Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 96 of 135  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Wednesday, January 07, 2015, 09:31, Anders Mjos, Conditioning Station, Development, TM2, , High Voltage Conditioning 

No Source Tray installed. Loop on cooling circuit D. All other circuits blanked off.

Voltages stated below are set point voltages. These corresponds reasonably well with the local read backs on the power supplies. The read back voltages in EPICS are somewhat lower.

Wednesday, January 07, 2015, 09:16: 20 / 10 kV (BIAS / EL)

Wednesday, January 07, 2015, 09:20: Vacuum responses from BIAS 27 kV. Corresponds to each increase in bias voltage.

Wednesday, January 07, 2015, 09:40: 30 / 15 kV 

Wednesday, January 07, 2015, 10:28: Sparking and vacuum responses continues with every 100 V BIAS increase. If the voltage is lowered and brought back up, no sparks are observed; the module is conditioning.

Wednesday, January 07, 2015, 12:09: 34 / 17.5 kV

 Wednesday, January 07, 2015, 13:05: 35 / 17.5 kV

Wednesday, January 07, 2015, 14:50: 37.5 / 20 kV

Wednesday, January 07, 2015, 15:40: 38.5 / 20 kV

Wednesday, January 07, 2015, 16:02: BIAS and EL power supplies off.


Thursday, January 08, 2015, 10:00: HV condtioning continues

Thursday, January 08, 2015, 10:11: 35 / 20 kV

Thursday, January 08, 2015, 10:29: 38.5 / 20 kV

Thursday, January 08, 2015, 11:43: 40 / 20 kV

about 15 sparks per hour (5 / 20 min)

Thursday, January 08, 2015, 14:41: 42.5 / 22.5 kV

Thursday, January 08, 2015, 15:08: Communication lost with RGA. Could not be recovered.

Thursday, January 08, 2015, 15:58: 45 / 22.5 kV

Thursday, January 08, 2015, 16:27: BIAS and EL power supplies off.


Friday, January 09, 2015, 08:52: 45 / 22.5 kV

Tried to recover RGA by unplugging and plugging power cord, but no success.

Friday, January 09, 2015, 10:45: Increased sparking at 48 kV - reduced to 47.5 kV

Friday, January 09, 2015, 11:53 : 50 / 25 kV

Friday, January 09, 2015, 12:28: ~ 1 spark / minute for the last 10 min

 Friday, January 09, 2015, 15:27: ~25 sparks / hour for the last 20 min

Friday, January 09, 2015, 16:18: ~18 sparks / hour for the last 20 min


Monday, January 12, 2015, 09:31: 50 / 25 kV

Monday, January 12, 2015, 10:31: No sparks for 20 min after ~30 min of conditioning.

Monday, January 12, 2015, 12:24: BIAS / EL power supplies tripped on conductivity (spark)

Monday, January 12, 2015, 13:13: 55 / 27.5 kV

Monday, January 12, 2015, 14:32: 1 spark for the last 10 min

Monday, January 12, 2015, 15:38: 57 / 30 kV

Monday, January 12, 2015, 15:48: ~60 sparks / hour for the last 10 min

Monday, January 12, 2015, 16:00: BIAS and EL power supplies off.


Tuesday, January 13, 2015, 08:45: 55 / 27.5 kV

Tuesday, January 13, 2015, 09:18: ~60 sparks / hour for the last 10 min

Tuesday, January 13, 2015, 10:17: No sparks for the last 10 min

Tuesday, January 13, 2015, 10:30: 57.5 / 30 kV

Tuesday, January 13, 2015, 11:34: 59 / 30 kV

Tuesday, January 13, 2015, 13:23: No sparks for the last 25 min 

Tuesday, January 13, 2015, 14:11: 60 / 30 kV

Tuesday, January 13, 2015, 14:42: Spark tripped TP2 and TP1S and both power supplies

Tuesday, January 13, 2015, 15:02: 60 / 30 kV (local read back 60.5 / 30 kV, 0.1 / 0.15 mA)

Tuesday, January 13, 2015, 15:38: BIAS and EL power supplies off.


