  ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  2725   Tuesday, December 03, 2024, 10:10 Frank SongITEStandard OperationTM2Ta#68module disconnectionTM2 with spent target TA#68 was disconnected 
in ITE and is being moved to SHC. All water
lines are purged for module storage.
 TM2_with_spent_target_TA#68_disconnection_in_ITE_2024-12-03.pdf 
  2729   Wednesday, December 04, 2024, 08:05 Frank SongITEStandard OperationTM3UCx#47Module ConnectionTM3 with new target UCx#47 was connected
in ITE right after be moved from TCS. 
 TM3_with_new_target_UCx#47_connection_in_ITE_2024-12-03.pdf 
  2742   Tuesday, January 07, 2025, 12:05 David WangITEStandard OperationTM3UCx #47ITE primary and secondary vacuum vessel leak check for 2025 shut downITE primary and secondary vacuum vessel
leak check for 2025 shut down have been done.
No leak.  The TM3 waterlines helium
  
  2747   Monday, January 13, 2025, 10:36 Frank SongITEStandard OperationTM3UCx#47module disconnection TM3 with spent target UCx#47 was
disconnected in ITE and will be moved to
SHC.
 TM3_with_spent_target_UCx#47_disconnection_in_ITE_2025-01-13.pdf 
  2643   Wednesday, July 17, 2024, 15:06 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround Complete - SHC/NHC AreaA safety walkaround for July 2024 was completed
for the B2 level by A. Newsome. No deficiencies
to report.
  
  2704   Thursday, October 10, 2024, 12:20 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround complete - ISAC Hot Cells, Target HallA safety walkaround was completed for the
ISAC Hot Cells and Target Hall Areas. 
The resulting spreadsheet can be
  
  2705   Friday, October 11, 2024, 15:59 Aaron TamFacilitiesRepair  ISAC B2 North Hot Cell Phone Fixed Resolution comment / Commentaire
de résolution:
    
  
  2730   Wednesday, December 04, 2024, 09:00 David WangFacilitiesStandard OperationTM2 all water lines on TM2 have been purged.all water lines on TM2 have been purged.
Refilled them(except HS ) with 60psi nitrogen
for module silo storage before next year
  
  2738   Friday, January 03, 2025, 09:59 Adam NewsomeFacilitiesStandard Operation  Safety Walkaround complete - ISAC Hot Cells, Target HallA safety walkaround was completed for the
ISAC Hot Cells and Target Hall Areas.
The resulting spreadsheet can be
  
  2744   Thursday, January 09, 2025, 11:08 David WangFacilitiesMaintenance  ITH:MP1 is deteriorating by watching on ITH:CG1 and CG2 readingsITH:MP1 is deteriorating by watching on
ITH:CG1 and CG2 readings and investigation
in pit. A fault 17644 has been issued. this
  
  146   Friday, July 13, 2012, 16:33 Bevan MossCraneRepair  Crane has stopped workingIn the AM today David and I used the crane
to raise the ground plate sheet metal into
place. This afternoon when I attempted to
  
  147   Monday, July 16, 2012, 11:55 Bevan MossCraneRepair  Crane has stopped working

    

       
            
  
  500   Tuesday, October 08, 2013, 18:12 Grant MinorCraneRepairTM4 Target Hall Crane Stuck in East-West Direction - UpdateGrant Minor wrote this e-mail today:
***
Hello all,
 THall_Crane_Bridge_Wheel_at_South_Rail_Splice_8Oct2013.JPGNORELCO_inv13045_joMS-064_31March2013.pdf 
  501   Wednesday, October 09, 2013, 19:33 Grant MinorCraneRepairTM4 Target Hall Crane not operational - likely controls / PLC hardware failure (not stuck wheel)

    

       
            
  
  503   Tuesday, October 15, 2013, 16:44 Grant MinorCraneRepair  Target Hall Crane - operational with temporary thermal sensor bypassE-mail correspondence on the Target Hall
crane fault diagnosis between October 11th
and 15th:
 ISAC_THall_Crane_elec_E5_1slash1_15Oct2013.pdf 
  557   Tuesday, November 26, 2013, 14:10 Travis CaveCraneMaintenance  Thermal relay replacedThe bad thermal motor protection relay
for the crane has been replaced with a new
unit. Crane was tested in pendant(local)
  
  840   Friday, February 06, 2015, 08:06 David WangCraneRepair  TH crane lost movement controls since last Friday.Last Friday, During the crane per use check,
I found the main power supply to to crane
was shut off. I was told   Don and Travis
  
  841   Friday, February 06, 2015, 12:27 David WangCraneRepair  TH crane troubleshoot Gordon crane technician started TH crane
trouble shooting this morning. The problem
is found that there is no 115VAC power supply
  
  843   Thursday, February 12, 2015, 09:11 David WangCraneRepairTM4 TH crane troubleshoot and annual inspection.Gordon crane technicians continued their
troubleshooting on this Tuesday. They found
the crane up-limit protection switch which
  
  844   Monday, February 16, 2015, 11:57 David WangCraneRepair  TH craneDave.Morris installed a new battery on
crane control PLC board and uploaded the
program. Travis, Dan and I tested the crane
  