1102
|
Wednesday, October 14, 2015, 14:49 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Install new high current cables to TM2 | I installed a set of new high current cables
for TM2 Febiad run. The top of TM2
is configured to Febiad mode. See attachments |
|
|
1103
|
Thursday, October 15, 2015, 08:07 |
David Wang | South Hot-Cell | Standard Operation | TM2 | no target | TM2 no target electrical check at SHC. | I did a TM2 no target electrical check
at SHC this morning. A to RU at 500v
is 250K which is low. anode- |
|
|
1124
|
Monday, November 16, 2015, 08:04 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 | Update TH schedule according to changes.
See attachment 1,2 .
update TH schedule weekly. See attachments |
|
|
1127
|
Monday, November 16, 2015, 10:37 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 has been disconnected at TCS. | I stopped the TM3 and TCS vacuum pumps
and water system. The TM3 is disconnected
and vented. It will be moved to silo this |
|
|
1138
|
Thursday, November 26, 2015, 06:25 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | TM4 vacuum has been connected in TCS. | TM4 vacuum has been connected in TCS. All
vacuum pumps were started yesterday. The
pumping down of TM4 and TCS are good so far. |
|
|
1139
|
Thursday, November 26, 2015, 07:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | Helium pressure test on TM4 HS line at CS | I did helium pressure test on TM4 HS line
at TCS this morning. 70psi helium 3
minutes, 0.0xE-9 atm.cc/sec base leak rate. |
|
|
1140
|
Thursday, November 26, 2015, 07:37 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | TM4 has been connected at CS | TM4 has been connected at TCS. The water
system is started. The TCS HV cover for TM4
is installed also. Basically, The TM4 is |
|
|
1142
|
Monday, November 30, 2015, 11:46 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 | Weekly update TH schedule according to
changes. see attachment 1,2 .
Update TH schedule before the weekend. |
|
|
1143
|
Tuesday, December 01, 2015, 06:41 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#14 | Turned off TCS all vacuum pumps and water pumps. | I turned off TCS vacuum and water pumps.
The TSC and TM4 are still under vacuum condition. |
|
|
1146
|
Tuesday, December 01, 2015, 14:30 |
David Wang | ITE | Standard Operation | TM4 | UCx 13 | TM4 has been connected in ITE | TM4 has been connected in ITE. All turbo-pumps
are started. Everything is good so far. |
|
|
1153
|
Friday, January 22, 2016, 14:24 |
David Wang | South Hot-Cell | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule (sketch) | Post a sketch of 2016 winter shut down
target hall schedule. see attachment 1,2
UPDATE THE SCHEDULE ACCORDING |
|
|
1154
|
Friday, February 12, 2016, 13:00 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | 2016 Winter shut down target hall schedule.
See attachments1,2.
update the schedule weekly. |
6x |
|
1156
|
Thursday, February 25, 2016, 06:48 |
David Wang | ITE | Standard Operation | | | 4 Shielding blocks have been transferred from ITE to block storage area. | Dan and I transferred 4 shielding blocks
from ITE to block storage area. The ITE pit
is opened now. |
|
|
1157
|
Thursday, February 25, 2016, 06:52 |
David Wang | Conditioning Station | Standard Operation | | | stop CS vacuum pumps. | I stopped the conditioning station vacuum
pumps. The CS is still under vacuum without
venting. |
|
|
1158
|
Thursday, February 25, 2016, 09:27 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been disconnected in ITW | TM2 has been disconnected in ITW (except
vacuum lines). The vacuum system is still
operating. |
|
|
1159
|
Thursday, February 25, 2016, 09:29 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been disconnected in ITE. | TM4 has been disconnect in ITE(except
vacuum lines). The ITE vacuum system is still
operating. |
|
|
1160
|
Wednesday, March 02, 2016, 09:51 |
David Wang | ITW | Standard Operation | TM2 | | all water lines on TM2 and TM4 are purged. | All water lines on TM2 and TM4 are purged
for upcoming water lines helium pressure
test. |
|
|
1161
|
Wednesday, March 02, 2016, 10:04 |
David Wang | ITW | Standard Operation | TM2 | | Leak check on ITW and TM2. | Dan and I leak checked TM2 and ITW primary
vacuum vessel. It was found a 1X E-7 atm.cc/sec
leak on top T flange seal between TM2 and |
|
|
1162
|
Friday, March 04, 2016, 12:34 |
David Wang | ITE | Standard Operation | TM4 | | TM4 ITE annual leak check | Dan and I finished TM4 and ITE annual leak
check on primary and secondary vacuum vessel.
We found one leak on a KF25 blank off |
|
|
1163
|
Friday, March 04, 2016, 13:58 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | Update Schedule according to changes.See
attachment1, 2.
Re-post it after some minor |