ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
830
|
Thursday, January 08, 2015, 08:04 |
David Wang | ITE | Standard Operation | TM4 | | TM4 water lines have been disconnected in ITE and purged. |
TM4 waterlines have been disconnected and purged in ITE. The TM4 vacuum system is still in operation. |
840
|
Friday, February 06, 2015, 08:06 |
David Wang | Crane | Repair | | | TH crane lost movement controls since last Friday. |
Last Friday, During the crane per use check, I found the main power supply to to crane was shut off. I was told Don and Travis shut off the main power before Triumf power outage. Travis restored crane main power and I could turn on the main relay on radio pedant in TH. But, I didnt have all crane main bridge movement controls on TH raido pedant except rotation. I still have all movement controls on small trolley from the radio pedant. When I operated radio pedant, Travis could hear the relay works in crane control room, but in TH no crane movements. It looks like a crane control problem so Dave Morris was contacted. Dave found one of battery on PLC board is dead and need to be replaced.He did order the battery right way. On this Wednesday, Dave noticed us we could temporarily run the crane. I went to T.H for checking. At the beginning, I found I cant not turn on the crane main relay from radio pedant in TH. Don was in crane control room. He switched the crane control from TH radio mode to control room pedant( big yellow control box laid on the ground, the mode switch is located on the up left corner of first main panel) and he turned on the main relay by doing this and got all movement controls from the big yellow pedant. After switching the mode back to TH radio mode I also got all the controls from TH radio pedant. Everything worked fine on crane so we moved the man lift into TH on Wednesday afternoon and arranged the TH crane inspection on Thursday. On Thursday morning, Gordon Crane guys came in TH and started their inspection. At the beginning, everything works fine. But after they did some operation and checks on crane, the crane main relay could not be switched on again (from TH raid box). The crane inspection job are suspended. RH group tried to active the main relay by switching the mode back to yellow pedant in crane control room just like we did on Wedsday, but it did not work this time. David Morris was contacted to check from his side if anything wrong. He checked and told us the program is working and everything is good from his side. A crane expert is needed to trouble shoot this problem. Neil Wong is going to bring Gordon crane guys and start to trouble shoot the problem this morning. |
841
|
Friday, February 06, 2015, 12:27 |
David Wang | Crane | Repair | | | TH crane troubleshoot |
Gordon crane technician started TH crane trouble shooting this morning. The problem is found that there is no 115VAC power supply to energize a main coil which is used to switch on 450V AC power supply to crane. He did a test and found the crane could be operated by big yellow pedant in control room when he manually gave the coil 115VAC power supply to energize it.. At that moment, the crane is set to big yellow pedant operating mode. But, he can not figure out why there is no 115VAC power to this coil.The wiring tracking back is not an easy job for him. The troubleshooting is stopped now. The job will be resumed on next week with more skilled technician involving in from Gordon crane. |
843
|
Thursday, February 12, 2015, 09:11 |
David Wang | Crane | Repair | TM4 | | TH crane troubleshoot and annual inspection. |
Gordon crane technicians continued their troubleshooting on this Tuesday. They found the crane up-limit protection switch which is installed on the same bracket with the the crane down view camera is broken. The spring inside the limit switch which is used for pushing the action plunge out in the switch lost its function. This up limit switch is the last protection for the crane so it is set as when it is in action the crane main contact coil which controls crane power supply will be in open position. The broken switch is replaced by a new one( same type) on this Wednesday. The crane annual inspection has been finished after the switch replacement. The crane works fine now. |
844
|
Monday, February 16, 2015, 11:57 |
David Wang | Crane | Repair | | | TH crane |
Dave.Morris installed a new battery on crane control PLC board and uploaded the program. Travis, Dan and I tested the crane in local, remote, and test mode. The crane works fine. Also, the TH lock up has been tested. Everything is good. |
847
|
Monday, February 23, 2015, 12:28 |
David Wang | ITE | Maintenance | | | 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. |
Dan and I replaced pedal wheels and coils on ITE water flow sensors. It is a shut down job we did every two years. See attachment for detail. |
Attachment 1: 2015_shut_down_ITE_water_sensors__replacements.pdf
|
|
848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement |
Dan and I replaced pedal wheels and coils on ITW water flow sensors. It is a shut down job we did every two years. See attachment for detail. |
Attachment 1: 2015_shut_down_ITW_water_sensors__replacements.pdf
|
|
849
|
Thursday, February 26, 2015, 09:22 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Mar 25th |
TH shut down activities schedule from Feb 23th-March 25th. The schedule will be updated each week. See attachment 1.
