  933   Thursday, June 04, 2015, 07:44 Dan McDonaldAssembly/Bench TestDevelopmentTM2 Movement of TM2 source tray to alignment area in ISACOnce the test stand was vented and all
lines purged Anders Mjos and myself jigged
up the water blocks and proceeded to remove
  
  932   Wednesday, June 03, 2015, 13:51 David WangConditioning StationStandard OperationTM4SiC #31TM4 is connected at CSTM4 has been connected at CS. CS HV cover
is installed.I made a pair of new cooling
lines for TM window cooling at CS. The TM4
 007.JPG009.JPG008.JPG010.JPG 
  931   Wednesday, June 03, 2015, 13:01 Anders MjosConditioning StationStandard OperationTM4SiC#31Conditioning SiC#31PNG1 connected to PNG in service cap
(as per David W)
 Wednesday, June 03, 2015, 12:59:
 SiC#31_Conditioning.docx 
  930   Wednesday, June 03, 2015, 11:22 David WangConditioning StationStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015I revised the Target Hall schedule to July
21 2015. It is the time new TM2 with ZrC
target started at ITW.
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp 
  929   Tuesday, June 02, 2015, 14:39 David WangConditioning StationStandard OperationTM4SiC #31TM4 and CS turbo- pumps are started .TM4 and CS turbo-pumps are started this
afternoon. Everything is good so far.
  
  928   Tuesday, June 02, 2015, 14:38 David WangConditioning StationRepairTM4 replace broken TM4 IG1 TM4 IG1 filament was broken during
last run  at ITE.  The broken filament
is replaced with a new one today when TM4
 002.JPG006.JPG 
  927   Tuesday, June 02, 2015, 14:32 David WangSouth Hot-CellStandard OperationTM4SiC #31Leak check on TM4 HS water line with new SiC #31 target. at SHCChad and I leak checked TM4 HS water line
with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec. 
No leak.  The line will be helium pressurized
 003.JPG005.JPG001.JPG 
  926   Tuesday, June 02, 2015, 11:54 Travis CaveConditioning StationStandard OperationTM4SiC#31Module movedTM#4 with SiC#31 has been moved from the
south hot cell to the conditioning station.
  
  925   Tuesday, June 02, 2015, 10:39 Travis CaveSouth Hot-CellStandard OperationTM4SiC#31Electrical CheckElectrical check on TM#4 with SiC#31. See
attached PDF for details.
 TM4_SiC31_elecchk_SHC.PDF 
  924   Tuesday, June 02, 2015, 09:43 chad fisherSouth Hot-CellStandard OperationTM4SiC#31SiC#31 installedTa #45 has been removed from TM4 and SIC#31installed.   
  923   Tuesday, June 02, 2015, 06:51 David WangSouth Hot-CellStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015Target Hall schedule weekly update. All
jobs are finished on time so far.
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf 
  922   Monday, June 01, 2015, 14:24 Travis CaveSouth Hot-CellStandard OperationTM4Ta#45Electrical CheckPost beam electrical check on the Ta#45
target installed on TM#4. See attached PDF.
 TM4_Ta45_elecchk_postbeam.PDF 
  921   Monday, June 01, 2015, 11:23 Travis CaveITEStandard OperationTM4Ta#45Module movedTM#4 with Ta#45 has been moved from the
east target station to the south hot cell.
  
  920   Friday, May 29, 2015, 09:16 Travis CaveConditioning StationStandard OperationTM2no targetModule movedTM#2 with no source tray has been moved
from the conditioning station to the north
east silo.
  
  919   Wednesday, May 27, 2015, 08:57 Travis CaveConditioning StationStandard OperationTM2 Module movedTM#2 with no source tray has been moved
from the south hot cell to the conditioning
station.
  
  918   Tuesday, May 26, 2015, 14:34 chad fisherSouth Hot-CellRepairTM2 Shutter replacementThe shutter in TM2 was successfully replaced
today.
New lock washer and nut were installed
 Shutter.jpg 
  917   Tuesday, May 26, 2015, 11:49 Grant MinorAssembly/Bench TestRepairTM2 TM2 New Source Tray - Braze & Solder Report - 22 May 2015Hello,

For reference, I have attached a list
 6x 
  916   Friday, May 22, 2015, 15:44 David WangITWStandard OperationTM1UCx125 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW. I  checked all ITW
water signals, and they are good.  ITW
  
  915   Wednesday, May 13, 2015, 13:55 chad fisherSouth Hot-CellRepairTM2 Shutter removalTM2 has been successfully de-shuttered.
All went pretty much according to
plan except I had to remove one fastener
 TM2_20150513_131339.jpgTM2_20150513_134232.jpg 
  914   Monday, May 11, 2015, 11:20 David WangSouth Hot-CellStandard OperationTM2 Target Hall Scheduled Activities April 07 - June 26 2015The schedule has some changes due to 
new TM2 source tray coil cooling line leaking
at test stand. Now,It is re-scheduled in
 6x 