ID Date Authordown Category Type Module Target/Number Subject
  972   Tuesday, June 30, 2015, 15:53 David WangConditioning StationDevelopmentTM2 leak on TM2 at CS

 I leak checked TM2 at CS this afternoon which including air to vacuum check on service cap and helium pressure test on water lines. There is a small leak on water line R ,U (COIL1) during the helium pressure test.. Below 20 psi helium, there is no leak on it. But , once the helium pressure is increased over 20 psi, it showed up on Leak Detector. At 60 psi helium, the leak rate is 9.4xE-9 atm.cc/sec. For detail information, See attachment.  All other water lines and air to vacuum seals are good.

Attachment 1: TM2_leak_check_2015-06-30.pdf
TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf TM2_leak_check_2015-06-30.pdf
Attachment 2: leak_check_2015-06-30_007.JPG
leak_check_2015-06-30_007.JPG
Attachment 3: leak_check_2015-06-30_009.JPG
leak_check_2015-06-30_009.JPG
  978   Friday, July 03, 2015, 09:41 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015

Updated the schedule before the weekend 2015-07-03. See attachment 1,2

Updated the schedule according to present TM2 refurbishment process. See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
  982   Tuesday, July 07, 2015, 12:12 David WangConditioning StationRepair  CS TP1S replacement

CS TP1S had been replaced with a new TP-301 pump this morning.The old pump was broken last week.

  984   Wednesday, July 08, 2015, 14:05 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC

Chad and I leak checked coil line(R,U) on TM2 at SHC yesterday. The leak detector was pumped down to 0.0Xe-9 atm.cc/sec before the check. Chad sprayed helium on the soldering joints connecting the cooling copper lines to the small holding blocks for the coil terminal(R,U).  After sprayed helium 2 seconds, I saw the leak rate on LD started to climbed up. The highest leak rate is 4.0xE-8 atm.cc/sec. It is a very positive response. We waited the leak detector pumped back to 0.0xE-9am.cc/sec, and tested again on the same joints. The result is same. Chad also sprayed helium on the R,U water blocks to check the C-seal. I saw a delayed tiny response on LD ( from 0.0 to 1.3xE-9atm.cc/sec). We think this tiny response is caused by the helium drifting to the leak soldering joint, but not a real C seal leak.

  985   Wednesday, July 08, 2015, 14:24 David WangSouth Hot-CellRepairTM2 TM2 pressure bubble test on RU water blocks.

July-06, 2015. Chad , Grant and I did the bubble test on R,U water blocks. We suspected the leak on the R,U circuit is from C seals on the water blocks so we did this test first. I applied both air and helium to R,U circuit , Chad applied snoop soap on the R,U water blocks.The air and helium pressure was increased from 40 psi to 90 psi Max step by step.Chad did not see any bubbles on the water blocks during the test. Since we did not find the leak source, we decided to do vacuum helium check on the all joints and c-seals of the R,U lines later.  Finally, We found the leak by vacuum helium spray the day after this bubble test. See other e-log.

  990   Thursday, July 09, 2015, 14:02 David WangConditioning StationDevelopmentTM1 TM1 is pumping down at CS

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

  998   Wednesday, July 15, 2015, 11:18 David WangSouth Hot-CellRepairTM2 leak check coil line(R,U) on TM2 at SHC

Chad and I leak checked the coil 1 circuit(R,U) after rebuilt coil line is installed on TM2 source tray. The pumping down on the circuit is very quick and smooth. The LD base lake rate 0.0xE-9 atm.cc/sec. Base pressure0.0xE-4 torr.

Chad sprayed lots helium on the R( coil 1+)and U(coil 1 -) water blocks. During  1 minute waiting time, there is no any response on LD. The R and U water blocks and C-seals are leak tight.

Attachment 1: 007.JPG
007.JPG
Attachment 2: 008.JPG
008.JPG
  999   Thursday, July 16, 2015, 07:38 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 07 2015

Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2

2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1006   Tuesday, July 21, 2015, 12:29 David WangITEMaintenance  target pit Hepa filter

Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box  is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room.  It will be moved out of there by Tony.N soon with RPG help.

  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.

The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced.

  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Update Target Hall schedule after the changing on TM2 process. See attachment 1,2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.

Dan and I moved 5 shielding blocks from ITE to block storage area. The move is smooth.

  1016   Monday, July 27, 2015, 15:34 David WangITEStandard OperationTM4 Leak check on TM4 HS water line with new UCX target. at SHC

Chad and I leak checked the HS line at SHC after UCX target installation. On first round helium spray, one of VCR fitting has a leak to E-6 atm.cc/sec range. Chad tightened the fitting, and solved the problem. We leak checked both VCR fittings twice. No leak. The line will be helium pressured at CS tomorrow.

  1017   Monday, July 27, 2015, 15:46 David WangSouth Hot-CellStandard Operation  The yellow steel plug is put on SHC in TH

The yellow steel plug is put on SHC in TH. The spent target is inside the SHC.The field around the SHC area in TH is so high that we have put it on. It will be moved out on this Thursday just before the spent target move. 

  1018   Monday, July 27, 2015, 17:03 David WangConditioning StationStandard OperationTM4UCx 13UCx13 and TM4 under vacuum at CS.

I connected the CS  vacuum system  to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE.

  1019   Tuesday, July 28, 2015, 10:12 David WangConditioning StationStandard OperationTM4UCx 13Helium pressure test on TM4 HS line at CS

I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium  2 minutes. base leak rate0.0x E-9 atm.cc/sec.  No response during the test. No leak.

  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replaced

Tony and I replaced the ITE TP4 turbo pump today. The pumping time on controller has been reset to 0. The replaced broken  pump is bagged and stored at west end of TH.

  1024   Wednesday, July 29, 2015, 06:24 David WangConditioning StationStandard OperationTM4UCx 13Stopped the CS and TM4 pumps and vent with argon.

Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target.

  1026   Wednesday, July 29, 2015, 10:14 David WangITEStandard OperationTM4 TM4 has been connected in ITE

Dan and I connected TM4 in ITE. We checked all water signals on ITE cooling circuits. Everything is good.

  1028   Friday, July 31, 2015, 09:47 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015

Weekly update of Target Hall schedule after so many jobs have been finished in this week.  See attachment 1, 2

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp