Entry  Thursday, April 23, 2015, 12:56, Anders Mjos, Conditioning Station, Maintenance, TM1, , IG1 Good Vacuum limit changed IG1GoodVacuum.png

Changed by Dave Morris. 

New value is 1E-5 T (old value was 7.09E-5 T)

Entry  Thursday, April 23, 2015, 09:08, David Wang, Conditioning Station, Maintenance, TM1, UCx12, Huge Leak on TM1 contaiment box window. 006.JPG008.JPG011.JPG009.JPGTM1_leak_check_at_CS_2015-04-23.pdf

There is a huge leak on TM1 containment box window. I did a 70 psi helium pressure test on all TM1 water circuits this morning. The LD base leak rate was 0.0XE-9 atm.cc/sec. When applying the 70 psi helium to containment box window circuit, the leak rate on LD jumped to 1XE-4 atm.cc/sec in 5 seconds.I released the helium source right away,t but the conditioning station is full of helium  molecules already, and the leak rate on LD stays at 1xE-5 atm.cc /sec.  The leak on this circuit is huge.    Other water lines are good.        

Entry  Wednesday, April 22, 2015, 11:05, David Wang, Conditioning Station, Standard Operation, TM1, , electrical check on TM1 at CS under vacuum 

I did an electrical check on TM1 at CS. The resistance check:A-B 3.918m ohm, A-C 5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m ohm. They are very close to the check we did in SHC. The only unusual thing I found during the check is the ohmmeter reading between A and 60 KV common (6.2K )and the Megga reading between them  at 250 V which is 0. I repeated 4 times and always got the same readings. However, after so many times check, the Megga reading between A and 60KV   suddenly went back to normal(300 M at 250V) at the final check.  And,it stays at 300M now.  All other measurements are same as we did at SHC before.         

Entry  Tuesday, April 21, 2015, 17:14, Isaac Earle, South Hot-Cell, Standard Operation, TM1, UC#12, UC#12 Installed in TM1 IMG_4836.JPGIMG_4833.JPG

On Friday April 17th, UC#12 target was installed in TM1.  One of the copper water lines was bent slightly as the target was lifted into the module which caused ~15 minute delay due to difficulty getting the VCR nut threads to engage.  Other than this the install went smoothly.

During replacement of the containment box panel two of the threaded holes were found to be stripped.  One on the top at the center, the other in the bottom right corner.  These two holes were left without fasteners (see attached photo).  It is unknown at this time whether these holes were already stripped, or if they were stripped during this installation.

Entry  Tuesday, April 21, 2015, 13:01, Grant Minor, ITW, Development, TM2, , TM2 MK4 Optics Tray - banana plug bore modification (on bench) ita6092_redlines_gminor_21apr2015.pdfTM2_Optics_Tray_Bore_Mod_21Apr2015_1.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_2.JPGTM2_Optics_Tray_Bore_Mod_21Apr2015_3.JPG

The MK4 optics tray prepared for TM2 (as per ITA6082) had an undersized bore for the banana plug, making insertion of the plug extremely difficult / impossible.

Reference stores parts were collected to check the fit:  male plug 3-4/01152 and female jack 1-6/1201.  The size of the female jack was checked with a #21 drill at .159".

The bore on the optics tray was drilled out dry using the #21 drill to the same depth as the original blind hole, by Maico and Dan McDonald.  Chips were carefully collected in a rag, and the hole was blown out with compressed air.

The fit was checked to be snug but possible, using the male plug and the Remote Handling ultem base (ref ITA6023).

Redlines and photos are attached.

 

Entry  Monday, April 20, 2015, 10:22, David Wang, Conditioning Station, Standard Operation, TM1, UCx12, TM1 with UCx12 has been connected to CS and ready for conditioing. 

The TH will be locked during the TM1 conditioning time due to  an interference issue between CS HV cover and a gas analysis valve on top of TM1. A work permit has been issued for the conditioning job because of it.

Entry  Monday, April 20, 2015, 10:12, Anders Mjos, Conditioning Station, Standard Operation, TM1, UC#12, Conditioning UC#12 

Monday, April 20, 2015, 09:35: Started cooling water circulation

HV cover did not fit due to interference with the air sampling valve. Target Hall will have to be locked out for conditioning to proceed. WP I2015-04-20-2

Monday, April 20, 2015, 10:09: Started chiller staging

Target hall and HV enclosure has been locked out.

