Entry  Monday, August 19, 2013, 10:08, Anders Mjos, ITE, Repair, TM4, SiC#29, Leak Check ITE_Leak_Test_2013-08-19.pdf
All water circuits except Coil 1 were leak checked by David and Anders. No obvious signals were detected except some small possible responses. See attached
notes for details.
Entry  Thursday, September 12, 2013, 09:29, Travis Cave, ITW, Standard Operation, TM4, SiC#29, module move 
TM#4 with SiC#29 has been moved to the south hot cell move went well.
Entry  Thursday, September 12, 2013, 10:35, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#29, Electrical check TM#4SiC#29FEBIADelechkpostbeam.PDF
TM#4 with SiC#29 post beam electrical check in the south hot cell see PDF for details.
Entry  Friday, September 13, 2013, 08:05, David Wang, South Hot-Cell, Repair, TM4, , TM4 coil 1 leak check in SHC TM4_coil_1_leak_check.pdf
Leak checked TM4 coil1 in SHC with Isaac . The leak detector only can pump down to 1.5xE-7 atm.cc/sec. The leak detector got the response once the helium
valve is open, not even close to the leak area. The leak detector got a very big response when the helium probe was put close to the coil terminal block
on target front side and spray helium for 2 clicks. The leak detector got a small  response when the probe was put close to water block area and spray
Entry  Monday, September 30, 2013, 15:59, Bevan Moss, South Hot-Cell, Standard Operation, TM4, SiC#29, Module move from SW Silo to SHC 
 TM4 was move by myself and Grant. Move went smoothly, no hang ups.
Entry  Tuesday, October 01, 2013, 10:59, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#29, Electrical check TM#4_elec_chk_SiC#29_SHC_post2.PDF
TM#4 with SiC#29 electrical check post beam see pdf for details.
Entry  Wednesday, October 02, 2013, 13:44, Bevan Moss, South Hot-Cell, Standard Operation, TM4, , Right Coil is leaking tm4leak.jpg
 Today Maico and Travis completed and electrical test to determine the right and left coil on TM4. The left coil is the negative side. From there
Maico pumped on both lines for a leak test. The leak cart pumped down to its lower limits on the left line and there was no response when sprayed with
helium. The right line would not pump below 2.5 x 10^-2 Torr and had a base leak rate of 3.3 x 10^-7 atm*cc/sec (this indicates a massive leak). Without
Entry  Wednesday, October 02, 2013, 14:47, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, Electrical check TM#4_elec_chk_No_Tgt_SHC.PDF
Electrical check done on TM#4 with no target, see PDF.
Entry  Thursday, October 03, 2013, 10:18, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
TM#4 with no target has been moved from the south hot cell to the south west silo.
Entry  Tuesday, October 08, 2013, 14:55, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
TM#4 with no target was to be moved today but the move was aborted when the crane failed to move in the East - West direction. The crane does not preform
this function in either remote or pendant operation.
Entry  Tuesday, October 08, 2013, 18:12, Grant Minor, Crane, Repair, TM4, , Target Hall Crane Stuck in East-West Direction - Update THall_Crane_Bridge_Wheel_at_South_Rail_Splice_8Oct2013.JPGNORELCO_inv13045_joMS-064_31March2013.pdf
Grant Minor wrote this e-mail today:
***
Hello all,
    Reply  Wednesday, October 09, 2013, 19:33, Grant Minor, Crane, Repair, TM4, , Target Hall Crane not operational - likely controls / PLC hardware failure (not stuck wheel) 


    
        
            
            Grant Minor wrote:
            
        
        
            
            Grant Minor
Entry  Wednesday, October 16, 2013, 10:12, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
TM#4 with no target has been moved from the south west silo to the south hot cell.
Entry  Thursday, October 17, 2013, 10:24, chad fisher, South Hot-Cell, Repair, TM4, , Coil Line Removal TM4_C2_circuit.pdf
The containment box was removed from TM4 earlier this morning in preparation for removal of the C2 circuit water lines, their respective water
blocks and conductor block.
Entry  Friday, October 18, 2013, 13:43, chad fisher, South Hot-Cell, Repair, TM4, , C2 Circuit Removal IMG_1224[1].JPGIMG_1227[1].JPGIMG_1230[1].JPG
The C2 circuit (coil 2) water lines and blocks have been revoed from TM4.
Water block jig could not be used as the window water block connection was nowhere near fitting into the jig (IMG_1224 image below) and
therefore caused an interference causing the rest of the blocks to not mate with the jig. A different tool that has never been used was implimented and
Entry  Friday, October 18, 2013, 14:33, Bevan Moss, South Hot-Cell, Standard Operation, TM4, , Module move 
 TM4 without a source tray was moved from the SHC to the TCS.  All went well.
Entry  Friday, October 18, 2013, 14:37, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Roughing Started 
 The roughing pump has been started.
Entry  Friday, October 18, 2013, 14:56, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, Electrical check TM#4_no_target_post_coilelectest.PDF
With the coil line removed an electrical check was done on TM#4 at the South Hot Cell see attached pdf.
Entry  Friday, October 18, 2013, 15:55, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Turbo Pumps are on 
 The Turbo pumps are now running on TCS
Entry  Monday, October 21, 2013, 10:52, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Cooling On and Electrical Connections Made 
 The electrical connection have been made and cooling package was started at ~10:50am today