208
|
Wednesday, November 07, 2012, 11:09 |
David Wang | South Hot-Cell | Standard Operation | TM1 | TiC | TM1 heat shield circuit leak check with TiC target at hot cell | Chad and i did a leak check on TM1(Lp-TiC)
heat shield water circuit at south hot cell.
There is no leak had been found on it. The |
|
209
|
Thursday, November 08, 2012, 08:42 |
David Wang | Conditioning Station | Standard Operation | TM1 | TiC #3 | TM1 TiC #3 target heat shield helium pressure check is done. | TM1 TiC #3 target heat shield
helium pressure check is done at conditioning
station. Applied 80 psi helium to HS circuit |
|
210
|
Thursday, November 08, 2012, 09:37 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Nb#7 | Nb#7 Autopsy | Nb#7 was dismantled and ready for inspection. |
|
211
|
Friday, November 09, 2012, 09:20 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | TiC#3 | Electrical check | Electrical check performed on TM#1 with
TiC#3 at the conditioning station under vacuum.
See PDF for details. |
|
213
|
Tuesday, November 13, 2012, 10:55 |
Travis Cave | ITW | Standard Operation | TM1 | TiC#3 | module move | TM#1 with TiC #3 moved from the conditioning
station to the west target station,
move went well. |
|
214
|
Wednesday, November 14, 2012, 10:57 |
David Wang | ITW | Standard Operation | TM1 | | TM1connected in ITW | I connected TM1 in ITW yesterday. Everything
is good so far. Travis was with me when i
did the job. |
|
225
|
Wednesday, January 02, 2013, 12:11 |
David Wang | ITW | Standard Operation | TM1 | | I moved 5 shielding blocks from ITW to block storage area | I moved 5 shielding blocks from ITW
to block storage area for preparing the TM1
disconnection. Air sampled and swiped blocks |
|
226
|
Thursday, January 03, 2013, 10:05 |
David Wang | ITW | Standard Operation | TM1 | | Disconnected TM1 in ITW. | TM1 has been disconnected in ITW. All
water lines had been purged. Travis was with
me during the job. |
|
227
|
Tuesday, January 08, 2013, 08:48 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | TiC#3 | Electrical check | TM#1 with TiC #3 post beam. See attached
PDF for results. |
|
228
|
Tuesday, January 08, 2013, 14:18 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | Electrical check | TM#1 was electrically check with out a
target see attached PDF for results. |
|
230
|
Monday, January 14, 2013, 14:09 |
Travis Cave | ITW | Standard Operation | TM1 | no target | module move | TM#1 has been moved from the south hot
hell to the west target station, move went
well. |
|
231
|
Tuesday, January 15, 2013, 10:49 |
David Wang | ITW | Standard Operation | TM1 | no target | TM1 vacuum system connection in ITW | I connected TM 1 vacuum system in ITW.
The TM1 and ITW will be pumped out for shut
down routine leak check. |
|
240
|
Thursday, January 24, 2013, 13:30 |
David Wang | ITW | Standard Operation | TM1 | | ITW-TM1 2013 winter shut down leak check. | 2013 winter shut down ITW-TM1 primary vacuum
vessel, secondary vacuum vessel, and water
lines leak check: connected leak detector |
|
245
|
Thursday, February 21, 2013, 14:05 |
David Wang | ITW | Repair | TM1 | | Disconnected EXIT1 in ITW. | Disconnected EXIT1 in ITW. All cables ,
wires and air lines are label marked. |
|
248
|
Tuesday, February 26, 2013, 10:26 |
Travis Cave | ITW | Standard Operation | TM1 | | module move | TM1 moved from the west station to the
southwest silo. Move went well. |
|
282
|
Tuesday, April 02, 2013, 10:07 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 inserted into hot cell | Ta#39 has been inserted into the hot cell
in preparation for TM1 target change. |
|
283
|
Wednesday, April 03, 2013, 10:59 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module move | TM#1 has been moved from the south west
silo to the south hot cell, move went well. |
|
285
|
Wednesday, April 03, 2013, 13:28 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 installed | Ta#39 has been installed onto TM1. |
|
286
|
Wednesday, April 03, 2013, 14:39 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Electrical check | Electrical check on TM#1 with Ta#39 installed
at the south hot cell. Target passed the
electrical checks, see attached pdf for details. |
|
287
|
Thursday, April 04, 2013, 11:06 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | Ta#39 | module move | TM#1 with Ta#39 has been moved from the
south hot cell to the conditioning station
move went well. |
|