812
|
Thursday, December 04, 2014, 16:37 |
David Wang | Conditioning Station | Development | TM2 | | connected TM2 and CS vacuum system . | I connected TM2 and CS vacuum system. All
vacuum pumps on TM2 and CS are started .The
pumping down is good so .far |
|
|
813
|
Friday, December 05, 2014, 07:47 |
David Wang | Conditioning Station | Development | TM2 | | TM2 at CS | The pumping down on TM2 at CS was good
overnight. However, the back up line pressure
is still too high for LD to get to 0.0-E-9atm.cc/sec |
|
|
814
|
Friday, December 05, 2014, 11:58 |
David Wang | Conditioning Station | Development | TM2 | | helium pressure test on TM2 tube heater +(D) water lines. | At CS, The leak detector is hooked directly
to the TM2 top service cap. The base LR 0.0xE-9
atm.cc/sec, base pressure 0.0xE-4torr. Applied |
6x |
|
827
|
Tuesday, January 06, 2015, 11:14 |
David Wang | ITE | Standard Operation | TM4 | | 4 Shielding blocks have been moved out of ITE . | 4 shielding blocks have been moved out
of ITE to block storage area. Fiona
did the survey and with me during the move. |
|
|
830
|
Thursday, January 08, 2015, 08:04 |
David Wang | ITE | Standard Operation | TM4 | | TM4 water lines have been disconnected in ITE and purged. | TM4 waterlines have been disconnected and
purged in ITE. The TM4 vacuum system is still
in operation. |
|
|
840
|
Friday, February 06, 2015, 08:06 |
David Wang | Crane | Repair | | | TH crane lost movement controls since last Friday. | Last Friday, During the crane per use check,
I found the main power supply to to crane
was shut off. I was told Don and Travis |
|
|
841
|
Friday, February 06, 2015, 12:27 |
David Wang | Crane | Repair | | | TH crane troubleshoot | Gordon crane technician started TH crane
trouble shooting this morning. The problem
is found that there is no 115VAC power supply |
|
|
843
|
Thursday, February 12, 2015, 09:11 |
David Wang | Crane | Repair | TM4 | | TH crane troubleshoot and annual inspection. | Gordon crane technicians continued their
troubleshooting on this Tuesday. They found
the crane up-limit protection switch which |
|
|
844
|
Monday, February 16, 2015, 11:57 |
David Wang | Crane | Repair | | | TH crane | Dave.Morris installed a new battery on
crane control PLC board and uploaded the
program. Travis, Dan and I tested the crane |
|
|
847
|
Monday, February 23, 2015, 12:28 |
David Wang | ITE | Maintenance | | | 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. | Dan and I replaced pedal wheels and coils
on ITE water flow sensors. It is a shut down
job we did every two years. See attachment |
|
|
848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement | Dan and I replaced pedal wheels and coils
on ITW water flow sensors. It is a shut
down job we did every two years. See attachment |
|
|
849
|
Thursday, February 26, 2015, 09:22 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Mar 25th | TH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1. |
 |
|
851
|
Monday, March 02, 2015, 10:52 |
David Wang | ITE | Maintenance | TM4 | UCx | ITE primary and secondary vacuum vessels leak check. | Dan and I leak checked ITE primary and
secondary vacuum vessels with TM4 in
ITE. The leak detector was hooked to ITE |
|
|
852
|
Thursday, March 05, 2015, 06:44 |
David Wang | ITE | Maintenance | TM4 | | 5 Shielding blocks have been moved to ITE. | 5 Shielding blocks have been moved to ITE
for next week TM1 move and RPG Radon test. |
|
|
853
|
Thursday, March 05, 2015, 07:17 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | TH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be |
6x |
|
859
|
Thursday, March 12, 2015, 13:04 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITE to ITW. | 5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move. |
|
|
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | This schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. |
   |
|
872
|
Wednesday, March 25, 2015, 14:25 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#45 | Leak check on TM4 HS water line with new Ta#45 target. at SHC | Chad and I leak checked TM4 HS water line
with new Ta#45 target installed at SHC. Leak
detector base leak rate 0.0Xe-9 atm.cc/sec, |
|
|
873
|
Wednesday, March 25, 2015, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 and CS turbo- pumps are started . | I connected TM4 and CS vacuum system after
TM4 move. CS roughing pump was started first
this morning. Later, Anders, Bill and I started |
|
|
875
|
Friday, March 27, 2015, 10:03 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | Helium pressure test on TM4 HS line at CS | The helium pressure test on TM4 HS line
at conditioning station is done. No leak.
I also leak checked all vacuum seals on TM4 |
  |