  1231   Friday, May 13, 2016, 10:08 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 HS and window line at CS with new Lp Ta targetThese two lines are passed helium pressure
test this morning. The LD base leak rate
0.0 X E-9 atm.cc/sec. The base pressure 0.0
  
  1232   Friday, May 13, 2016, 10:12 David WangConditioning StationStandard OperationTM2 TM2 water lines, heaters, EE, and EL are connected at TCS.The HV  cover is installed on to TM2
after the connections. The HV key is returned
back to B2 level. The TCS Faraday cage is
  
  1234   Monday, May 16, 2016, 11:16 David WangITWStandard OperationTM1 ITW, TM1 turbo-pumps are swithched offI let isac opp switched off ITW turbo-pumps.
The argon vent valve in electrical room is
opened. The ITW argon venting will be started 
  
  1240   Friday, May 20, 2016, 08:13 David WangConditioning StationStandard OperationTM2Ta#48I switched off TCS and TM2 water systemDisconnected  TM2 at TCS(vacuum system
still on). Purged all TM2 water lines for
helium pressure test.
  
  1241   Friday, May 20, 2016, 10:38 David WangConditioning StationStandard OperationTM2Ta#48Helium pressure test on TM2 with new Lp Ta targetLD base LR: 0.0 X E-9. Base pressure:0.0
X E-4. 70 psi helium. 5 minutes each circuit.
  
  1242   Tuesday, May 24, 2016, 10:39 David WangConditioning StationStandard OperationTM2Ta#48TM2 and TCS turbo-pumps have been switched off this morning.The TCS and TM2 are still under vacuum
without venting
  
  1243   Tuesday, May 24, 2016, 10:42 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update the TH schedules. See attachments
1, 2,3.
 Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1246   Wednesday, May 25, 2016, 14:08 David WangITWStandard OperationTM2Ta#48TM2 has been connected in ITWTM2 has been connected in ITW by Dan.M
and David.W. All turbo-pumps have been started.
Everything is good so fine.
  
  1249   Thursday, June 02, 2016, 11:59 David WangSouth Hot-CellRepairTM3 5K mega test on TM3I did a 5KV mega test on TM3.  Only5Mohm
@5kV between coli line PQ and chassis(ground).
It confirmed the close gap between P,Q and
 5K_mega_check_on_TM3.pdf 
  1253   Tuesday, June 07, 2016, 11:36 David WangITEStandard OperationTM4Ta#47TM4 has been disconnected in ITE.Dan and I disconnected TM4 in ITE. HS water
lines has been purged.
  
  1254   Tuesday, June 07, 2016, 11:37 David WangITEStandard OperationTM4Ta#47TM4 has been moved from ITE to SHCBill and Yasmine did the move. Everything
is good.
  
  1255   Tuesday, June 07, 2016, 11:42 David WangSouth Hot-CellStandard OperationTM4Ta#47electrical check on TM4 with old Ta target at SHC.I did an electrical check on TM4 with the
old target still installed. The number is
a little bit low on 500V mega check between
 electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdfelectrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf 
  1256   Tuesday, June 07, 2016, 17:11 David WangConditioning StationStandard OperationTM4UC#16TM4 UCx16 electrical check and leak check at SHCChad and I finished the TM4 UCx6 electrical
check and leak check at SHC. Leak check result
on HS line is good. There is a dead short
 UCX_16_electrical_test.pdfelectrical_check._TM4_UCx16_at_TCS..pdf 
  1257   Tuesday, June 07, 2016, 17:14 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 target has been moved from SHC to TCS.Bill and Yasmine did the move remotely
this afternoon. The move is successful.
  
  1258   Tuesday, June 07, 2016, 18:17 David WangConditioning StationStandard OperationTM4UC#16TM4 and TCS turbo pumps are started.TM4 and TCS vacuum system are connected.
  Turbo pumps are started.  Everything
is fine so far.
  
  1260   Thursday, June 09, 2016, 08:37 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 helium pressure test at TCSI did a helium pressure test on TM4 at
TCS with UCX16 target installed on the module.
No leak has been found on all using water
 TM4_withUCx16_helium_pressure_test_at_TCS.pdf 
  1261   Thursday, June 09, 2016, 09:44 David WangConditioning StationStandard OperationTM4UC#16TM4 has been connected at TCSIt is ready for HV conditioning/ heating.    
  1262   Thursday, June 09, 2016, 10:04 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update .  Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1263   Tuesday, June 14, 2016, 08:04 David WangConditioning StationStandard OperationTM4UC#16TM4 has been disconnected at TCSThe TM4 and TCS are vented with argon.    
  1265   Tuesday, June 14, 2016, 11:20 David WangITEStandard OperationTM4 TM4 has been connected in ITETM4 and ITE are under roughing now.   