Wednesday, January 14, 2015, 08:34: 60 / 30 kV

Wednesday, January 14, 2015, 10:41: 3 sparks / hour for the last 60 min

Wednesday, January 14, 2015, 13:39: 61 / 30 kV

Wednesday, January 14, 2015, 14:29: 61.5 / 30 kV (local read back 62 / 30 kV, 0.1 / 0.15 mA)

Wednesday, January 14, 2015, 15:40: ~ 6 sparks / hour for the last 20 min

Wednesday, January 14, 2015, 16:07: TP2 found to be tripped off. Restarted.

Wednesday, January 14, 2015, 16:23: 60 sparks / hour for the last 20 min

Wednesday, January 14, 2015, 16:28: BIAS and EL power supplies off.


Thursday, January 15, 2015, 08:27: 60 / 30 kV

Thursday, January 15, 2015, 11:24: ~35 sparks / hour for the last 20 min

Thursday, January 15, 2015, 14:09: 12 sparks / hour for the last 60 min

Thursday, January 15, 2015, 15:33: 58 / 30 kV

Thursday, January 15, 2015, 15:49: 56 / 30 kV

Sparks observed both at 58 and 56 kV

Thursday, January 15, 2015, 15:57: BIAS and EL power supplies off.


Monday, January 19, 2015, 09:53: 55 / 30 kV

Monday, January 19, 2015, 11:44: ~20 sparks / hour for the last 20 min

Monday, January 19, 2015, 12:53: ~10 sparks / hour for the last 20 min 

Monday, January 19, 2015, 16:30: 50 / 30 kV

Monday, January 19, 2015, 17:31: BIAS and EL power supplies off.


Tuesday, January 20, 2015, 08:54: 40 / 20 kV

Tuesday, January 20, 2015, 09:05: 50 / 25 kV

Tuesday, January 20, 2015, 13:43: 8 sparks / hour for the last 60 min

Tuesday, January 20, 2015, 16:43: 3 sparks / hour for the last 60 min


Wednesday, January 21, 2015, 09:10: 40 / 20 kV

Wednesday, January 21, 2015, 09:20: No sparks

Wednesday, January 21, 2015, 09:23: 50 / 25 kV

Wednesday, January 21, 2015, 10:33: 3 sparks / hour for the last 60 min

Wednesday, January 21, 2015, 13:43: 6 sparks / hour for the last 60 min

Wednesday, January 21, 2015, 16:07: 5 sparks / hour for the last 60 min

Wednesday, January 21, 2015, 16:09: BIAS and EL power supplies off.


Thursday, January 22, 2015, 09:11: 40 / 20 kV

Thursday, January 22, 2015, 10:14: No sparks

Thursday, January 22, 2015, 10:16: 45 / 25 kV

Thursday, January 22, 2015, 11:26: No sparks

Thursday, January 22, 2015, 16:57: No sparks

Thursday, January 22, 2015, 16:57: BIAS and EL power supplies off.


Friday, January 23, 2015, 09:28: 40 / 20 kV

Friday, January 23, 2015, 09:39: No sparks

Friday, January 23, 2015, 09:40: 50 / 25 kV 

Friday, January 23, 2015, 16:16: No sparks.

Friday, January 23, 2015, 16:17: BIAS and EL power supplies off. 


Monday, January 26, 2015, 09:17: 40 / 20 kV

Monday, January 26, 2015, 09:29: No sparks

Monday, January 26, 2015, 09:30: 50 / 25 kV

Monday, January 26, 2015, 09:52: No sparks

Monday, January 26, 2015, 09:53: 55 / 27.5 kV

Monday, January 26, 2015, 16:55: No sparks for 7 hours. BIAS and EL power supplies off. 


