Entry  Friday, February 06, 2015, 12:27, David Wang, Crane, Repair, , , TH crane troubleshoot  

Gordon crane technician started TH crane trouble shooting this morning. The problem is found that there is no 115VAC power supply to energize  a main coil which is used to switch on 450V AC power supply to crane. He did a test and found  the crane could be operated  by big yellow pedant in control room when he manually gave the coil 115VAC power supply to energize it.. At that moment, the crane is set to big yellow pedant operating mode. But, he can not figure out why there is no 115VAC power to this coil.The wiring  tracking back is not an easy job for him. The troubleshooting is  stopped now. The job will be resumed on next week with more skilled technician involving in from Gordon crane.

Entry  Thursday, February 12, 2015, 09:11, David Wang, Crane, Repair, TM4, , TH crane troubleshoot and annual inspection. 

Gordon crane technicians continued their troubleshooting on this Tuesday. They found the crane up-limit protection switch which is installed on the same bracket with the the crane down view camera is broken. The spring inside the limit switch  which is used for pushing the action plunge out in the switch lost its function. This up limit switch is the last protection for the crane so it is set as when it is in action the crane main contact coil  which controls crane  power supply will be in open position. The broken switch is replaced by a new one( same type) on this Wednesday. The crane annual inspection has been  finished after the switch replacement. The crane works fine now.

Entry  Monday, February 16, 2015, 11:57, David Wang, Crane, Repair, , , TH crane 

Dave.Morris installed a new battery on crane control PLC board and uploaded the program. Travis, Dan and I tested the crane in local, remote, and test mode. The crane works fine. Also, the TH lock up has been tested. Everything is good.

Entry  Monday, February 23, 2015, 12:28, David Wang, ITE, Maintenance, , , 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. 2015_shut_down_ITE_water_sensors__replacements.pdf

Dan and I replaced pedal wheels and coils on ITE water flow sensors. It is a shut down job we did every two years. See attachment for detail.

Entry  Wednesday, February 25, 2015, 10:44, David Wang, ITW, Maintenance, , , 2015 shut dwon ITW water sensor coils and pedal wheels replacement 2015_shut_down_ITW_water_sensors__replacements.pdf

Dan and I replaced pedal wheels and coils on ITW water flow sensors. It is a shut down job we did every two years. See attachment for detail.

Entry  Thursday, February 26, 2015, 09:22, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Mar 25th Target_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdf

TH shut down activities schedule from Feb 23th-March 25th. The schedule will be updated each week. See attachment 1.

Feb-27-2015: Updated the schedule, and uploaded as PDF file. See attachment 2.

Entry  Monday, March 02, 2015, 10:52, David Wang, ITE, Maintenance, TM4, UCx, ITE primary and secondary vacuum vessels leak check. 

Dan and I leak checked ITE primary and secondary vacuum vessels with TM4  in ITE. The leak detector was hooked to ITE TP2 BV2. Leak detector  base leak rate: 0.0xE-09 atm.cc/sec, base pressure: 0.0xE-4 torr. All secondary vacuum vessel seals has been checked(helium spray), and no leak has been found. On the ITE primary vacuum vessel, we  leak checked every thing except the TM4 service cap and water lines inside the TM4. NO leak has been found on ITE primary vessels. The primary vacuum seals on TM4 service cap and TM4 waterlines(helium pressure test) will be checked at CS later.

Entry  Thursday, March 05, 2015, 06:44, David Wang, ITE, Maintenance, TM4, , 5 Shielding blocks have been moved to ITE. 

5 Shielding blocks have been moved to ITE for next week TM1 move and RPG Radon test.

Entry  Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x

TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned. See attachments for updated schedule.

I updated the schedule today. See attachment 3, 4 for updating.  2015-Mar-10.

2013-Mar -13, I updated the schedule to show the jobs we finished this week. See attachment 5,6

Entry  Thursday, March 12, 2015, 13:04, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITE to ITW. 

5 shielding blocks have been transferred from ITE to ITW for next week TM4 move.

Entry  Monday, March 23, 2015, 07:56, David Wang, ITE, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp

This schedule is following Dons schedule on module moves. See attachments for updating.

2015-03-27: Weekly update the schedule. The shut down job is close to the end. See attachment 3, 4.

Entry  Wednesday, March 25, 2015, 14:25, David Wang, South Hot-Cell, Standard Operation, TM4, Ta#45, Leak check on TM4 HS water line with new Ta#45 target. at SHC 

Chad and I leak checked TM4 HS water line with new Ta#45 target installed at SHC. Leak detector base leak rate 0.0Xe-9 atm.cc/sec, base pressure 0.0Xe-4 torr. Chad sprayed helium twice on each of HS 2 VCR joints.No leak has been found. The joints are leak tight. The helium pressure test  will be done at CS later.

Entry  Wednesday, March 25, 2015, 14:34, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 and CS turbo- pumps are started . 

I connected TM4 and CS vacuum system after TM4 move. CS roughing pump was started first this morning. Later, Anders, Bill and I started 3 turbo pumps on TM4 and CS. The pumping down is good so far. The CS vacuum system ion gauges are turned on also.

Entry  Friday, March 27, 2015, 10:03, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, Helium pressure test on TM4 HS line at CS 001.JPG005.JPG006.JPG

The helium pressure test on TM4 HS line at conditioning station is done. No leak. I also leak checked all vacuum seals on TM4 service cap. They are all good.

Entry  Friday, March 27, 2015, 11:29, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 is connected at CS 010.JPG013.JPG012.JPG

TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been  installed onto the TM4 service cap.The CS water system is started. All water signals are good so far.   Anders will start  HV and heaters conditioning on next Monday.

Entry  Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp

Updated schedule this morning after last Fridays ISAC facility support group meeting.

Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time  weekly update.

Entry  Wednesday, April 01, 2015, 06:56, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 has been disconnected at CS. 

TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday.

Entry  Wednesday, April 01, 2015, 13:08, David Wang, ITE, Standard Operation, TM4, , Replaced ITE tank to module 42X0.275 o-ring 001.JPG002.JPG004.JPG005.JPG006.JPG

I replaced ITE tank to module 42 ID X 0.275 o-ring. The o-ring is changed once a year before the first beam time. The flanges was cleaned and the new o-ring was installed. It works fine.

Entry  Wednesday, April 01, 2015, 13:12, David Wang, ITE, Standard Operation, TM4, Ta#45, TM4 has been connected in ITE 

TM4 has been connected in ITE. ITE six turbo-pumps have been started. So far so good.

Entry  Friday, April 10, 2015, 15:40, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITW to ITE. 

5 shielding  blocks have been transferred to ITE. The ITE is configured to take proton beam.