Entry  Thursday, January 16, 2014, 10:36, chad fisher, South Hot-Cell, Repair, , , East Manipulator Repair Manip_repair_20140114.jpgManip_repair_20140115.jpg

The repair/cable replacement on the east manipulator is now complete.

Yesterday's initail cable replacement went very well however, due to a minor glich, we were unable to test the tong movement until I was out of the hot cell. Tong did not fully close and felt like there was a "hard stop" at a repeatable spot in the  closing of the tong. Upon further investagation, I determined that the problem was definelty on the slave side.

I conducted a troublshooting exercise this morning to narrow down the problem. I quickly found that the new tong came from the manufacture with two incorrect fasteners (socket head cap screws) instead of set screws. As a result the tong was being kept from closing as the head of the socket head cap screws was interfering.

I replaced the SHCS was the set screws from the old tong. The tong now functions with full range of motion.

Jan. 15, 37 minutes in cell .26 mSv

Jan. 16, 16 minutes in cell (as I did some clean up of compressable waste) .05 mSv

Also, the inital repair utilized a prototype tool I designed (and with assistance from Maico, built). This tool made the repair much easier. I will be making small improvements to the design and issuing drawings to the vault and shop.

 

 

Entry  Monday, January 20, 2014, 13:35, David Wang, ITE, Standard Operation, TM4, , 5 shielding blocks had been moved out of ITE 

5 SHIELDING BLOCKS HAD BEEN MOVED OUT OF ITE.AIR SAMPLE AND SWIPED FIRST BLOCK AND ITE PIT.NOTHING HAD BEEN FOUND ON ALPHA MONITOR AND OTHER TWO MONITORS.

Entry  Monday, January 20, 2014, 13:38, David Wang, ITE, Standard Operation, TM4, , DISCONNECTED TM4 IN ITE. 

I DISCONNECTED TM4 IN ITE. ALL WATER LINES HAD BEEN PURGED OUT WITH PRESSURE AIR.

Entry  Wednesday, January 22, 2014, 10:51, David Wang, ITE, Repair, , , Removed 4 shielding blocks located on top of preseperator in TH 

Travis and I removed 4 shielding blocks located on top of pre-seperator  in TH. This is a job for ITE harp 9 re-installation after it  is repaired . The blocks move are successful.

Entry  Monday, February 03, 2014, 14:45, Travis Cave, Spent Target Vault, Standard Operation, , , Spent targets to mini storage and the F-308s to the Target Hall Vault_Storage_February_3_2014.pdfMini_Vault_Storage_February_3_2014.pdf

Targets NiO#1(101), Nb#5(85), TaC#1(92), and ZrC#5(81) have been moved from the storage vault and placed in the mini storage. The F-308 flasks have also been moved in to the target hall as well. The attached are the current statuses of both vaults.

Entry  Tuesday, February 04, 2014, 08:04, David Wang, South Hot-Cell, Repair, TM2, , Leak check TM2 tube heater (+) water line. IMG_0012.JPGIMG_0013.JPG

Chad and I leak checked TM2 tube heater(+) water line yesterday afternoon. The water line was difficult to pump down on base leak rate, but LD  base pressure was fine . The base pressure on leak detector was pumped to 0.0XE-4 torr quickly. The base leak rate only could be pumped  to  4.5 xE-8 atm.cc/sec after 1 hour waiting time. All vacuum connections to leak detector  in the target hall were leak checked and they were good. Chad checked helium flow in SHC. He sprayed helium twice on tube heater(+) water block soldering joints. I did not see any response on leak detector in TH.The base Leak rate and base pressure did not move up during the test.  See attachment pictures.

Entry  Tuesday, February 04, 2014, 09:42, David Wang, South Hot-Cell, Repair, TM2, , pressure test on TM2 tube heater +(D) water line. 10x

Chad and I did a pressure test on TM2 tube Heater+(D) water line.I pressurized the D line with shop air from quick connectors(both ends) on service cap.chad applied bubble soap onto the D water block in SHC. The test started from 5psi,and increased 5psi each time to 40 psi. From 5 to 35 psi, no bubble has been found on water block. At 40 psi , bubble appeared from blind blank off seal , but not from soldering joints. Since the o-ring seal for the blank off is  vacuum seal , but not for pressurizing, It is understandable the seal could not hold 40 psi pressure air. No bubble had been found on the D water block soldering joints .See attachment pictures.

Entry  Wednesday, February 05, 2014, 14:05, David Wang, South Hot-Cell, Repair, TM2, , Leak check TM2 tube heater (+) water line from inside service cap in TH. 005.JPG008.JPG005.JPG

Bevan and I did a leak check on TM2 tube heater+ from inside service cap in TH. The leak detector base leak rate 0.0xE-9 atm.cc/sec, base  pressure 0.0xE-4totrr. One of side panel on service cap was opened. Bevan sprayed the helium to the "D" line inside the blue insulator.The helium flow was checked , and he sprayed twice. No response has been found on leak detector.  See attachment pictures

Entry  Wednesday, February 05, 2014, 14:12, Travis Cave, Spent Target Vault, Standard Operation, , , Targets moved from mini storage to F-308s 

All targets in the mini storage (4) have been moved from there and placed into the F-308s and those have been moved to the mech services room.

