  IDdown Date Author Category Type Module Target/Number Subject Text Attachments
  872   Wednesday, March 25, 2015, 14:25 David WangSouth Hot-CellStandard OperationTM4Ta#45Leak check on TM4 HS water line with new Ta#45 target. at SHCChad and I leak checked TM4 HS water line
with new Ta#45 target installed at SHC. Leak
detector base leak rate 0.0Xe-9 atm.cc/sec,
  
  871   Wednesday, March 25, 2015, 10:37 chad fisherSouth Hot-CellDevelopment  TM2 optics tray buildTM2 optics tray build is continuing. Going
well. Hope to have assembly and alignment
finished by Friday.
 20150325_101718.jpg20150325_101735.jpg20150325_102024.jpg 
  870   Tuesday, March 24, 2015, 13:57 Travis CaveSouth Hot-CellStandard OperationTM4Ta#45Electrical checkTM#4 electrical checks with and without
the target installed, installed target is
Ta#45.
 TM4_no_tgt_elec_chk_CS.PDFTM4_Ta45_elec_chk_SHC.PDF 
  869   Tuesday, March 24, 2015, 09:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#45Ta#45 installedTa#45 has been installed onto TM4 and is
ready for leak and electrical check. High
current fasteners torqued to 130 in.lbs.
  
  868   Tuesday, March 24, 2015, 08:46 Travis CaveConditioning StationStandard OperationTM4No targetModule moveTM#4  with no target has been moved
from conditioning station to the south hot
cell.
  
  867   Monday, March 23, 2015, 14:03 chad fisherSouth Hot-CellStandard Operation Ta#45Ta#45 inserted into hot cellTa#45 has been inserted into the hot cell.
Swipe taken of inner tool port area: 100000
counts/min.
  
  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateThis schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics TrayFinal assembly and alignment of TM2 optics
tray continued today. Front section is "aligned".
 20150320_113132[2].jpg20150320_113018_1[1].jpg 
  864   Tuesday, March 17, 2015, 10:33 Travis CaveSpent Target VaultStandard Operation UC#11Spent Target MoveThe spent UC#11 has benn moved from the
south hot cell to the spent target vault.
See attached PDF for details.
 Vault_Storage_March_17_2015.pdf 
  863   Monday, March 16, 2015, 14:16 Travis CaveConditioning StationStandard OperationTM4No targetModule moveTM#4 from south hot cell to the conditioning
station no target is attached to the module.
  
  862   Monday, March 16, 2015, 09:41 Travis CaveITEStandard OperationTM4UC#11Module moveTM#4 with UC#11 moved from the east target
station to the south hot cell.
  
  861   Friday, March 13, 2015, 13:36 Travis CaveSpent Target VaultStandard Operation ThO#1Spent Target MoveThe ThO#1 has been placed in the storage
vault placed in pail #122 in spot 2B of the
vault. It was 6.2mSv/hr upon removal from
 Storage_Vault_March_13_2015.pdf 
  860   Thursday, March 12, 2015, 13:33 Anders MjosSouth Hot-CellStandard OperationTM1ThO#1Target inspectionChad, Anders and Alex inspected the target
this morning. The target had no significant
visible damage to the container. Some material
  
  859   Thursday, March 12, 2015, 13:04 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move.
  
  858   Thursday, March 12, 2015, 09:48 Travis CaveSouth Hot-CellStandard OperationTM2No target Module moveTM#2 with no target and no source tray
has been moved from the conditioning station
to the north east silo.
  
  857   Tuesday, March 10, 2015, 09:01 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1Module moveTM#1 has been moved from the west station
to the south hot cell had the ThO#1 target
removed and then the modules was moved from
 TM1_THO_elec_chk_postbeamSHC.PDF 
  856   Monday, March 09, 2015, 14:01 chad fisherSouth Hot-CellStandard OperationTM1ThO#1ThO#1 removedThO#1 has been removed from TM1 and placed
into the plastic dissection box.
Containment box cover has been reinstalled
  
  855   Monday, March 09, 2015, 09:42 chad fisherSouth Hot-CellDevelopment  Hot Cell Table Swiping3 swipes of the south hot cell table were
taken from the target hall through the roof
hatch (2 standard, 1 alpha).
  
  854   Thursday, March 05, 2015, 14:30 chad fisherSouth Hot-CellDevelopment  Dissection BoxBox for dissecting targets almost complete.
Should be done tomorrow.
 20150305_142144.jpg 
  853   Thursday, March 05, 2015, 07:17 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateTH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be
 6x 