841
|
Friday, February 06, 2015, 12:27 |
David Wang | Crane | Repair | | | TH crane troubleshoot | Gordon crane technician started TH crane
trouble shooting this morning. The problem
is found that there is no 115VAC power supply |
|
843
|
Thursday, February 12, 2015, 09:11 |
David Wang | Crane | Repair | TM4 | | TH crane troubleshoot and annual inspection. | Gordon crane technicians continued their
troubleshooting on this Tuesday. They found
the crane up-limit protection switch which |
|
844
|
Monday, February 16, 2015, 11:57 |
David Wang | Crane | Repair | | | TH crane | Dave.Morris installed a new battery on
crane control PLC board and uploaded the
program. Travis, Dan and I tested the crane |
|
847
|
Monday, February 23, 2015, 12:28 |
David Wang | ITE | Maintenance | | | 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. | Dan and I replaced pedal wheels and coils
on ITE water flow sensors. It is a shut down
job we did every two years. See attachment |
|
848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement | Dan and I replaced pedal wheels and coils
on ITW water flow sensors. It is a shut
down job we did every two years. See attachment |
|
849
|
Thursday, February 26, 2015, 09:22 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Mar 25th | TH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1. |
|
851
|
Monday, March 02, 2015, 10:52 |
David Wang | ITE | Maintenance | TM4 | UCx | ITE primary and secondary vacuum vessels leak check. | Dan and I leak checked ITE primary and
secondary vacuum vessels with TM4 in
ITE. The leak detector was hooked to ITE |
|
852
|
Thursday, March 05, 2015, 06:44 |
David Wang | ITE | Maintenance | TM4 | | 5 Shielding blocks have been moved to ITE. | 5 Shielding blocks have been moved to ITE
for next week TM1 move and RPG Radon test. |
|
853
|
Thursday, March 05, 2015, 07:17 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | TH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be |
6x |
859
|
Thursday, March 12, 2015, 13:04 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITE to ITW. | 5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move. |
|
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | This schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. |
|
872
|
Wednesday, March 25, 2015, 14:25 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#45 | Leak check on TM4 HS water line with new Ta#45 target. at SHC | Chad and I leak checked TM4 HS water line
with new Ta#45 target installed at SHC. Leak
detector base leak rate 0.0Xe-9 atm.cc/sec, |
|
873
|
Wednesday, March 25, 2015, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 and CS turbo- pumps are started . | I connected TM4 and CS vacuum system after
TM4 move. CS roughing pump was started first
this morning. Later, Anders, Bill and I started |
|
875
|
Friday, March 27, 2015, 10:03 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | Helium pressure test on TM4 HS line at CS | The helium pressure test on TM4 HS line
at conditioning station is done. No leak.
I also leak checked all vacuum seals on TM4 |
|
876
|
Friday, March 27, 2015, 11:29 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 is connected at CS | TM4 has been connected at CS which includes
high current cables, water lines, EE cable,
and Enizel lens cable. The HV cover has been |
|
877
|
Monday, March 30, 2015, 07:38 |
David Wang | ITE | Standard Operation | TM4 | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | Updated schedule this morning after last
Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. |
|
880
|
Wednesday, April 01, 2015, 06:56 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 has been disconnected at CS. | TM4 has been disconnected at CS. The CS
and TM4 is venting for move. Anders stopped
vacuum and water system yesterday. |
|
882
|
Wednesday, April 01, 2015, 13:08 |
David Wang | ITE | Standard Operation | TM4 | | Replaced ITE tank to module 42X0.275 o-ring | I replaced ITE tank to module 42 ID X 0.275
o-ring. The o-ring is changed once a year
before the first beam time. The flanges was |
|
883
|
Wednesday, April 01, 2015, 13:12 |
David Wang | ITE | Standard Operation | TM4 | Ta#45 | TM4 has been connected in ITE | TM4 has been connected in ITE. ITE six
turbo-pumps have been started. So far so
good. |
|
884
|
Friday, April 10, 2015, 15:40 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITW to ITE. | 5 shielding blocks have been transferred
to ITE. The ITE is configured to take proton
beam. |
|