Feb-27-2015: Updated the schedule, and uploaded as PDF file. See attachment 2. |
Attachment 1: Target_Hall_shut_down_activities.mpp
|
Attachment 2: Target_Hall_shut_down_activities.pdf
|
|
851
|
Monday, March 02, 2015, 10:52 |
David Wang | ITE | Maintenance | TM4 | UCx | ITE primary and secondary vacuum vessels leak check. |
Dan and I leak checked ITE primary and secondary vacuum vessels with TM4 in ITE. The leak detector was hooked to ITE TP2 BV2. Leak detector base leak rate: 0.0xE-09 atm.cc/sec, base pressure: 0.0xE-4 torr. All secondary vacuum vessel seals has been checked(helium spray), and no leak has been found. On the ITE primary vacuum vessel, we leak checked every thing except the TM4 service cap and water lines inside the TM4. NO leak has been found on ITE primary vessels. The primary vacuum seals on TM4 service cap and TM4 waterlines(helium pressure test) will be checked at CS later. |
852
|
Thursday, March 05, 2015, 06:44 |
David Wang | ITE | Maintenance | TM4 | | 5 Shielding blocks have been moved to ITE. |
5 Shielding blocks have been moved to ITE for next week TM1 move and RPG Radon test. |
853
|
Thursday, March 05, 2015, 07:17 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update |
TH shut down jobs are processing as scheduled this week. Discussed with Don, and we think the jobs scheduled in next week should be processed as we planned. See attachments for updated schedule.
I updated the schedule today. See attachment 3, 4 for updating. 2015-Mar-10.
2013-Mar -13, I updated the schedule to show the jobs we finished this week. See attachment 5,6 |
Attachment 1: Target_Hall_shut_down_activities.pdf
|
|
Attachment 2: Target_Hall_shut_down_activities.mpp
|
Attachment 3: Target_Hall_shut_down_activities.pdf
|
|
Attachment 4: Target_Hall_shut_down_activities.mpp
|
Attachment 5: Target_Hall_shut_down_activities.pdf
|
|
Attachment 6: Target_Hall_shut_down_activities.mpp
|
859
|
Thursday, March 12, 2015, 13:04 |
David Wang | ITE | Standard Operation | TM4 | | 5 Shielding blocks have been transferred from ITE to ITW. |
5 shielding blocks have been transferred from ITE to ITW for next week TM4 move. |
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update |
This schedule is following Dons schedule on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. The shut down job is close to the end. See attachment 3, 4. |
Attachment 1: Target_Hall_shut_down_activities.pdf
|
|
Attachment 2: Target_Hall_shut_down_activities.mpp
|
Attachment 3: Target_Hall_shut_down_activities.pdf
|
|
Attachment 4: Target_Hall_shut_down_activities.mpp
|
872
|
Wednesday, March 25, 2015, 14:25 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#45 | Leak check on TM4 HS water line with new Ta#45 target. at SHC |
Chad and I leak checked TM4 HS water line with new Ta#45 target installed at SHC. Leak detector base leak rate 0.0Xe-9 atm.cc/sec, base pressure 0.0Xe-4 torr. Chad sprayed helium twice on each of HS 2 VCR joints.No leak has been found. The joints are leak tight. The helium pressure test will be done at CS later. |
873
|
Wednesday, March 25, 2015, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 and CS turbo- pumps are started . |
I connected TM4 and CS vacuum system after TM4 move. CS roughing pump was started first this morning. Later, Anders, Bill and I started 3 turbo pumps on TM4 and CS. The pumping down is good so far. The CS vacuum system ion gauges are turned on also. |
875
|
Friday, March 27, 2015, 10:03 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | Helium pressure test on TM4 HS line at CS |
The helium pressure test on TM4 HS line at conditioning station is done. No leak. I also leak checked all vacuum seals on TM4 service cap. They are all good. |
Attachment 1: 001.JPG
|
|
Attachment 2: 005.JPG
|
|
Attachment 3: 006.JPG
|
|
876
|
Friday, March 27, 2015, 11:29 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 is connected at CS |
TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been installed onto the TM4 service cap.The CS water system is started. All water signals are good so far. Anders will start HV and heaters conditioning on next Monday. |
Attachment 1: 010.JPG
|
|
Attachment 2: 013.JPG
|
|
Attachment 3: 012.JPG
|
|
877
|
Monday, March 30, 2015, 07:38 |
David Wang | ITE | Standard Operation | TM4 | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update |
Updated schedule this morning after last Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time weekly update. |
Attachment 1: Target_Hall_shut_down_activities.pdf
|
|
Attachment 2: Target_Hall_shut_down_activities.mpp
|
Attachment 3: Target_Hall_shut_down_activities.pdf
|
|
Attachment 4: Target_Hall_shut_down_activities.mpp
|
880
|
Wednesday, April 01, 2015, 06:56 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#45 | TM4 has been disconnected at CS. |
TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday. |
882
|
Wednesday, April 01, 2015, 13:08 |
David Wang | ITE | Standard Operation | TM4 | | Replaced ITE tank to module 42X0.275 o-ring |
I replaced ITE tank to module 42 ID X 0.275 o-ring. The o-ring is changed once a year before the first beam time. The flanges was cleaned and the new o-ring was installed. It works fine. |
Attachment 1: 001.JPG
|
|
Attachment 2: 002.JPG
|
|
Attachment 3: 004.JPG
|
|
Attachment 4: 005.JPG
|
|
Attachment 5: 006.JPG
|
|