  1218   Friday, April 29, 2016, 08:01 David WangConditioning StationMaintenanceTM2 TM2 leak check at TCS, helium pressure testAnders and I finished the most part of
TM2 water lines helium pressure test yesterday.I
list the system parameters and test result
  
  1219   Friday, April 29, 2016, 10:06 David WangConditioning StationStandard OperationTM2 I switched off TCS and TM2 vacuum pumps.  I switched off TCS and TM2 vacuum
pumps. The TM2 will be disconnected at TCS
today and moved to silo on next Monday.
  
  1222   Wednesday, May 04, 2016, 12:01 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Update schedule weekly. See attachment
1,2,3.
 Target_Hall_shedule_130_Apr_to_Sep_2016.pdfTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1223   Monday, May 09, 2016, 08:43 David WangConditioning StationRepairTM3 I reinstalled all the side panel on TM3 service cap.They were moved for TM3 inspection job
last week. All the bolts on the panel are
hand tight only now since they will be removed
  
  1226   Tuesday, May 10, 2016, 13:54 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on window line and HS line.Chad and I leak checked the TM2 HS and
window lines after new target installation. 
The window line was very easy pumped down
  
  1229   Wednesday, May 11, 2016, 13:15 David WangConditioning StationMaintenanceTM2 TCS tank top flange seal is changed this morningI changed TCS tank top flange seal(o-ring
42.00"ID X 0.275" DIA) this morning
before TM2 was moved to TCS.
  
  1230   Wednesday, May 11, 2016, 13:16 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.TM2 and TCS vacuum system has been connected.
I started all turbo pumps. Everything is
good so far.
  
  1231   Friday, May 13, 2016, 10:08 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 HS and window line at CS with new Lp Ta targetThese two lines are passed helium pressure
test this morning. The LD base leak rate
0.0 X E-9 atm.cc/sec. The base pressure 0.0
  
  1232   Friday, May 13, 2016, 10:12 David WangConditioning StationStandard OperationTM2 TM2 water lines, heaters, EE, and EL are connected at TCS.The HV  cover is installed on to TM2
after the connections. The HV key is returned
back to B2 level. The TCS Faraday cage is
  
  1234   Monday, May 16, 2016, 11:16 David WangITWStandard OperationTM1 ITW, TM1 turbo-pumps are swithched offI let isac opp switched off ITW turbo-pumps.
The argon vent valve in electrical room is
opened. The ITW argon venting will be started 
  
  1240   Friday, May 20, 2016, 08:13 David WangConditioning StationStandard OperationTM2Ta#48I switched off TCS and TM2 water systemDisconnected  TM2 at TCS(vacuum system
still on). Purged all TM2 water lines for
helium pressure test.
  
  1241   Friday, May 20, 2016, 10:38 David WangConditioning StationStandard OperationTM2Ta#48Helium pressure test on TM2 with new Lp Ta targetLD base LR: 0.0 X E-9. Base pressure:0.0
X E-4. 70 psi helium. 5 minutes each circuit.
  
  1242   Tuesday, May 24, 2016, 10:39 David WangConditioning StationStandard OperationTM2Ta#48TM2 and TCS turbo-pumps have been switched off this morning.The TCS and TM2 are still under vacuum
without venting
  
  1243   Tuesday, May 24, 2016, 10:42 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update the TH schedules. See attachments
1, 2,3.
 Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1246   Wednesday, May 25, 2016, 14:08 David WangITWStandard OperationTM2Ta#48TM2 has been connected in ITWTM2 has been connected in ITW by Dan.M
and David.W. All turbo-pumps have been started.
Everything is good so fine.
  
  1249   Thursday, June 02, 2016, 11:59 David WangSouth Hot-CellRepairTM3 5K mega test on TM3I did a 5KV mega test on TM3.  Only5Mohm
@5kV between coli line PQ and chassis(ground).
It confirmed the close gap between P,Q and
 5K_mega_check_on_TM3.pdf 
  1253   Tuesday, June 07, 2016, 11:36 David WangITEStandard OperationTM4Ta#47TM4 has been disconnected in ITE.Dan and I disconnected TM4 in ITE. HS water
lines has been purged.
  
  1254   Tuesday, June 07, 2016, 11:37 David WangITEStandard OperationTM4Ta#47TM4 has been moved from ITE to SHCBill and Yasmine did the move. Everything
is good.
  
  1255   Tuesday, June 07, 2016, 11:42 David WangSouth Hot-CellStandard OperationTM4Ta#47electrical check on TM4 with old Ta target at SHC.I did an electrical check on TM4 with the
old target still installed. The number is
a little bit low on 500V mega check between
 electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdfelectrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf 
  1256   Tuesday, June 07, 2016, 17:11 David WangConditioning StationStandard OperationTM4UC#16TM4 UCx16 electrical check and leak check at SHCChad and I finished the TM4 UCx6 electrical
check and leak check at SHC. Leak check result
on HS line is good. There is a dead short
 UCX_16_electrical_test.pdfelectrical_check._TM4_UCx16_at_TCS..pdf 