Monday, April 20, 2015, 13:45: 22 kV, 0.04 mA BIAS 

Monday, April 20, 2015, 14:58: No sparks observed. BIAS off


Tuesday, April 21, 2015, 08:26:  Starting heater auto-ramp to 500 / 230 A at 2 A/min

Tuesday, April 21, 2015, 08:32: BIAS/EE to 20 / 1.5 kV

Tuesday, April 21, 2015, 12:59: TGHT / TBHT at 327 / 230 A. Pausing the auto-ramping. Bill will be monitoring TCS while I am off-site.

Tuesday, April 21, 2015, 15:56: Continue auto-ramping

Tuesday, April 21, 2015, 17:34: Auto-ramping finished. TGHT / TBHT at 500 / 230 A


Wednesday, April 22, 2015, 08:43: Vacuum tripped heaters and BIAS over night. Switching off to do a leak check on the service cap.

Wednesday, April 22, 2015, 09:03: Stopping turbo and roughing pump for David. David is preparing a leak check.

Wednesday, April 22, 2015, 09:06: Started roughing pump.

Wednesday, April 22, 2015, 09:22: Roughing pump trips off after a few minutes of pumping.

Wednesday, April 22, 2015, 13:11: Stopped water flow.

Wednesday, April 22, 2015, 16:07: Starting turbos 

Wednesday, April 22, 2015, 16:15: All turbos at speed.


David found a leak on the window line this morning.
https://elog.triumf.ca/TIS/RH-ISAC/896

Thursday, April 23, 2015, 11:12 : Starting cooling pack

Good vacuum limit on IG1 changed from 7E-5 T to 1E-5 T

Thursday, April 23, 2015, 12:53 : Starting heater auto-ramp to 500 / 230 A at 2 A/min. Bad vacuum limit reduced to 8E-6 T

Thursday, April 23, 2015, 13:03 : BIAS/EE to 15/ 1.5 kV

Thursday, April 23, 2015, 13:28 : BIAS/EE to 20/ 1.5 kV. No sparking observed

Thursday, April 23, 2015, 17:23: Auto-ramping finished. TGHT / TBHT at 500 / 230 A

Thursday, April 23, 2015, 17:51: Fault on cooling circuit (Fault 2).. Manually starting CP1

Thursday, April 23, 2015, 18:01: Cycled power of chiller unit. System recovered. Enabled staging.

Thursday, April 23, 2015, 18:42 : One minor spark observed. Starting cool down at 12 and 9 A/min

Thursday, April 23, 2015, 19:51 : Heaters and BIAS off


Friday, April 24, 2015, 08:21 : Water cooling off

Entry  Monday, April 20, 2015, 07:27, David Wang, ITE, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp

Weekly target hall schedule update.2015-04-20

weekly target hall schedule update 2015-04-27 attachments 3,4.

Entry  Friday, April 17, 2015, 14:04, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#12, Module move 

TM#1 with UCx#12 has been moved from the south hot cell to the conditioning station.

Entry  Friday, April 17, 2015, 11:56, Travis Cave, South Hot-Cell, Standard Operation, TM1, UC#12, Electrical check TM1_UC#12_tgt_elec_chk_SHC.PDF

Electrical check of TM#1 with UCx#12 attached. See attached PDF for details.

Entry  Friday, April 17, 2015, 09:09, Travis Cave, South Hot-Cell, Standard Operation, TM1, No target, Module move 

TM#1 with no target has been moved from the south west silo to the south hot cell for the installation of the UCx target.

Entry  Wednesday, April 15, 2015, 09:01, Anders Mjos, Conditioning Station, Development, , , Archiver variables added by Controls 

 

 

 

 

 

 

 

 

 

 

The following variable have been added to the archiver (as per work request)

TCS:TS5:RDTEMP 
TCS:TCM1:EE:RDTEMP 
TCS:TCM1:COIL1:RDTEMP 
TCS:TCM1:TBHT:RDTEMP 
TCS:TCM1:TGHT:RDTEMP 
TCS:TCM1:MSP:RDTEMP 
TCS:TCM1:HVC1:RDTEMP 
TCS:TCM1:HS:RDTEMP 
TCS:FC:SCALECUR 
TCS:COL:SCALECUR 
TCS:TK2:RDLEVEL 
TCS:TK2:RDLEVEL 
TCS:DIF1:RDFLOW 
TCS:CHILL:RDHRS

The archiver was restarted.

 

 

Entry  Monday, April 13, 2015, 08:59, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp

See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.

Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015.    See attachments 3,4.

Entry  Friday, April 10, 2015, 15:40, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITW to ITE. 