Entry  Friday, February 07, 2014, 10:29, chad fisher, South Hot-Cell, Repair, TM2, , TM2 C.B. and circuit D TM2_20140207_1.jpgTM2_20140207_2.jpg

Containment box has been removed and the blank off from circuit D has been removed for inspection of both the blank off and water block sealing surface.

Entry  Tuesday, February 11, 2014, 13:56, chad fisher, South Hot-Cell, Repair, TM2, , waterblock cleaning TM2_20140207_2.jpgTM2_20140211_2.jpg

New cleaning and polishing pads have been inserted onto the hot cell as well as rubber bungs and a new blank off.

The inital waterblock cleaning with the "scotch bright" pads has been completed. See attached pictures...the first picture being before and the second after.

Tommorow the water block will have bungs put in and a leak check to check the block will take place. After that, the new blank off will be installed and tested.

 

Entry  Thursday, February 13, 2014, 09:24, David Wang, South Hot-Cell, Repair, TM2, , Leak check TM2 tube heater (+) water line with rubber insert blocked WB in SHC 001.JPG002.JPG003.JPG004.JPG

Chad and I  did the Leak checked TM2 tube heater (+) water line  with rubber insert plugged water block on " D"  in SHC. The Leak detector was very easy to pump down to the bottom leak rate and pressure. Chad checked the helium flow in SHC, and sprayed 10 second helium on  the block. There is no response had been found during the test. The test was repeated again and no leak has been found. See attachment pictures.

Entry  Thursday, February 13, 2014, 13:30, David Wang, South Hot-Cell, Repair, TM2, , pressure test on TM2 tube heater +(D) water line. 

Chad and I did the pressure test on TM2tube heater+(D) water  line at SHC with shop air.We tested from 30psi to 80psi on both side of D line. The bubbles were found at 50-55psi on blank off seal in SHC.

    Reply  Thursday, February 13, 2014, 14:15, David Wang, South Hot-Cell, Repair, TM2, , pressure test on TM2 tube heater +(D) water line. 007.JPG008.JPG013.JPG

David Wang wrote:

Chad and I did the pressure test on TM2tube heater+(D) water  line at SHC with shop air.We tested from 30psi to 80psi on both side of D line. The bubbles were found at 50-55psi on blank off seal in SHC.

 I would like to correct this E-LOG. There is no real  leaking bubble had been found during the whole test according to the information supplied by Chad  Fisher during  this afternoon meeting. I would like to attach some pictures took from TH during this test.

Entry  Thursday, February 13, 2014, 14:23, David Wang, South Hot-Cell, Repair, TM2, , Leak check on TM2 tube heater (+) water line with blank off(elastic seal) installed on WB. 005.JPG001.JPG

Chad and I did the leak check on TM2 tube heater (+) water line  with blank off( + elastic o ring seal) installed on "D"  water block in SHC. We got the same no leak result as we got with rubber insert this morning.

Entry  Monday, February 17, 2014, 09:32, David Wang, Conditioning Station, Repair, TM2, , helium pressure test on TM2 tube heater +(D) water line. 6x

I did the helium pressure test on Tube heater+ line this morning. The vacuum on CS and TM2 are very good. The base lake rate on leak detector was 1.7xE-7 atm.cc/sec. Base pressure was 0.0xE-4torr.  I applied helium to the "D"line .The test started from 30psi up to 80psi on both side "D" line.The base leak rate slightly changed to 1.9xE-7 atm.cc/sec during the test,but not base pressure. At this base leak rate level, No obvious leak had been found . See attachment pictures. The test will be repeated later when the base leak rate could be pumped into E -8 or E-9(the best) range.            

Entry  Tuesday, February 18, 2014, 11:26, David Wang, Conditioning Station, Repair, TM2, , I stopped turbo pumps and disconnected vacuum system on TM 2 and CS 

I stopped turbo pumps and disconnected vacuum system on TM2 and CS. The TM2 will be moved to SHC for C seal installation on "D" water block.

Entry  Thursday, February 20, 2014, 11:04, chad fisher, South Hot-Cell, Repair, TM2, , Readying TM2 for C-Seal Leak Check TM2_20140220_01.jpg

Containment box has been removed and water block jig installed.

Entry  Monday, February 24, 2014, 11:05, chad fisher, South Hot-Cell, Repair, TM2, , Circuit D blank off 

The blank off with the o-ring has been removed, manipulator fixed, circuit D water block sealinhg surfaces cleaned and blank off with c-seals installed and torqued. Leak check will occur shortly.

Entry  Monday, February 24, 2014, 12:09, chad fisher, South Hot-Cell, Repair, TM2, , C-seal blank off test TM2_20140224_1.jpg

Circuit D has passed the vacuum leak check. Jig has been removed and containment box re-installed for move to conditioning station.