Entry  Friday, April 26, 2013, 14:31, chad fisher, South Hot-Cell, Repair, TM3, , TM3 refurb E.O.D. IMG_1039.JPG
Service tray side of the waterblock jig is installed and all locking tabs enagaed save the heat shield circuit. Locking tab for heat shield circuit with
be worked on Monday morning and installation of the source tray side of the waterblock jig should commence on monday as well.
Entry  Monday, April 29, 2013, 15:58, Bevan Moss, South Hot-Cell, Repair, TM3, , Source Tray Removal 20130429_TM3_SOURCE_TRAY_REMOVAL_IMG_0620.JPG
Chad removed the source tray from TM3  today, see attached picture (video was also taken). There was some interference between the window cooling
lines and the frame work as well as the clamps for the ground electrode and the water block alignment jig. There was also interference between the optics
alignment post (specifically the mushroom top) and the water block alignment jig. Investigation into these inferences needs to be completed as they could
Entry  Tuesday, April 30, 2013, 07:47, chad fisher, South Hot-Cell, Repair, TM3, , TM3 Source Tray Removal IMG_1043[1].JPG
The source tray has sucessfully been removed from TM3.
I will put a report in the TM3 rev 3 docushare directory as there were some items of note during this procedure.
Entry  Tuesday, April 30, 2013, 07:51, chad fisher, South Hot-Cell, Repair, TM3, , Coil line flow check 
David and I checked circuits p and q (the water cooled coil ciruit) for flow this morning as, with the source tray still in the module, there was both
a leak and a leak tight blockage. Both p and q allowed air flow through them confirming that the blockage was in the surce tray side of the system.
The heat shield circuit was also tested for flow and it passed.
Entry  Thursday, May 02, 2013, 10:09, chad fisher, South Hot-Cell, Repair, TM3, , Service tray water block leak check 
David and I preformed a helium leak check on the service tray waterblocks and verify that no damage had been done during jig installation. All 14 circuits
were checked and verified to be ok except circuit E and circuit I which were unstable when helium was applied. The resonse time on E and I would suggest
that it is an issue with the bungs that were used and not the braze joint however.
Entry  Friday, May 03, 2013, 09:53, chad fisher, South Hot-Cell, Repair, TM3, , 9 pin connector wiring IMG_1047[1].JPGIMG_1048[1].JPGIMG_1050[1].JPG
With the aid of nic new manipulator snap fingers made by Maico the peek cable ties restraining the 9 pin connector wiring to the gas lines have been
cut.
Entry  Monday, May 06, 2013, 15:45, Bevan Moss, Conditioning Station, Repair, TM3, , 55 pin connector removed 20130506_55_pin_conector_removal_IMG_3530.JPG20130506_55_pin_conector_removal_IMG_3525.JPG20130506_55_pin_conector_removal_IMG_3532.JPG20130506_55_pin_conector_removal_IMG_3535.JPG
Travis and I removed the 55 pin connector from the service cap today. The feed through was left in place as a new design for the replacement has yet
to be designed. It was not possible to test if the cables could be pulled easily as I believe there is still 1 cable tie in the containment box. The wires
were cut flush with the top of the copper tube in case Chad cannot remove them via the hot cell. Other items removed include several cable ties and a clamp
Entry  Tuesday, May 07, 2013, 12:07, David Wang, ITW, Standard Operation, TM1, , I moved 5 shielding blocks from ITE to ITW. 
Water interlock check  on ITW is done. All water signals are strong on EL panel.  ITW is configured to take proton beam.
Entry  Wednesday, May 08, 2013, 10:12, chad fisher, South Hot-Cell, Repair, TM3, , TM3 9 pin wiring removal IMG_1055[1].JPG
The 9 pin wiring has successfully been removed from TM3.
Entry  Wednesday, May 08, 2013, 13:48, chad fisher, South Hot-Cell, Repair, TM3, , IMG wiring check 
Checks of the wiring for the IMG are complete and have passed.
Entry  Thursday, May 09, 2013, 10:13, chad fisher, South Hot-Cell, Development, , , Mock-up Progress IMG_1056[1].JPGIMG_1057[1].JPGIMG_1058[1].JPG
The source tray for the mock-up has been setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the photos for the TM3 rebuild that took place in the anteroom in 09' and Maico and Dan for the support in ironing
the issues with the source tray side soldering issues.
Entry  Thursday, May 09, 2013, 14:23, chad fisher, South Hot-Cell, Repair, TM3, , Water Block Jig Removal IMG_1059[1].JPG
The source tray side of the water block jig has been removed in preparation for moving the module to the  conditioning station for electrical tests.
Entry  Friday, May 10, 2013, 09:26, chad fisher, South Hot-Cell, Repair, TM3, , Containment box reinstalled IMG_1062[1].JPGIMG_1063[1].JPG
the containment box has been reinstalled onto TM3. After electrical checks it is ready to move to the conditioning station...for electrical tests.
Entry  Wednesday, May 15, 2013, 10:00, David Wang, ITE, Standard Operation, TM4, , Disconnected TM4 in ITE. 
HS had been purged. The ITE is under venting. The TM4 will be moved to SH on next Tuesday which is May 21th.
Entry  Wednesday, May 15, 2013, 10:20, Bevan Moss, Conditioning Station, Repair, , , Roof top chiller failed 
I have been getting a fault on the roof top chiller for the 2 tandem 7.5  ton chillers. I have checked and we have water flow and the temperatures  are
nowhere near freezing. I believe they are over heating as the fans  on that side are not coming on. The blades are free to turn by hand but  the VFD controller
keeps saying off. I have tried turning it on and off  and that also did nothing. I have contacted ESC for further advice.
Entry  Wednesday, May 15, 2013, 10:25, Bevan Moss, Conditioning Station, Repair, , , ONICON flow meter 
 Scott Adair from Riada sales came to site to complete diagnostics on the ONICON flow meter. He could not determine the problem and believes that
there was a short in the head. He has taken the flow meter for what should be warranty repair. The flow meter is for diagnostics only, the conditioning
station can still operate without it.
Entry  Wednesday, May 15, 2013, 16:21, Bevan Moss, Conditioning Station, Repair, , , BIAS Current readings off by a factor of 5 
 A special thanks to Kazuya, Jane and Ray who jumped on this issue right  away! The limit of the BIAS PS was set as 20000uA when in reality it is
4000uA. The issue has  now been corrected. Please remember to divide the current by 5 for any elogs older than this one.
Entry  Wednesday, May 15, 2013, 17:32, Bevan Moss, Conditioning Station, Standard Operation, TM3, , TM3 in place but not connected 15052013_TM3_in_place_but_not_connected.xlsx
 To confirm that the sparking was coming from the module rather than the conditioning station TM3 was grounded and the conditioning station biased.
Attached are the results. Highlights include that there was no sparking and the station was able to achieve 60kV (limited by controls from going higher).
The current from the raw file has been corrected by the required factor of 5.
Entry  Friday, May 17, 2013, 10:04, chad fisher, South Hot-Cell, Repair, , , Manipulator Repair 
Manipulator has been sucessfully repaired. Recieved 0.19 mSv. Took Approx. 10-20 minutes
Entry  Friday, May 17, 2013, 12:02, Travis Cave, Conditioning Station, Standard Operation, TM3, , module move 
TM#3 with no target or source trays has been moved from the conditioning station to the NE silo.