Tuesday, January 27, 2015, 09:10: 40 / 20 kV

Tuesday, January 27, 2015, 09:16: 50 / 25 kV  

Tuesday, January 27, 2015, 09:31: 55 / 27.5 kV

Tuesday, January 27, 2015, 09:51: No Sparks

Tuesday, January 27, 2015, 09:53: 57.5 / 30 kV (one spark while increasing BIAS voltage)

Tuesday, January 27, 2015, 10:14: No sparks

Tuesday, January 27, 2015, 10:18: 58 / 30 kV. Some sparks

Tuesday, January 27, 2015, 10:46: 59 / 30 kV. Some sparks while increasing BIAS voltage

Tuesday, January 27, 2015, 11:43: 59.5 / 30 kV. Some sparks while increasing BIAS voltage

Tuesday, January 27, 2015, 13:24: Spark

Tuesday, January 27, 2015, 13:33: 11 sparks for the last 10 min

Tuesday, January 27, 2015, 13:33: 59 / 30 kV

Tuesday, January 27, 2015, 13:35: 57.5 / 30 kV 

Tuesday, January 27, 2015, 16:14: ~3 sparks / hour for the last 60 min

Tuesday, January 27, 2015, 16:53: ~3 sparks / hour for the last 60 min

Tuesday, January 27, 2015, 16:55: BIAS and EL power supplies off. 


Wednesday, January 28, 2015, 09:11: 40 / 20 kV

Wednesday, January 28, 2015, 09:17: 50 / 25 kV 

Wednesday, January 28, 2015, 09:27: 55 / 27.5 kV 

Wednesday, January 28, 2015, 10:35: 11 sparks observed. BIAS and EL off - preparing for power outage

Entry  Tuesday, January 06, 2015, 11:21, Anders Mjos, Conditioning Station, Development, TM2, , He leak check of cooling circuits. 2015-01-06_He_leak_check_water_circuits.pdf

No leak detected on either He-detector (connected directly to Service Cap) or on RGA. See attached screen shots.

A vacuum increase (air only on RGA) was seen when de-pressurizing circuit I.

Entry  Tuesday, January 06, 2015, 11:14, David Wang, ITE, Standard Operation, TM4, , 4 Shielding blocks have been moved out of ITE . 

4 shielding blocks have been moved out of  ITE to block storage area. Fiona did the survey and with me during the move.

Entry  Monday, January 05, 2015, 15:01, Anders Mjos, Conditioning Station, Development, TM2, , RGA switched on 
 
Entry  Monday, January 05, 2015, 12:47, Anders Mjos, Conditioning Station, Development, TM2, , Cooling package started 

 by "enable staging" button. MP3 has to be turned off-on to open WPV1

Entry  Tuesday, December 23, 2014, 14:10, Anders Mjos, Conditioning Station, Development, TM2, , He leak check of the Service Cap using RGA 

The RGA showed no response to He-spray on the Service Cap. He stable at 3.5E-9 T partial pressure, water at 1.3E-6 T. IG1 at 9.9E-8 T

Entry  Monday, December 15, 2014, 15:55, Grant Minor, Conditioning Station, Repair, , , Access to ISAC TCS TK2 Expansion Tank - Fall Arrest TK2_Expansion_Tank_Elevation_ISAC1_Exp_Hall_15Dec2014.JPGTK2_Expansion_Tank_-_Fall_Arrest_Config_1_-_15Dec2014.JPGTK2_Expansion_Tank_-_Fall_Arrest_Config_2_-_15Dec2014.JPGTK2_Expansion_Tank_-_Fall_Arrest_Config_3_-_15Dec2014.JPG

Hello all,

Access was required this morning to the TCS TK2 Expansion Tank to open a valve and re-fill the tank.

As the access path to this tank lacked any form of Fall Protection, Fall Arrest was employed.

Worksafe BC Part 11 Section 11.2 requires fall protection to be employed at elevations greater than 3 meters.  The expansion tank is located at an elevation far exceeding this regulation.
http://www2.worksafebc.com/publications/ohsregulation/part11.asp

The worker, Allon Messenberg, was fitted with a harness, personal self-retracting lifeline / lanyard with shock-pack, and carried two steel rope ring-ended slings with him to tie off to the structural beams overhead.  All products used were DBI-Sala safety products, which are kept in the Remote Handling machine shop Fall Protection Equipment lockers.  Several RH group members have keys to this locker, including me.

Three configurations were required to gain access to the tank (photo attached):
Configuration 1: Traversing the section between the 2nd floor offices and the ventilation duct.
Configuration 2: Traversing the section between the ventilation duct and the "cross point" of the structural beams.
Configuration 3: Tied-off to the "cross point" of the structural beams and working within the reach limits of the personal SRL and shock-pack.

