Message ID: 755     Entry time: Wednesday, September 24, 2014, 15:03
Author: David Wang 
Category: South Hot-Cell 
Type: Standard Operation 
Module: TM4 
Target/Number: Ta#44 
Subject: Leak check on TM4 HS water line with new Ta#44 target. at SHC 

This morning Chad and I leak checked TM4 HS line with new Ta#44 target installed. I calibrated LD before the check. Before check, the LD base LR 0.0xE-9 atm.cc/sec, base LP 0.0xE-4 torr. Chad sprayed helium on both VCR fittings and did a flush around the target. There is no any response had been found on LD,. The line is good on leak tight. with spray method.  No helium pressure test on the HS line at CS since TM4 was moved back to ITE directly.