537
|
Tuesday, November 12, 2013, 09:51 |
David Wang | ITE | Standard Operation | TM3 | | TM3 disconnection | TM3 has been disconnected this morning
and purged all HV water lines. I found
the power plug for all turbo pump fans wasnt |
|
538
|
Tuesday, November 12, 2013, 10:59 |
Bevan Moss | South Hot-Cell | Standard Operation | TM2 | | Electrical Test | Don Jackson and Myself completed
started an electrical test on TM2. All lines
passed the with OL to ground. When testing |
|
539
|
Tuesday, November 12, 2013, 12:43 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | TM2 moved from SHC to TCS | TM2 was moved by myself and David
from the SHC to the TCS. Move went well.
Curiously the fields on the module were measured |
|
540
|
Tuesday, November 12, 2013, 14:31 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | Turbo pumps started | The turbo pumps have been started
on TM2 and the conditioning station. |
|
541
|
Tuesday, November 12, 2013, 14:33 |
Bevan Moss | Conditioning Station | Repair | | | Cooling manifold returned | The cooling manifold for the conditioning
station high power water cooled lines has
been returned. The cooling package can once |
|
542
|
Wednesday, November 13, 2013, 10:01 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 leak check at conditioning station | I leak checked TM2 at conditioning station
this morning. All air to vacuum seals on
the top of the module are good. All water |
|
543
|
Thursday, November 14, 2013, 08:08 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Blank off and jig removal | Firday, November 8 all water blocks (excluding
I and K) were blanked off and vacuum leak
checked. No responses were found. (First |
|
544
|
Friday, November 15, 2013, 16:48 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Testing | High voltage testing was started
on TM2 with no source tray today. The maximum
stable for 1 minute voltage reached was 47.5kV |
|
545
|
Monday, November 18, 2013, 11:54 |
Bevan Moss | Conditioning Station | Repair | TM2 | | Fault on TCS Chill | This morning when I went to start
HV conditioning CP2 and CP3 both had faults
and the temperature of the water was ~27C. |
|
546
|
Monday, November 18, 2013, 16:42 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV Testing | The Glory of TM2 continues 100V at
a time. Today I brought the module to 46kV
and left it there for 1 hour. During this |
|
547
|
Monday, November 18, 2013, 16:44 |
Bevan Moss | Conditioning Station | Standard Operation | | | Testing of cooling package | I have tested all of the compressors
for TCS. All are operational and cycled as
they should. |
|
549
|
Tuesday, November 19, 2013, 14:24 |
David Wang | ITE | Repair | | | ITE TP3 | Hi
all, The old ITE TP3 pump is
moved out and the new pump is in |
|
550
|
Tuesday, November 19, 2013, 16:55 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV conditioning | HV conditioning of TM2 continued
today. At ~53.5kV the module started to spark
externally to the HV cover. This is the first |
|
553
|
Wednesday, November 20, 2013, 13:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM2 | | HV testing of TM2 | HV testing without the cover continued
today. With the EINZEL lens at 30kV the target
module was able to achieve 58.7kV. At this |
|
557
|
Tuesday, November 26, 2013, 14:10 |
Travis Cave | Crane | Maintenance | | | Thermal relay replaced | The bad thermal motor protection relay
for the crane has been replaced with a new
unit. Crane was tested in pendant(local) |
|
558
|
Wednesday, November 27, 2013, 12:50 |
Bevan Moss | South Hot-Cell | Standard Operation | TM3 | | Ground devices wiring check | Travis and I completed an electrical
check on the wiring harness for the devices
on the ground plane. All lines passed 500V |
|
559
|
Wednesday, November 27, 2013, 15:24 |
Bevan Moss | South Hot-Cell | Maintenance | TM3 | | Wiring Harness Electrical Test | Maico removed the containment box
today allow Travis and I to further test
the wiring harness. I disconnected the junction |
|
560
|
Friday, November 29, 2013, 11:54 |
chad fisher | South Hot-Cell | Repair | TM3 | | Steerer short investegation | Using in cell camera and transit the suspect
line on the steerers was inspected as best
as possible. An existing photo of the complete |
|
561
|
Friday, November 29, 2013, 11:57 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Steerer short investegation |
|
|
563
|
Tuesday, December 03, 2013, 09:58 |
David Wang | ITW | Standard Operation | TM4 | | I moved 5 shielding blocks from ITW to block storage area. | I moved 5 shielding blocks from ITW to
block storage area. |
|