5 shielding  blocks have been transferred to ITE. The ITE is configured to take proton beam.

Entry  Wednesday, April 01, 2015, 13:12, David Wang, ITE, Standard Operation, TM4, Ta#45, TM4 has been connected in ITE 

TM4 has been connected in ITE. ITE six turbo-pumps have been started. So far so good.

Entry  Wednesday, April 01, 2015, 13:08, David Wang, ITE, Standard Operation, TM4, , Replaced ITE tank to module 42X0.275 o-ring 001.JPG002.JPG004.JPG005.JPG006.JPG

I replaced ITE tank to module 42 ID X 0.275 o-ring. The o-ring is changed once a year before the first beam time. The flanges was cleaned and the new o-ring was installed. It works fine.

Entry  Wednesday, April 01, 2015, 10:52, Travis Cave, ITE, Standard Operation, TM4, Ta#45, Module move 

TM#4 with Ta#45 has been moved from the conditioning station to the east target station.

Entry  Wednesday, April 01, 2015, 06:56, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 has been disconnected at CS. 

TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday.

Entry  Tuesday, March 31, 2015, 11:36, chad fisher, South Hot-Cell, Development, TM2, , TM2 Optics Tray Complete 20150331_OPTICS_FRONT.jpg20150331_OPTICS_MIDDLE.jpg20150331_OPTICS_BACK.jpg

TM2 optics tray is complete.

Master alignment tray: 0 up/down, 0 left/right

Optics tray: Front 0 up/down, 0 left/right. Middle 0 up/down, 0 left/right. Back 0 up/down, 0 left right.

 

Entry  Monday, March 30, 2015, 09:03, Anders Mjos, Conditioning Station, Standard Operation, TM4, Ta#45, Ta#45 Conditionoing Ta#45_Conditioning.docx

Monday, March 30, 2015, 08:59: Reset chiller by switching on off power (fault 2)

Monday, March 30, 2015, 09:02: Switched on CHILL:CP2, TS5 at 34 C

Monday, March 30, 2015, 10:24 : Cage locked. EE to GND. BIAS and EL ON.

Troubleshooting BIAS current limiting. Turned out to be a EPICS initialization issue. Resolved by setting/changing the current limit again in EPICS.

Monday, March 30, 2015, 14:00: BIAS/EL 18 / 9 kV

Monday, March 30, 2015, 14:16: BIAS/EL 24 / 12 kV

Monday, March 30, 2015, 16:03: BIAS/EL 30 / 15 kV. Occasional sparking while stepping up since 26 kV

Monday, March 30, 2015, 16:13: BIAS/EL 30.8 / 15 kV. 110% of scheduled 28 kV. BIAS/EL 0.04 / 0.09 mA

Monday, March 30, 2015, 17:26 : Maintained BIAS over 1 hour. One spark after.

Monday, March 30, 2015, 17:27 : BIAS / EL off.


Tuesday, March 31, 2015, 08:12: Cage access. EE to EE PS. Cage locked.

Tuesday, March 31, 2015, 08:24: BIAS/EL/EE at 30.8 / 15 / 1 kV

Tuesday, March 31, 2015, 08:26 : EE to 2 kV, 1.96 mA

Tuesday, March 31, 2015, 08:46: No sparks for 20 min.

Tuesday, March 31, 2015, 08:48 : BIAS/EL/EE at 20 / 9.3 / 1.5 kV

Tuesday, March 31, 2015, 08:57: Started auto ramping of heaters to 580 / 230 A at 2 A/min.

Tuesday, March 31, 2015, 10:54: TBHT at 230 A

Tuesday, March 31, 2015, 14:05: TGHT at 580 A

Tuesday, March 31, 2015, 14:21: BIAS/EL/EE to 30.8 / 15 / 2 kV

Tuesday, March 31, 2015, 17:48: Source stable for 4h

Tuesday, March 31, 2015, 18:20: Lowered IAS/EL/EE to 20 / 9.3 / 1.5 kV. IG2 at 6.2E-6 T

Tuesday, March 31, 2015, 21:27: Starting ramp down at 15/12 A/min. IG2 at 6.8E-6 T

Tuesday, March 31, 2015, 21:51: BIAS/EL/EE to zero and off. IG2 at 6.6E-6 T

Tuesday, March 31, 2015, 22:17: TGHT and TBHT off

Tuesday, March 31, 2015, 22:41: Turbos off.

Tuesday, March 31, 2015, 22:42: Water off.