on the service stand (the wires running from the stand to the power supplies.  (see TB23400
for details)
 
Entry  Thursday, July 09, 2020, 06:44, Isaac Earle, Development, Other, M9, Alignment of M9 Q1Q2 magnets complete 
 Mike Vogel reported that alignment of the Q1Q2 assembly w.r.t. the T2 and B1 flanges was completed on July 7.  This was performed in the test
stand with the flange positions set to the measurements taken in the 2019 shutdown.  Alignment to the theoretical location was achieved within 0.1mm.
The axis of the Q1 and Q2 magnets were aligned to each other previously within similar accuracy.
Entry  Wednesday, May 04, 2022, 11:27, Adam Newsome, Standard Operation, Target 2, M9, M9 and M20 Beam Blocker Actuation Test 
The beam blockers for M9 and M20 were actuated, and vacuum was monitored to ensure no disruptions. Both actuation tests were successful. Motion was observed
and no abnormalities noted. Cabling and air connections checked: OK.
 
Entry  Wednesday, July 06, 2022, 12:49, Adam Newsome, Repair, Other, Hot Cell, Hot Cell - Helium wand tubing broken 
The tubing for the helium wand inside the hot cell is broken and needs to be replaced. More tubing has been ordered and the job will be completed in
the coming weeks.
Entry  Wednesday, July 06, 2022, 12:52, Adam Newsome, Other, Other, Hot Cell, Potential hot cell window oil leak 
Some oil was noticed around the hot cell window, on the control panel, and on the ground below the control panel. A leak is suspected. 
 
Suggest tightening all bolts to specified torque along the window, and monitoring overflow oil level (position today was marked). If the problem
Entry  Thursday, July 28, 2022, 12:51, Adam Newsome, Repair, Other, Hot Cell, Meson Hall Hot Cell - Nuclear Ventilation Issue 
It was reported today by Peter Bratt that the nuclear ventilation system for the hot cell is not functioning. At this time, the cause of the issue is
unknown. Remote Handling and Electrical Services are investigating. This e-log will be updated when the issue is resolved.
 
Entry  Tuesday, August 30, 2022, 14:24, Adam Newsome, Maintenance, Other, Hot Cell, Nuclear Ventilation - Filter Change 
Mechanical Services Group changed the pre-filter in the ventilation system on Aug. 29, 2022 as per work permit C2022-08-29-2.
 
It is recommended that Mechanical Services change the HEPA filter as soon as possible. These filters are on order with approximately 7 month lead
Entry  Wednesday, May 03, 2023, 10:06, Adam Newsome, Maintenance, Other, Hot Cell, Meson Hall Hot Cell - Nuclear Ventilation HEPA Filter Changed, Operational 
The HEPA filter in the nuclear ventilation system for the Meson Hall Hot Cell was changed and tested by mechanical services under work permit C2023-04-25-14.

 
Entry  Thursday, February 01, 2024, 11:14, Albert Kong, Standard Operation, Target 1, Hot Cell, T1-MK1 Flush and Purge on Hot Cell IMG_3950.JPEGIMG_3975.JPEGIMG_3973.JPEGIMG_3971.JPEGT1&T2_Pump-Down_and_Leak_Check_Record_05_FEB_2024.pdf
The recently removed T1-MK1 target ladder was flushed with city water for ~30s at all target positions. It was then purged with compressed air at ~5
psi for ~1 minute at all target positions. We then left the target ladder in pos5 to fully extend the bellows and allow it to dry overnight.
This ELOG will be updated as we progress with work done to dry the target ladder and eventually exchange the spent targets.
Entry  Thursday, February 15, 2024, 12:38, Riley Sykes, Repair, Other, Hot Cell, Indium Extruder Hand Pump 
Feb 1 2024
Hand Pump observed to be losing pressure at full extension of cylinder, seals likely blown. Due to Enerpac P84 being an obsolete model, a newer
model hand pump was ordered.
Entry  Thursday, October 10, 2024, 12:24, Adam Newsome, Other, Other, Hot Cell, Safety Walkaround Complete - Meson Hall HC/WC Area 
A safety walkaround was completed for the Meson Hall Hot/Warm Cells. 
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: 
Entry  Friday, November 29, 2024, 11:57, Adam Newsome, Maintenance, Other, Hot Cell, Hot cell and warm cell maintenance tasks Operator_left_oil_level_before_refill.jpgOperator_Left_oil_level_after_refill.JPGOperator_right_oil_level.jpgRight_window_water_level_before_refill.jpgWarm_cell_water_window_after_refill.jpg
The following maintenance tasks were completed on 2024-11-29 by A. Newsome, A. Kong, A. Tam, M. Dalla Valle:

    Warm cell right window water level topup... the water level was a couple inches lower from the top. Using a tube connected to the nearby
sink, the level was topped up fully. See attached before/after picture.
    Hot cell oil level checks:
    
        Right side OK.