Transitions between the three configurations required brief moments of un-clipping from the harnesses.  This will be solved in the future via the use of additional carabiners and lanyards.

Operations has advised me that they have observed either TRIUMF workers or contractors working in this area without wearing Fall Arrest equipment.  My request is for staff and operations to stay vigilant in observing access to this area. 

Any work performed in this area without the usage of fall arrest must be reported in an NCR.

I welcome any comments from those who have ideas for improving the safe method of access to this tank.

The cooling package is described in the TCS operating manual, Document-103881.  Page 8 states clearly that Fall Arrest is required to access this valve.

Regards,

Grant

Entry  Monday, December 15, 2014, 08:50, Anders Mjos, Conditioning Station, Maintenance, TM2, , TK2 level below 15 in (secondary loop) 

 The level dropped below 15 in over the weekend. MP2 stopped, but MP3 condtinued pumping.

    Reply  Monday, December 15, 2014, 09:41, Anders Mjos, Conditioning Station, Maintenance, TM2, , Water leak found at the isolation transforer 

Anders Mjos wrote:

 The level dropped below 15 in over the weekend. MP2 stopped, but MP3 condtinued pumping.

 e-fault submitted and Niel Wong has been contacted.

Niel Wong came and had a look at the system. We decided to close the circuit as the water is no longer used with the new power supplies. The circuit will be monitored, but not repaired unless it is needed again.

       Reply  Monday, December 15, 2014, 12:53, Anders Mjos, Conditioning Station, Maintenance, TM2, , TCSTK2 topped up 

Anders Mjos wrote:

Anders Mjos wrote:

 The level dropped below 15 in over the weekend. MP2 stopped, but MP3 condtinued pumping.

 e-fault submitted and Niel Wong has been contacted.

Niel Wong came and had a look at the system. We decided to close the circuit as the water is no longer used with the new power supplies. The circuit will be monitored, but not repaired unless it is needed again.

 Due to the water leak, the expansion tank needed topping up. It was filled from 14 in to 20 in. See work permit I2014-12-15-2.

       Reply  Monday, December 15, 2014, 13:25, Anders Mjos, Conditioning Station, Maintenance, TM2, , BIASSW1 temperature and flow removed from interlock chain 

Anders Mjos wrote:

Anders Mjos wrote:

 The level dropped below 15 in over the weekend. MP2 stopped, but MP3 condtinued pumping.

 e-fault submitted and Niel Wong has been contacted.

Niel Wong came and had a look at the system. We decided to close the circuit as the water is no longer used with the new power supplies. The circuit will be monitored, but not repaired unless it is needed again.

The valved off water circuit has been valved off and  TCS:WFB2:BIASSW1 and TCS:TCM2:BIASSW1 have been removed from the power supply interlock chain by Dave Morris.

Entry  Monday, December 08, 2014, 15:22, Anders Mjos, Conditioning Station, Development, TM2, , Circuit D water test TCS_Heater_Transmission_Power.xlsxCircuit_D_test_results_for_TM2_status_meeting_2014-12-11.pdfHeated_water_leak_test_plan.pdfHeated_water_leak_test_Circuit_D_RESULTS.docx

Monday, December 08, 2014, 14:00: Dan M and Anders connected the water supply to circuit D and installed the module cover.

Monday, December 08, 2014, 14:50: Circulating water on circuit D. IG1 vacuum stable at 3.1E-7 T. No response on mass 18 on RGA

Monday, December 08, 2014, 15:30: Test TGHT and TBHT PS. Can be switched on, but set points need to be corrected.

Monday, December 08, 2014, 16:11: Started CHILLCP2

Monday, December 08, 2014, 16:26: Stopped CHILLCP2


Tuesday, December 09, 2014, 09:02: Started CHILLCP1. TS5 at 31.5 C

Tuesday, December 09, 2014, 09:33: Stopped CHILLCP1. TS5 at 17. 1 C

Tuesday, December 09, 2014, 14:54: Tested TGHT to 600 A and 2.05 V (local read back). EPICS read back and set point is not correct. Circuit resistance ~ 3.4 mOhm.

