  841   Friday, February 06, 2015, 12:27 David WangCraneRepair  TH crane troubleshoot Gordon crane technician started TH crane
trouble shooting this morning. The problem
is found that there is no 115VAC power supply
  
  843   Thursday, February 12, 2015, 09:11 David WangCraneRepairTM4 TH crane troubleshoot and annual inspection.Gordon crane technicians continued their
troubleshooting on this Tuesday. They found
the crane up-limit protection switch which
  
  844   Monday, February 16, 2015, 11:57 David WangCraneRepair  TH craneDave.Morris installed a new battery on
crane control PLC board and uploaded the
program. Travis, Dan and I tested the crane
  
  847   Monday, February 23, 2015, 12:28 David WangITEMaintenance  2015 shut down coils and pedal wheels replacement on ITE water flow sensors.Dan and I replaced pedal wheels and coils
on ITE water flow sensors. It is a shut down
job we did every two years. See attachment
 2015_shut_down_ITE_water_sensors__replacements.pdf 
  848   Wednesday, February 25, 2015, 10:44 David WangITWMaintenance  2015 shut dwon ITW water sensor coils and pedal wheels replacementDan and I replaced pedal wheels and coils
on ITW water flow sensors. It  is a shut
down job we did every two years. See attachment
 2015_shut_down_ITW_water_sensors__replacements.pdf 
  849   Thursday, February 26, 2015, 09:22 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Mar 25thTH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1.
 Target_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdf 
  851   Monday, March 02, 2015, 10:52 David WangITEMaintenanceTM4UCxITE primary and secondary vacuum vessels leak check.Dan and I leak checked ITE primary and
secondary vacuum vessels with TM4  in
ITE. The leak detector was hooked to ITE
  
  852   Thursday, March 05, 2015, 06:44 David WangITEMaintenanceTM4 5 Shielding blocks have been moved to ITE.5 Shielding blocks have been moved to ITE
for next week TM1 move and RPG Radon test.
  
  853   Thursday, March 05, 2015, 07:17 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateTH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be
 6x 
  859   Thursday, March 12, 2015, 13:04 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move.
  
  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateThis schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  872   Wednesday, March 25, 2015, 14:25 David WangSouth Hot-CellStandard OperationTM4Ta#45Leak check on TM4 HS water line with new Ta#45 target. at SHCChad and I leak checked TM4 HS water line
with new Ta#45 target installed at SHC. Leak
detector base leak rate 0.0Xe-9 atm.cc/sec,
  
  873   Wednesday, March 25, 2015, 14:34 David WangConditioning StationStandard OperationTM4Ta#45 TM4 and CS turbo- pumps are started .I connected TM4 and CS vacuum system after
TM4 move. CS roughing pump was started first
this morning. Later, Anders, Bill and I started
  
  875   Friday, March 27, 2015, 10:03 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CSThe helium pressure test on TM4 HS line
at conditioning station is done. No leak.
I also leak checked all vacuum seals on TM4
 001.JPG005.JPG006.JPG 
  876   Friday, March 27, 2015, 11:29 David WangConditioning StationStandard OperationTM4Ta#45TM4 is connected at CSTM4 has been connected at CS which includes
high current cables, water lines, EE cable,
and Enizel lens cable. The HV cover has been 
 010.JPG013.JPG012.JPG 
  877   Monday, March 30, 2015, 07:38 David WangITEStandard OperationTM4 TH Shut Down Activities Schedule Feb 23th- Apr 15th updateUpdated schedule this morning after last
Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  880   Wednesday, April 01, 2015, 06:56 David WangConditioning StationStandard OperationTM4Ta#45TM4 has been disconnected at CS.TM4 has been disconnected at CS. The CS
and TM4 is venting for move. Anders stopped
vacuum and water system yesterday.
  
  882   Wednesday, April 01, 2015, 13:08 David WangITEStandard OperationTM4 Replaced ITE tank to module 42X0.275 o-ringI replaced ITE tank to module 42 ID X 0.275
o-ring. The o-ring is changed once a year
before the first beam time. The flanges was
 001.JPG002.JPG004.JPG005.JPG006.JPG 
  883   Wednesday, April 01, 2015, 13:12 David WangITEStandard OperationTM4Ta#45TM4 has been connected in ITETM4 has been connected in ITE. ITE six
turbo-pumps have been started. So far so
good.
  
  884   Friday, April 10, 2015, 15:40 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.5 shielding  blocks have been transferred
to ITE. The ITE is configured to take proton
beam.
  