Message ID: 778     Entry time: Tuesday, November 04, 2014, 11:05
Author: David Wang 
Category: South Hot-Cell 
Type: Standard Operation 
Module: TM1 
Target/Number: ThO#1 
Subject: Leak check on TM1 HS water line withThO#1 installed. 

Chad and I leak checked HS line on TM1 with ThO#1 target installed. The LD pumped down to base leak rate 0.0xE-9 atm.cc/sec, base leak rate 0.0xE-4 torr. The pumping down process is normal. Chad sprayed helium on both VCR joints (each for 2 seconds) , and he did a flush spray around the target for 5 seconds. No any response had been found on LD during and after the spray( 40seconds waiting time). The target is leak tight.