Tuesday, December 09, 2014, 15:14: Tested TBHT to 272 A and 0.97 V (local read back). EPICS read back and set point is not correct. Circuit resistance ~ 3.6 mOhm.

Tuesday, December 09, 2014, 16:01: TGHT and TBHT switched off.


Wednesday, December 10, 2014, 08:30: TGHT and TBHT power supplies cannot be run with TS5 > 25. Bypasses/Forces not implemented. Waiting for controls.

Wednesday, December 10, 2014, 10:44: Water is stable on RGA, however N, O and Ar shows repeated short term spikes of ~4x magnitude. Spikes are also visible on IG1


Vacuum stable over night.

Thursday, December 11, 2014, 08:22: Starting CHILLCP3. TS5 at 33.1 C, TBHT at 30.2 C

Thursday, December 11, 2014, 08:58 : Staging enabled


Vacuum stable over night.

Dave M corrected scale of TGHT and TBHT.

TS5 forced


 

Lost water in expansion tank over the weekend. See other e-log entries regarding the water leak and fix. Vacuum stable over the weekend.

Monday, December 15, 2014, 13:49: TGHT and TBHT PS at 600 A and 270 A

Monday, December 15, 2014, 14:06: TGHT to 700 A

Monday, December 15, 2014, 18:03: Autoramping down at 5 A/15 s

Monday, December 15, 2014, 18:26: TGHT and TBHT at 0 A. TS5 is at 35 C


Vacuum stable over night

Tuesday, December 16, 2014, 08:07: TGHT and TBHT to 700 A and 270 A

Tuesday, December 16, 2014, 09:00: Stopped MP2. MP3 tripped. TGHT and TBHT tripped.

Tuesday, December 16, 2014, 09:05: started MP2, TGHT and TBHT

Tuesday, December 16, 2014, 16:21: TGHT to 600 A. Will leave both TGHT and TBHT on over night to keep the water warm.


Vacuum stable over night. TS5 at 37.5 C TBHT return at 34.5 C

Wednesday, December 17, 2014, 08:15: TGHT to 750 A

Wednesday, December 17, 2014, 08:35 : TGHT to 800 A

Wednesday, December 17, 2014, 16:09 : TGHT to 700 A. TS5 at 40 C TBHT return at 37 C


Vacuum stable over night. TS5 at 39.3 C and TBHT return at 36.2 C

Thursday, December 18, 2014, 07:54: Starting CHILLCP1

Thursday, December 18, 2014, 08:34: Stopped cHILLCP1 TS5 at 20 C

Thursday, December 18, 2014, 09:07: TGHT to 800 A

Thursday, December 18, 2014, 16:10: TGHT to 700 A


Vacuum stable over night. TS5 at 39.0 C and TBHT return at 35.9 C

Friday, December 19, 2014, 08:17: TGHT to 800 A

Friday, December 19, 2014, 11:54: TGHT to 650 A. TS5 at 39.9 C 


Vacuum stable over the weekend. TS5 at 38.4 C and TBHT return at 35.4 C

Monday, December 22, 2014, 08:31 : Started CHILLCP3

Monday, December 22, 2014, 09:30: Stopped CHILLCP3 

Monday, December 22, 2014, 10:08: TGHT to 800 A

Monday, December 22, 2014, 16:25: TGHT to 700 A


Vacuum stable over night. TS5 at 38.4 C and TBHT return at 35.3 C

Tuesday, December 23, 2014, 08:16: TGHT to 800 A

Tuesday, December 23, 2014, 13:10 : Starting CHILLCP3. TS5 at 39.5 C and TBHT return at 36.4 C

Tuesday, December 23, 2014, 13:14: TGHT and TBHt to 0 and off. 

Leak check found no leaks on Service Cap

Tuesday, December 23, 2014, 14:14 : Stopped CHILLCP3

Tuesday, December 23, 2014, 14:20: RGA filament off

Tuesday, December 23, 2014, 14:23: Stopped MP2 and MP3

Entry  Friday, December 05, 2014, 13:46, Anders Mjos, Conditioning Station, Development, TM2, , Not able to start water system 

 TCS:WPV1 does not open when staging is enabled. Multiple attempts have been made, but the valve remains closed.

