  1733   Friday, June 08, 2018, 11:36 chad fisherSouth Hot-CellRepairTM2 TM2 Source Tray Removal Progress

The containment box has been removed from TM2, the Enzel lens and steerers disconnected and optics tray removal has commenced.

Attachment 1: TM2_06082018.jpg
TM2_06082018.jpg
  1734   Friday, June 08, 2018, 14:24 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move

 TM#2 has been moved from the conditioning station to the south hot cell.

  1735   Monday, June 11, 2018, 11:30 chad fisherSouth Hot-CellRepairTM2 TM2 containment box on

Tm2 containment box has been re-installed onto TM2.

  1736   Tuesday, June 12, 2018, 11:26 chad fisherSouth Hot-CellRepairTM2 TM4 Optics Tray

I have "slung" the TM4 optics tray in preparation for its removal.

Attachment 1: fh.jpg
fh.jpg
  1743   Wednesday, June 27, 2018, 14:56 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule move

 TM2 has been moved from the silo to the south hot cell.

  1745   Friday, June 29, 2018, 10:15 chad fisherSouth Hot-CellStandard OperationTM2 TM2 work and target install

On Thursday, June 29th the containment box of TM2 was removed and the optics tray re-installed and reconnected. The box was then re-installed.

Friday the window waterlines were leak checked, Nb target installed (with new fasteners, high current torqued to 130 in*lbs) target leak and electrical checked and containment box cover installed with new fasteners.

  1747   Friday, June 29, 2018, 13:36 Travis CaveSouth Hot-CellStandard OperationTM2Nb#8Electrical Check

 The results of the various electrical checks performed on the TM#2 with and without the Nb#8 target attached.

Attachment 1: TM2_elec_chk_steerers_and_lens_062818.pdf
TM2_elec_chk_steerers_and_lens_062818.pdf
Attachment 2: TM2_Nb8_elec_chk_shc.pdf
TM2_Nb8_elec_chk_shc.pdf
Attachment 3: TM2_notgt_elec_chk_shc_062918.pdf
TM2_notgt_elec_chk_shc_062918.pdf
  1748   Tuesday, July 03, 2018, 09:57 Travis CaveITWStandard OperationTM2Nb#8Module move

 TM#2 with Nb#8 has been moved from the south hot cell to the west target station.

  1750   Tuesday, July 03, 2018, 14:42 David WangITWStandard OperationTM2Nb#8TM2 has been connected to ITW.

TM2 has been connected to ITW. All turbo pumps are started. See attachment for connection checklist.

Attachment 1: Nb#4_Module_connection_checklist.pdf
Nb#4_Module_connection_checklist.pdf Nb#4_Module_connection_checklist.pdf Nb#4_Module_connection_checklist.pdf
  1751   Wednesday, July 11, 2018, 15:06 Anders MjosITWStandard OperationTM2Nb#8Block move

Maico and Travis moved blocks from ITE to ITW yesterday

  1752   Wednesday, July 11, 2018, 15:09 Anders MjosITWMaintenanceTM2Nb#8Uncovered ITW to toubleshoot 2A2M19

The 2A2M19 beam profile monitor did not work and was e-faulted. After initial troubleshooting 2 blocks were removed form ITW to inspect the entrance module where the beam monitor is installed. The cable was found not to be connected and was quickly fixed. Blocks reinstalled. The work was done by Maico, Travis and Anders

  1758   Wednesday, July 25, 2018, 13:21 Anders MjosITWRepairTM2Nb#8Leak check of ITW

ITW Entrance Module was leak checked yesterday with the support of Vacuum Group (Dimo & Edi). The leak detector was connected to primary backing vacuum line. A leak response was found near the bellow for the beam profile monitor on top of the Entrance Module. It could be confirmed today by actuating the monitor, that the leak was indeed at that location. The plan is to move the TM and Entrance Module out for target exchange and repair, respectively. Drawings of the device available on ITA0200and ITA5128

Attachment 1: Entrance_Module_Leak_2018-07-25.docx
  1759   Tuesday, July 31, 2018, 10:20 Travis CaveSouth Hot-CellStandard OperationTM2Nb#8Module move

 TM#2 with Nb#8 has been moved from ITW to the south hot cell.

  1762   Wednesday, August 01, 2018, 14:48 Travis CaveConditioning StationStandard OperationTM2UC#23Spent Target Move

 TM#2 with UC#23 has been moved from the south hot cell to the conditioning station.

  1763   Wednesday, August 01, 2018, 15:12 Anders MjosSouth Hot-CellStandard OperationTM2UC#23Target mounted - water leak on HS line

The heat shield water lines were not purged ahead of target exchange in the hot cell. This resulted in water leaking onto the new target assembly (heat shield) when the cooling lines were opened at top and bottom (for connecting leak detector). Excess water was wiped up with paper towels.

Attachment 1: 20180801_180130904_iOS.jpg
20180801_180130904_iOS.jpg
  1767   Tuesday, August 14, 2018, 10:27 Travis CaveITWStandard OperationTM2UC#23Module move

 Both the West Entrance and TM#2 with UC#23 have been moved back into their places in the west target station. The Entrance module move wasn't completely smooth as it did suffer a little bumpiness when the shield plug part was installed, I was lifted back out again and no visible damage was observed on the delicate items.

  1768   Monday, August 20, 2018, 09:55 Travis CaveSouth Hot-CellStandard OperationTM2Ta#56 and UC#23Electrical Check

 Electrical Checks of the last two targets Ta#56 and UC#23

Attachment 1: Electrical_Check_TM4_Ta56_SHC.pdf
Electrical_Check_TM4_Ta56_SHC.pdf
Attachment 2: Electrical_Check_TM2_UC23_CS.pdf
Electrical_Check_TM2_UC23_CS.pdf
Attachment 3: Electrical_Check_TM2_UC23_SHC.pdf
Electrical_Check_TM2_UC23_SHC.pdf
  1784   Tuesday, September 18, 2018, 12:59 Travis CaveSouth Hot-CellStandard OperationTM2UC#23Module move

 TM#2 with UC#23 has been moved from ITW to the south hot cell. The shield plug was also installed remotely as well.

  1785   Thursday, September 20, 2018, 08:36 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Check

 Results of the electrical check on TM#2 with no target after Chad cleaned out the bolt hole on the module where the target mounts.

Attachment 1: Electrical_Chk_TM2_no_tgt_Sept-20-2018.pdf
Electrical_Chk_TM2_no_tgt_Sept-20-2018.pdf
  1786   Thursday, September 20, 2018, 14:35 Travis CaveSouth Hot-CellStandard OperationTM2nSiC#1Electrical Check

 TM#2 with the nSiC#1 target had its check done on it at the south hot cell see attached for results.

Attachment 1: Electrical_Chk_TM2_SHC_nSiC#1_Sept-20-2018.pdf
Electrical_Chk_TM2_SHC_nSiC#1_Sept-20-2018.pdf