  163   Monday, August 20, 2012, 12:28 David WangITWStandard OperationTM1 I moved 5 shielding blocks from ITE to ITW,I moved 5 shielding blocks from ITE 
to ITW.ITW is configured to take proton beam
now.
  
  176   Wednesday, September 12, 2012, 11:59 David WangITWStandard OperationTM1UCxTM1 disconnected in ITWI removed 5 shielding blocks from ITW to
block storage area, and disconnected TM1
in ITW. After UCx run,  the radioactive
  
  177   Thursday, September 13, 2012, 11:03 Travis CaveSouth Hot-CellStandard OperationTM1UCx#4module moveTM#1 with UCx#4 has been moved from the
west target station to the south hot cell.
Move went well.
  
  178   Thursday, September 13, 2012, 13:27 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule moveTM#1 has been moved from the south hot
cell to the south west silo. Move went well.
  
  180   Tuesday, September 18, 2012, 09:13 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule moveTM#1 moved from the south west silo to
the south hot cell, move went well.
  
  181   Tuesday, September 18, 2012, 13:41 David WangSouth Hot-CellStandard OperationTM1Nb#7leak check heat shield circuitChad  and i did a leak check on TM1 heat
shield circuit with new Nb#7 target  installed.
It took about 5 mins pump down  the circuit
  
  182   Tuesday, September 18, 2012, 13:47 chad fisherSouth Hot-CellStandard OperationTM1Nb#7Nb #7 install Cover BaselineNb #7 was installed and tested today.
Inside face of the containment box
cover was cleaned with methanol and a baseline
 IMG_3191.JPGIMG_3192.JPG 
  183   Wednesday, September 19, 2012, 11:23 Travis CaveSouth Hot-CellStandard OperationTM1Nb#7Electrical checkTM#1 with Nb#7 attached was electrically
checked at the south hot cell yesterday,
see attached pdf for details. Some notes
 TM1_Nb7_Elec_chk_SHC.PDF 
  184   Wednesday, September 19, 2012, 11:24 Travis CaveConditioning StationStandard OperationTM1Nb#7module moveTM#1 with Nb#7 was moved from the south
hot cell to the conditioning station. Move
went well.
  
  185   Thursday, September 20, 2012, 08:45 Travis CaveConditioning StationStandard OperationTM1Nb#7Electrical checkElectrical check was done at the conditioning
station this morning results are on the attached
PDF.
 TM1_Nb7_Elec_chk_CS.PDF 
  186   Thursday, September 20, 2012, 09:16 David WangConditioning StationStandard OperationTM1Nb#7TM1 Nb#7 target heat shield helium pressure check is done.Leak detector pumped down to base LR1.3xE-9
atm.cc/sec, and BP 8xE-3 torr. All  high
vacuum gauge readings at CS and TM1 are at
  
  187   Tuesday, September 25, 2012, 10:34 Travis CaveITWStandard OperationTM1Nb#7module moveTM#1 with Nb#7 moved from the conditioning
station to the west target station. Move
went well.
  
  188   Tuesday, September 25, 2012, 14:33 David WangITWStandard OperationTM1Nb#7TM1connected in ITWTM 1 is in ITW now. All connections are
done. The turbo pumps had been started  this
afternoon. The vacuum looks good so far.
  
  190   Tuesday, October 02, 2012, 11:47 David WangITWStandard OperationTM1Nb#7I moved 5 shielding blocks from ITE to ITW.5 shielding blocks have been moved from
ITE to ITW. ITW is configured to take proton
beam now.
  
  202   Tuesday, November 06, 2012, 11:06 Travis CaveITWStandard OperationTM1Nb#7module moveTM#1 with Nb#7 has been moved from the
west target station to the south hot cell
move went well.
  
  203   Tuesday, November 06, 2012, 11:34 chad fisherSouth Hot-CellStandard OperationTM1 Nb#7 RemovalAttached are pre-removal pictures of NB#7
and the inside face of the containment box
cover before cleaning.
 IMG_0797[1].JPGIMG_0798[1].JPGIMG_0799[1].JPG 
  204   Tuesday, November 06, 2012, 12:08 David WangITWStandard OperationTM1Nb#7TM1 disconnected in ITWBevan and I disconnected TM1 in ITW this
morning. The TM1 was moved to south hot cell
later.   
  
  205   Tuesday, November 06, 2012, 14:00 chad fisherSouth Hot-CellStandard OperationTM1TiC#3TiC#3 InstalledTiC#3 sucessfully installed and ready for
leak and electrical check.
  
  206   Wednesday, November 07, 2012, 09:25 Travis CaveSouth Hot-CellStandard OperationTM1TiC#3Electrical checkTM#1 with TiC#3 target has had the electrical
performed on it. See attached PDF for details.
 TM_1_TiC_3_Elec_check_SHC.PDF 
  207   Wednesday, November 07, 2012, 10:25 Travis CaveConditioning StationStandard OperationTM1TiC#3module moveTM#1 with TiC#3 has been moved from the
south hot cell to the conditioning station,
move went well.
  