    Reply  Monday, December 08, 2014, 13:52, Anders Mjos, Conditioning Station, Development, TM2, , Fixed - Not able to start water system 

Anders Mjos wrote:

 TCS:WPV1 does not open when staging is enabled. Multiple attempts have been made, but the valve remains closed.

 Dave Morris looked at the PLC controls and found that the code was not writing to the output after the PLC migration. He corrected it.

Entry  Friday, December 05, 2014, 15:41, Anders Mjos, Conditioning Station, Development, TM2, , RGA results 2014-12-05-14-25_TM2.png2014-12-05-14-25_TM2.txt

Measurement taken at 14:25. IG2 at ~7.7E-6 T

Entry  Friday, December 05, 2014, 11:58, David Wang, Conditioning Station, Development, TM2, , helium pressure test on TM2 tube heater +(D) water lines. 6x

At CS, The leak detector is hooked directly to the TM2 top service cap. The base LR 0.0xE-9 atm.cc/sec, base pressure 0.0xE-4torr. Applied 80 psi helium to TM2 tube heater +(D) line . During 3 minutes applying time , I did  not see any tiny change on LD readings. The line is perfectly vacuum sealed.  See attachment pictures.

Entry  Friday, December 05, 2014, 07:47, David Wang, Conditioning Station, Development, TM2, , TM2 at CS 

The pumping down on TM2 at CS was good overnight. However, the back up line pressure is still too high for LD to get to 0.0-E-9atm.cc/sec . It only could get to 1.2xE-7 atm.cc/sec. It is not enough for a good leak check . I dont want to have any ambiguous situation on this" D" line leak check. So,I am going to reconfigure the leak detector to the spare KF25 pot on the TM2 service cap. All pumps are stopped . The CS and TM2 will be vented soon. After that, a manual valve will be installed on that spare KF25 pot for future helium pressure check at CS. Then, The TM2 and CS will be pumped down again.

Entry  Thursday, December 04, 2014, 16:37, David Wang, Conditioning Station, Development, TM2, , connected TM2 and CS vacuum system . 

I connected TM2 and CS vacuum system. All vacuum pumps on TM2 and CS are started .The pumping down is good so .far

Entry  Thursday, December 04, 2014, 09:57, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target placed in F-308. 

Spent targets in the mini storage were placed into the F-308s yesterday, all F-308 have been removed from the the target hall and they no reside for the time being in the hallway between the north and south hot cells.

Entry  Thursday, December 04, 2014, 09:54, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical check TM2_elec_check_no_source_traySHC.PDF

Results of electrical check of TM#2 with no source tray and no containment box attached. See PDF for results.

Entry  Thursday, December 04, 2014, 09:49, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module move 

TM#2 has been moved from the south hot cell to the conditioning station.

Entry  Tuesday, December 02, 2014, 13:33, David Wang, South Hot-Cell, Development, TM2, , Leak check on TM2 tube heater +(D) at SHC 2014-12-02_003.JPG2014-12-02_001.JPG2014-12-02_004.JPG

Chad and I leak checked TM2 tube heater+(D) circuit at SHC with water bypass loop and new seals installed on the water block. The LD base LR 0.0xE-9 atm.cc/sec,base pressure0.0xE-4 torr. Chad sprayed helium on the leak check area in SHC for 5 seconds. No any response has been found on LD during 1minutes waiting time. The test was repeated again and the result is same. NO LEAK at this stage!  After the TM2 is moved to CS , The D line will be pressured with 80 psi helium for helium pressure leak test before any hot water is circuited through it.  

Entry  Tuesday, December 02, 2014, 10:15, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Reburb. Loop Install TM2_20141202_01.jpg20141203_142215.jpg20141203_143530.jpg

Final polish, clean with methanol and clean compressed air.

Loop installed and torqued to 90 in lbs.

Minimum of approximately 1"  between loop and containment box at closest point.

Entry  Monday, December 01, 2014, 14:48, Travis Cave, Spent Target Vault, Standard Operation, , , F-308s moved 

The F-308s have been moved into the target hall,  for filling on wednesday.

ELOG V2.9.2-2455