Thursday, January 08, 2015, 08:04, David Wang, ITE, Standard Operation, TM4, , TM4 water lines have been disconnected in ITE and purged.
Friday, February 06, 2015, 08:06, David Wang, Crane, Repair, , , TH crane lost movement controls since last Friday.
Friday, February 06, 2015, 12:27, David Wang, Crane, Repair, , , TH crane troubleshoot
Thursday, February 12, 2015, 09:11, David Wang, Crane, Repair, TM4, , TH crane troubleshoot and annual inspection.
Monday, February 16, 2015, 11:57, David Wang, Crane, Repair, , , TH crane
Monday, February 23, 2015, 12:28, David Wang, ITE, Maintenance, , , 2015 shut down coils and pedal wheels replacement on ITE water flow sensors.
Wednesday, February 25, 2015, 10:44, David Wang, ITW, Maintenance, , , 2015 shut dwon ITW water sensor coils and pedal wheels replacement
Thursday, February 26, 2015, 09:22, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Mar 25th
Monday, March 02, 2015, 10:52, David Wang, ITE, Maintenance, TM4, UCx, ITE primary and secondary vacuum vessels leak check.
Thursday, March 05, 2015, 06:44, David Wang, ITE, Maintenance, TM4, , 5 Shielding blocks have been moved to ITE.
Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update
6x
Thursday, March 12, 2015, 13:04, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITE to ITW.
Monday, March 23, 2015, 07:56, David Wang, ITE, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update
Wednesday, March 25, 2015, 14:25, David Wang, South Hot-Cell, Standard Operation, TM4, Ta#45, Leak check on TM4 HS water line with new Ta#45 target. at SHC
Wednesday, March 25, 2015, 14:34, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 and CS turbo- pumps are started .
Friday, March 27, 2015, 10:03, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, Helium pressure test on TM4 HS line at CS
Friday, March 27, 2015, 11:29, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 is connected at CS
Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update
Wednesday, April 01, 2015, 06:56, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 has been disconnected at CS.
Wednesday, April 01, 2015, 13:08, David Wang, ITE, Standard Operation, TM4, , Replaced ITE tank to module 42X0.275 o-ring